Day 196 – Thursday 4th May 2017 – LAST DAY of work on phase 2

Day 196 – Thursday 4th May 2017  – LAST DAY of work on phase 2

Workmen finished today on Springdale after 196 days of men on site.  Work has been on going since June 26th 2016.  Plumber – Marcus Kelly and his mate Josh completed their work on the upstairs bathroom and radiators in the sunroom, bedroom and study.  Their work looks first class.  Springdale is now a totally different place to the house we bought over 2 years ago.

Internal work is still to be completed, but this will be on going for some time.

Pictures of the upstairs bathroom work can be seen below.

View of shower area and towel radiator

View of shower area and towel radiator

Bathroom all finished

Upstairs Bathroom all finished

view to bathroom window

view to bathroom window

New toilet and wash basin

New toilet and wash basin

View of shower, reflection of window in showerboard

View of shower, reflection of window in showerboard

Radiator towel rail in new upstairs bathroom

Radiator towel rail in new upstairs bathroom

Bathroom all finished - view of new shower, showerboards and screen

Bathroom all finished – view of new shower, showerboards and screen

Day 195 – Wednesday 3rd May 2017 – phase 2

Day 195 – Wednesday 3rd May 2017 – phase 2

Work on the upstairs bathroom continues.

Wash basin installed

Wash basin installed

Wash basin installed - view towards the window

Wash basin installed – view towards the window

skirting board around shower base painted and glossed

skirting board around shower base painted and glossed

skirting board around shower base painted and glossed pic 2

skirting board around shower base painted and glossed pic 2

radiator in bedroom beneath front window

radiator in upstairs bedroom beneath front window

radiator in bedroom beneath dormer window

radiator in bedroom beneath dormer window

radiator in study beneath the velux window

radiator in study beneath the velux window

 

Day 166 -Wednesday 1st March 2017 – phase 2

Day 166 -Wednesday 1st March 2017 – phase 2

view-of-springdale-progress-so-far-boarded-up-porch-ready-for-demolition-of-the-inside-wall

View of Springdale from the front with boarded up old porch now ready for demolition of wall inside

springdale-on-the-first-of-march-2017

Springdale-on-the-first-of-March-2017

old-porch-wall-inside-ready-for-demolition

old-porch-wall-inside-ready-for-demolition

old-radiators-from-hallway

old-radiators-from-hallway

old-porch-boarded-up

old-porch-boarded-up inside

front-of-house-boarded-up-ready-for-demolition-of-wall-inside

front-of-house-boarded-up-ready-for-demolition-of-wall-inside                              View from the outside

 

looking-down-from-scaffolding-to-boarded-up-front

looking-down-from-scaffolding-to-boarded-up-front

dormer-lead-around-window

dormer-lead-around-window

dormer-sides-lined-with-lead

dormer-sides-lined-with-lead

rendering-applied-today-as-seen-throught-the-scaffolding

rendering-applied-today-as-seen-throught-the-scaffolding

rendering-as-seen-from-second-level-of-the-scaffolding-looks-perfect

rendering-as-seen-from-second-level-of-the-scaffolding-looks-perfect

rendering-as-seen-from-second-level-of-the-scaffolding-pic-3

rendering-as-seen-from-second-level-of-the-scaffolding-pic-3

rendering-pic-4

rendering-pic-4

view-of-bedroom-and-dormer-more-plastering-completed-today

view-of-bedroom-and-dormer-more-plastering-completed-today

view-of-2-bedrrom-windows-and-new-plastering

view-of-2-bedroom-windows-and-new-plastering

wall-channelled-out-for-plug-sockets

wall-channelled-out-for-plug-sockets

entrance-to-study

entrance-to-study

waste-pipe-connected-to-downpipe-which-has-been-connected-to-the-house-drains

new waste-pipe-installed and connected-to-new downpipe-which-has-been-connected-to-the-house-drains

waste-downpipe-connected-to-vent-with-birds-nest-top

waste-downpipe-connected-to-vent-with-birds-nest-top

shower-waste-and-wash-hand-basin-waste-water-pipe-in-white-connected-to-the-waste-pipe-under-the-guttering

shower-waste-and-wash-hand-basin-waste-water-pipe-in-white-connected-to-the-waste-pipe-under-the-guttering

waste-pipe-from-new-upstairs-toilet-not-yet-put-in

waste pipe from new upstairs toilet as yet not installed

white-waste-pipe-coming-from-right-to-left-join-waste-pipe-from-shower-and-then-flows-through-to-main-waste-pipe-outside

white-waste-pipe-coming-from-right-to-left-join-waste-pipe-from-shower-and-then-flows-through-to-main-waste-pipe-outside

plumbing-pipes-under-old-ceiling-in-the-old-porch-middle-pipe-is-cold-water-supply-to-upstairs-toilet-right-beam-hot-and-cold-supply-of-water-to-the-wash-basin-short-pipe-radiator-pipe-to-bedr

Plumbing pipes under old ceiling of the old porch. Middle pipe is the cold water supply to the upstairs toilet. Right of the beam is the hot and cold supply of water to the wash basin. Short pipe is the radiator pipe to the bedroom.

Day 165 – Tuesday 28th February 2017 – phase 2

Day 165 – Tuesday 28th February 2017 – phase 2

old-front-and-porch-at-the-beginning-of-tuesday-28th-february-steel-beam-in-place

old-front-and-porch-at-the-beginning-of-tuesday-28th-february-steel-beam-in-place

old-front-and-porch-at-the-end-of-tuesday-28th-february-scratch-coat-applied-over-beam

old-front-and-porch-at-the-end-of-tuesday-28th-february-scratch-coat-applied-over-beam

dormer-from-the-outside-progress-so-far

dormer-from-the-outside-progress-so-far

doorway-with-frame-in-place-skimmed-with-plaster

bedroom doorway-with-frame-in-place-skimmed-with-plaster

plastering-continues-upstairs-in-the-new-bedroom-view-over-to-staircase-through-lefthand-doorway-and-to-ensuite-through-right-hand-doorway

plastering-continues-upstairs-in-the-new-bedroom-view-over-to-staircase-through-left hand-doorway-and-to-ensuite-through-right-hand-doorway

view-across-to-dormer-side-of-bedroom-and-plastering-on-this-side-of-bedroom-and-around-beam

view-across-to-dormer-side-of-bedroom-and-plastering-on-this-side-of-bedroom-and-around-beam

top-and-bottom-of-small-window-upstairs-skimmed-with-plaster

top-and-bottom-of-small-window-upstairs-skimmed-with-plaster

window-sill-and-around-windows-skimmed-with-plaster

window-sill-and-around-windows-skimmed-with-plaster

view-through-to-old-hall-from-new-upstairs-study-this-is-where-a-new-cupboard-will-be-built-over-the-new-staircase

view-through-to-old-hall-from-new-upstairs-study-this-is-where-a-new-cupboard-will-be-built-over-the-new-staircase

view-from-scaffolding-of-windows-which-have-now-been-prepared-for-rendering

view-from-scaffolding-of-windows-which-have-now-been-prepared-for-rendering

upstairs-bedroom-windows-being-prepared-for-rendering-mesh-installed-around-sides

upstairs-bedroom-windows-being-prepared-for-rendering-mesh-installed-around-sides

toilet-waste-pipe-in-place-in-ensuite-with-water-supply-pipe-at-the-side

toilet-waste-pipe-in-place-in-ensuite-with-water-supply-pipe-at-the-side

toilet-waste-pipe-in-place-in-ensuite

toilet-waste-pipe-in-place-in-ensuite

toilet-waste-pipe-now-in-position-through-the-back-of-the-eaves-to-the-outside

toilet-waste-pipe-now-in-position-through-the-back-of-the-eaves-to-the-outside

waste-pipe-from-toilet-just-visible-coming-to-the-outside-of-the-house

waste-pipe-from-toilet-just-visible-coming-to-the-outside-of-the-house

waste-pipe-for-wash-hand-basin-in-ceiling-at-the-edge-of-the-old-hall

waste-pipe-for-wash-hand-basin-in-ceiling-at-the-edge-of-the-old-hall. A white pipe which joins up with the waste water from the shower. This will join the outside waste pipe outside the house on the side

waste-water-pipe-for-shower

waste-water-pipe-for-shower

waste-pipe-for-wash-hand-basin-in-ensuite-with-water-supply-pipe-holes-behind

waste-pipe-for-wash-hand-basin-in-ensuite-with-water-supply-pipe-holes-behind

waste-water-pipe-for-wash-basin

waste-water-pipe-for-wash-basin

waste-water-pipe-to-outside-from-shower-to-be-joined-to-main-waste-pipe

waste-water-pipe-to-outside-from-shower-to-be-joined-to-main-waste-pipe

pipes-for-hot-and-cold-water-going-through-into-old-porch-ceiling-and-up-to-the-new-upstairs

pipes-for-hot-and-cold-water-going-through-into-old-porch-ceiling-and-up-to-the-new-upstairs

hot-and-cold-water-pipes-to-upstairs-in-ceiling-of-old-hall-thinner-pipes-are-radiator-pipes

hot-and-cold-water-pipes-to-upstairs-in-ceiling-of-old-hall-thinner-pipes-are-radiator-pipes

hot-and-cold-water-pipes-and-radiator-pipes-for-upstairs

hot-and-cold-water-pipes-and-radiator-pipes-for-upstairs

plasterboarding-at-the-side-of-the-dormer

plaster boarding-at-the-side-of-the-dormer