BUILDING WORK – PHASE 2
Days – 196 (actual workmen days since phase 1 began with kitchen build in June 2016) see Building Work for Kitchen Build
Sunday 8th January 2017 – Thursday 4th May 2017 – Phase 2
Lots of preparation for the start of the new extension. We applied for planning permission and are now creating an upstairs area to the house. This will become a master bedroom and ensuite bathroom and a small study. Downstairs in the large hallway which we have used as a sitting room, we would like a sun and TV room.

How it looked over Christmas

Before phase 2

present opening mess!

Hall as sitting room

removing-carpets-in-preparation-for-an-upstairs-master-bedroom

removing-carpets-in-preparation-for-an-upstairs-master-bedroom picture 2

clearing-the-balcony-ready-for-its-removal

underlay-removal
Day 126 – Monday 9th January 2017 – phase 2

Cleared Hallway And Balcony – Ready For A New Upstairs

Balcony – ready for removal

Balustrade on balcony overlooking hall

view-of-hall-from-balcony

hallway-ready-for-new-upstairs-extension
Day 127 -Tuesday 10th January 2017 – Phase 2

view-of-balcony

balcony-balustrade-removed

balcony-railings-removed

balcony-removed-half-a-beam-left

wood-from-balcony

ceiling-removed-from-old-vaulted-hallway-pic 2

ceiling-removed-from-old-vaulted-hallway-pic 3

ceiling-removed-from-old-vaulted-hallway

current-front-of-house-day-127

outside-rubble

phase-2-curtains-up-for-demolition-of-front-hall-and-balcony-to-create-a-master-bedroom-and-ensuite-and-an-upstairs-study

remaining-beams-from-old-ceiling-in-hallway

scaffolding-for-beam-removal

rubble-from-hall-ceiling
Day 128 – Wednesday 11th January 2017 – Phase 2

Picture of before the old beams from the vaulted structure were removed

After the beams were removed from old vaulted structure the roof laths can be seen

New beams going in for the master bedroom

beams-removed-pic-2

Large hall and attic space

new-beams-going-into-place-for-bedroom-rectangular-gap-at-middle-back-of-pic-is-where-the-stairs-will-be-located

bedroom-beams-all-going-into-place

another-view-of-bedroom-beams

scaffolding-in-large-hall-and-cutting-equipment-for-new-beams-for-bedroom

wood-being-stored-inside-bad-weather-forecast-gap-for-staircase-at-top-of-picture

marcus-plumber-going-under-floor-in-hall-re-routing-water-pipes-under-house-pipes-were-in-attic

Marcus-plumber-going-under-floor-in-hall-re-routing-water-pipes-under-house
Day 129 – Thursday 12th January 2017 – Phase 2
Day 3 only for phase 2, the building of the master bedroom, ensuite and small study.
Progress has been very quick in 3 days. The balcony and huge vaulted ceiling has been removed, new beams for bedroom floor are in place and gap left for a staircase. Partitioning has started today.

front-of-house-12-1-17 for reference!

front-of-house-12-1-17

old-chandelier

cutting-machinery-for-beams-and-partition-walls

work-above-the-new-beams

view-of-new-upstairs

view-of-the-work-completed-today-at-new-bedroom-floor-level

partition-wall-has-been-partially-completed-on-the-right-this-will-be-the-supporting-beam-for-new-roof

view-down-to-the-hall-below

inspection-going-on

walking-the-plank

ladders-to-this-level-this-is-where-the-stairs-will-come-up-also-view-of-work-and-new-beams
Day 130 – Friday 13th January 2017 – phase 2

Scaffolding arrived for phase 2

Scaffolding truck

scaffolding-through-the-blinds-in-sitting-room

The Front Of Springdale -Scaffolding-going-up-around-the-front-and-sides

Scaffolding around house – View from front garden

scaffolding

scaffolding-at-the-side

scaffolding-at-the-right-hand-side

side-scaffolding

scaffolding-from-outside-along-left-side-of-house

scaffolding-at-right-side-and-satellite-dish

balcony-window-from-outside-not-in-great-condition

balcony-window-from-outside-not-in-great-condition-and-tiles-in-poor-state

bottom-scaffolding

chimney-to-be-removed

top-scaffolding-view-towards-fields-over-the-top-of-the-house

top-scaffolding-view-towards-fields-showing-chimney-that-is-to-be-removed

view-from-scaffolding-corner-potential-view

view-from-scaffolding

view-from-top-scaffolding

view-from-top-scaffolding-over-small-garage

the-beginning-of-the-new-bedroom

rockwool-insulation-in-new-master-bedroom-extension

old-chandelier-from-hall-and-old-water-tank-from-attic
Day 131 -Monday 16th January 2017 – phase 2
Small steel beams arrived and preparation for insertion, also blocks for gable delivered

Blocks in place ready for start of gable

bedroom-area

attic-area-cleared-out

area-where-study-will-be
Day 132 -Tuesday 17th January 2017 – phase 2
Tile removal on both sides of the house and middle parts, supervised by the bat licenced ecologists as we have a potential for bats. On an earlier survey we were told we must have a bat licence as we have potential for bats in our roof space. No bats or evidence of bats was found. Electrician also at work today in the roof space, sorting out wiring, a major task.

tile removal today under the supervision of the bat licenced ecologists

roof-tiles-being-removed-one-by-one-and-inspected-for-bats-by-a-bat-licenced-ecologist-as-per-our-planning-permission

bat-licenced-ecologist-inspect-tiles-as-they-are-removed-as-per-our-planning-permission-states-as-we-have-potential-for transitionary bats

tiles-removed

tiles-stripped-back

tiles-stripped-back-pic-2

rotten-wooden-beam-removed

small-supporting-beams-in-place-across-porch

view-of-supporting-beams-from-right-side-of-house

left-side-of-house-17-1-17 protected from weather until canopy goes on

left-side-of-roof –  Lots of cluster flies found under the tiles, already found hundreds in the attic. No bats found or evidence of bats

rockwool-insulation-in-partition-wall

wiring-by-electrician-to-be-sorted-out-many-wires-are-now-defunct

extent-of-bedroom-to-be-and-partition-wall
Day 133 – Wednesday 18th January 2017 – phase 2

progress-after-day-133-new-wall-going-up-over-new-supporting-beam-at-front-of-house

front-of-house-so-far-with-new-wall

new-wall-over-new-supporting-beam-over-old-porch-roof

another-view-of-new-wall-over-old-porch

new-supporting-beam-as-seen-from-right-side-of-scaffolding

new-wall-over-right-side-of-house-front

left-side-of-house-from-scaffolding-showing-new-wall-going-up-over-the-front-of-the-house-on-the-new-support-beam

left-side-where-tiles-were-removed-yesterday-for-insertion-of-the-large-supporting-steel-next-week

area-of-roof-where-tiles-were-removed-yesterday-with-bat-ecologists-this-is-where-a-huge-steel-beam-will-be-inserted-into-the-house-for-the-support-of-the-roof-and-the-new-wall-will-be-built-on-top

right-side-of-house-roof

top-of-old-balcony-window-just-visible-from-scaffolding

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area-pic-2

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area-pic-3
Day 134 – Thursday 19th January 2017 – phase 2

progress-on-day-134-formation-of-upstairs-windows

progress-on-day-134-formation-of-upstairs-windows-pic-2

side-view-of-new-upstairs

opening-for-middle-window

view-looking-down-from-top-scaffolding-onto-old-balcony-window

view-looking-down-from-top-scaffolding-onto-old-balcony-window-also-showing-areas-of-roof-that-have-been-prepared-for-new-steel-beam

view-from-the-right-hand-side-of-house-steel-beams-in-brown-now-at-the-bottom-of-the-wall

view-of-the-new-wall-from-the-left-side-of-the-scaffolding

view-of-right-hand-side-of-roof

view-of-double-wall-built-on-top-of-new-steel-beam-at-the-front-of-the-house-and-pitched-roof-covered-to-protect-from-the-weather-roof-felt-is-in-poor-condition-probably-the-original-roofing-felt

view-from-the-right-hand-side-of-house-showing-double-wall-and-exposed-roof-covered

left-hand-side-of-roof
Day 135 and 136 – Friday 20th January and Saturday 21st January 2017 – phase 2

men-at-work-day-135

centre-window

new-concrete-window-sill

progress-day-135

small-beam-over-new-window-opening

view-from-left-hand-side

view-of-new-window-openings-and-small-steel-support-above-new-window

view-of-new-window-openings-from-right-hand-side

view-through-to-bedroom-from-scaffolding

view-of-new-window-openings-from-second-level-of-scaffolding

view-of-new-window-openings-from-scaffolding
Part of phase 1 being completed, the outside rendering of the new kitchen, Friday and Saturday

new-tyrolean-render-applied-today

new-tyrolean-render-applied-side-of-new-kitchen
Day 138 – Monday 23rd January 2017Â – phase 2
Chimney removal

To Begin the underside of the chimney Is supported to stop debris entering the old kitchen

Chimney

No Chimney

chimney-removed-view from-scaffolding

chimney-removed-view from-scaffolding-pic-2

chimney-removed-view from top of scaffolding-pic-3

daylight-from-the-hall-where-the-chimney-was

Area where chimney was, creating more space for upstairs bedroom and a dormer window

old-position-of-chimney

This area to be removed after big steels go in later in the week

into-the-new-bedroom. Staircase will be fitted here
Day 139 – Tuesday 24th January 2017 – phase 2
Electrician today alongside the builders preparing wiring that will be under the flooring.

upstairs-area-being-prepared-by-electrician-for-new-wiring-for-the-downstairs-hall-area-also-old-chimney-area-clearly-visible-in-the-sloping-roof-this-will-become-a-dormer-window

closer-view-of-holes-in-beams-drilled-for-wiring-also-closer-view-of-the-thick-beams

noggins-of-wood-screwed-in-between-beams-to-strengthen-the-floor-structure

view-of-the-opening-for-the-staircase-and-the-other-side-of-the-house-which-will-have-a-small-study

view-of-the-old-balcony-window-and-new-beams

thick-beams-in-place-over-new-downstairs-hall

flooring-delivered-and-ready-for-installation-in-the-new-upstairs

celotex-insulation-delivered-and-ready-to-install-in-new-upstairs
Day 140 – Wednesday 25th January 2017 – phase 2
Two large steel beams arrived today for craning into place tomorrow to support new roof for house and upstairs

truck-maneouvering-up-drive-with-2-large-half-a-ton-steel-beams

swinging-first-large-new-steel-beam-onto-grass

swinging-first-large-new-steel-beam-off-truck-onto-the-lawn

first-beam

first-large-new-roof-beam

first-beam-another-pic

beam-swinging-onto-lawn

beam-2

second-beam

second-steel-beam

two-beams-on-grass

In ceiling above the hall herring-bone-supports

herring-bone-supports-above-new-hall

flooring-stacked-up-and-gap-where-bedroom-wall-will-go

flooring-starting-to-go-down

flooring-to-edge-of-what-will-be-the-new-ensuite

edge-of-what-is-to-be-ensuite-bathroom
Day 141 – Thursday 26th January 2017 – phase 2
A very important day for the build – the huge new steel beams lifted into the correct position, more scaffolding going up, a 2 day job with 4 men to create a canopy right over the house, which will mean that work is not so weather dependent and the house will be more protected when the roof comes off. Also from phase 1, air vents over flat utility room roof going in, to try and allow air to flow and to stop build up of condensation.

High Ab Crane for lifting the Steel Beams

Pre-preparation of crane, house and roof, and the beams

Steels on the grass ready for lift onto roof and final position

Steel beams with slings

Supporting stand for crane

Steel beams showing their full size and length

Beams propped up ready for lift by crane

Builder now cutting into roof, where tiles have been removed previously, for beam to inserted onto a prepared strengthened area on an existing original wall of the house

Crane begins lift via radio control, operator in high viz jacket whilst the other builder controls the direction of the beam using an attached guide rope

Beam is lifted

direction still controlled by rope

beam rising

First beam going up

Beam going up pic 2

beam-going-up-3

Beam going up pic 4

Beam going up pic 5

Beam going up pic 6

Beam going up pic 7

Beam going up pic 8

manoeuvring beam

beam going into position

view of crane

Beam going up pic 9 – wrong angle – beam has to be readjusted

Steel beam has to be repositioned as scaffolding is preventing the beam from locating in its correct position in the roof

Beam being manoeuvred over scaffolding

Beam being manoeuvred

beam now at correct angle to be manoeuvred into position

close up

manoeuvring beam

manoeuvred-into-position-1

manoeuvred-into-position-2

manoeuvred-into-position-3

First beam in place

Pictures from scaffolding of the first beam in place – pic 2

first-beam-in-place-pic-3

first-beam-in-place-pic-4

beam 2 to go here

preparing-roof-for-beam-2

Second beam being craned in

second-beam-being-craned-in-pic-3

second-beam-being-craned-in-pic-4

second-beam-being-craned-in

second-beam-being-craned-in-pic-5

second-beam-going-into-position

second beam in position

different view of beam 2

Two new steel beams in place under new scaffolding

two-new-steel-beams-in-place-pic-3

two-new-steel-beams-in-place-pic-2

steel-beam-number-2-in-position

steel-beam-number-2-in-position-pic-2
More scaffolding going up to create a canopy over house

scaffolding  arrives

scaffolders-move-truck-to-driveway -2-days-construction-ahead

scaffold unloading

unloading scaffolding

scaffolders-and-one-ton-water-containers-to-hold-scaffolding-and-canopy-securely

next-phase-of-scaffolding-with-water-container-1-ton-weights

new-scaffolding-going-up-to-cover-house

new-scaffolding-going-up-to-cover-house-pic-3

new-scaffolding-going-up-to-cover-house-pic-2

water-containers-to-act-as-weights-to-keep-canopy-and-scaffolding-secure

Phase 1 the fibre-glass-roof-and-new-condensation-vents-to try to eliminate damp patches on utility ceiling

fibre-glass-roof-and-new-condensation-vents

Phase 1 pointing-on-roof-tiles-over-new-kitchen

view-of-new-kitchen-roof-in-red-beyond-scaffolding

steel-beam-number-1-from-inside-house-pic-2

steel-beam-number-1-from-inside-house
Day 142 – Friday 27th January 2017 – phase 2
A full day of completing the scaffolding and canopy over the house

canopy-beginning-to-go-over-house

canopy-from-the-right

canopy-from-the-front

canopy-completed-showing-left-side-of-house-and-the-water-containers-which-hold-scaffolding-in-place

beams-and-new-window-gaps-under-the-canopy-window-fitter-came-out-and-measured-these-gaps-for-windows-today

beams-under-canopy-and-another-pic

beams-under-canopy-another-pic

inside-canopy-on-scaffolding-left-side-of-house

two-beams-now-under-canopy

view-down-to-garages-below-and-skip
Day 143 – Saturday 28th January 2017 – phase 2
Split levels – ground floor and new upstairs visible together

picure-showing-opening-for-the-staircase-the-floor-below-and-the-upstairs-area-expanding

new-upstairs-area-around-where-the-top-of-the-staircase-will-be

this-is-the-old-balcony-window-still-intact-at-present-with-gap-to-hall-below-just-in-front-through-the-window-the-small-steel-can-be-seen-straddling-the-porch-to-form-the-new-front-of-the-house

photo-through-gap-in-the-new-flooring-showing-the-inner-porch-door-below

steel-beam-number-1-showing-it-on-the-inside-of-house-from-upstairs-area

view-from-the-orchard-field-down-over-the-the-house-where-the-canopy-can-be-seen-over-the-top

view-of-back-of-house-new-kitchen-and-canopy-visible-over-the-top-of-main-house-pic-2

view-of-back-of-house-new-kitchen-and-canopy-visible-over-the-top-of-main-house

view-of-back-of-house-and-new-kitchen
Day 144 – Monday 30th January 2017 – phase 2

Opening up the roof

left-side-of-roof-opened-up

left-side-of-roof-new-beams-seen-just-inside

steel-beams-now-with-wood-inserts

steel-beams-now-with-wood-inserts-right-side-of-house

steel-beams-now-with-wood-inserts-right-side-of-house-pic-2

old-balcony-window-new-flooring-for-bedroom-on-the-other-side-of-the-window-can-be-seen
Day 145 – Tuesday 31st January 2017 – phase 2
Roof tiles all stripped off today under supervision from bat licensed ecologist. Balcony window taken out and flat roof taken off. From phase 1, worktop for new kitchen which had been measured and cut to size has now been fitted.

newly-fitted-worktop-for-kitchen-and-island-unit

New worktop fitted – a transformation

balcony-window-now-removed-view-through-to-new-bedroom-floor and through to hall below

left-side-of-house-tiles-stripped-under-supervision-of-a-bat-licensed-ecologist

left-and-front-stripped-of-tiles

right-side-of-house-tiles-all-stripped-off

view-of-stripped-roof-from-left

view-into-house-over-old-porch

view-of-what-will-be-new-bedroom-floor

view-through-gap-that-will-be-middle-window-in-the-bedroom

view-through-gap-which-will-be-new-ensuite-bathroom-window

top-of-roof-now-to-compare-later-when-new-roof-is-on

view-from-front-through-to-house-from-scaffolding-of-the-inside-where-the-old-balcony-has-been-removed

gap-from-below-seen-in-previous-pictures-as-light-shining-through-from-house

tiles-all-stacked-to-be-reused-for-new-roof

tiles-all-stacked-to-be-reused-for-new-roof-down-side-of-scaffolding
Day 146 – Wednesday 1st February 2017 – phase 2

glimpse-of-new-bedroom-through-gap-in-old-hall-ceiling-flooring-down

view-from-gap-in-flooring-to-bathroom-area

view-from-gap-in-flooring-to-bedroom-windows

view-from-right-across-floored-upstairs

view-through-middle-window-from-scaffolding-of-right-side-of-bathroom-and-study

view-from-scaffolding-through-middle-window-to-back-of-new-bedroom-and-covered-area-of-staircase

view-to-left-side-of-bedroom-and-flooring-base

left-side-of-bedroom-not-floored-yet-beams-down

view-through-to-left-side-of-bedroom

right-side-of-house

view-from-left-side-of-house-from-scaffolding

rubble-and-remnants-of-old-loft

old-rafters-and-wood-removed-from-house
Day 147 – Thursday 2nd February 2017 – phase 2

New flat roof under construction and view into what will be the master bedroom. This is tied into the top of the existing roof.

view-over-newly-created-flat-roof

view-over-newly-created-flat-roof-another-angle

Beams now inserted in between steel beams to form the structure of the flat roof

New roof rafters on the left side of the house. These have been attached to the newly inserted ridge board that will come out to the front of the house and form the top of the pitched roof and gable end on the right hand side

rafters on the right hand side of the house attached to the ridge board, pic 2

bathroom-window opening -to-be-slightly-altered-as-roof-rafters clip- the edge-of- the window

Bathroom window pic 2

rafters to ridge board viewed form left side. Cross beams notched into steel

view of rafters through bathroom window opening. Edge of bathroom can be seen marked out with wood in flooring

View into bedroom from the right

View through left window to newly created bedroom floor space

new-drawer-unit-in-kitchen-island-fitted-out-with-worktop-for-scone-and-pastry-making-at-a-good-working-height

new-drawer-unit-in-kitchen-island-fitted-out-with-worktop
Day 148 -Friday 3rd February 2017 – phase 2

Bathroom window gap has been decreased in size as rafters were going to clip edge of window

more-rafters-inserted-on-right-and-front-of-gable-built-today

gable-end-on-right-hand-side-now-being-created-over-bathroom-window-gap

gable-end-on-right-over-bathroom-window

new rafters in place on right side

view-of-underside-of-rafters-over-what-will-be-the-side-of-the-bathroom

middle-window-insulated-below

view-to-the-right-showing-beams-for-flat-roof-and-rafters-to-flat-roof

view-into-master-bedroom-area-being-used-for-construction-of-roof

upstairs-left-hand-window-gap
Day 149 -Monday 6th February 2017 – phase 2

Kymin walk – View down hillside – canopy of Springdale visible as big white roof

zoomed-in-photo-of-canopy-from-hillside-above-the-house

left-side-of-roof-beside-lower-level-scaffolding

on-scaffolding

velux-window-frame-work-created

new-wall-partition-created-between-new-eaves-and-bathroom-and-study-room-which-will-have-a-sloping-roof

framework-for-wall-of-bathroom

view-from-left-side-of-house-across-new-upstairs-area-part-of-left-side-of-roof-now-removed-pic-2

view-from-left-side-of-house-across-new-upstairs-area-

left-side-of-upstairs-area-pic-2

left-side-of-upstairs-area