Day 192 – Wednesday 26th April 2017 – phase 2

Bathroom upstairs partly tiled and floor boarded, screwed down and tiled over, by Marcus Kelly, plumber and Josh

Upstairs bathroom progress so far
Bathroom upstairs partly tiled and floor boarded, screwed down and tiled over, by Marcus Kelly, plumber and Josh
Upstairs bathroom progress so far
View of Springdale from the front with boarded up old porch now ready for demolition of wall inside
Springdale-on-the-first-of-March-2017
old-porch-wall-inside-ready-for-demolition
old-radiators-from-hallway
old-porch-boarded-up inside
front-of-house-boarded-up-ready-for-demolition-of-wall-inside View from the outside
looking-down-from-scaffolding-to-boarded-up-front
dormer-lead-around-window
dormer-sides-lined-with-lead
rendering-applied-today-as-seen-throught-the-scaffolding
rendering-as-seen-from-second-level-of-the-scaffolding-looks-perfect
rendering-as-seen-from-second-level-of-the-scaffolding-pic-3
rendering-pic-4
view-of-bedroom-and-dormer-more-plastering-completed-today
view-of-2-bedroom-windows-and-new-plastering
wall-channelled-out-for-plug-sockets
entrance-to-study
new waste-pipe-installed and connected-to-new downpipe-which-has-been-connected-to-the-house-drains
waste-downpipe-connected-to-vent-with-birds-nest-top
shower-waste-and-wash-hand-basin-waste-water-pipe-in-white-connected-to-the-waste-pipe-under-the-guttering
waste pipe from new upstairs toilet as yet not installed
white-waste-pipe-coming-from-right-to-left-join-waste-pipe-from-shower-and-then-flows-through-to-main-waste-pipe-outside
Plumbing pipes under old ceiling of the old porch. Middle pipe is the cold water supply to the upstairs toilet. Right of the beam is the hot and cold supply of water to the wash basin. Short pipe is the radiator pipe to the bedroom.
Windows arrived today. Most of plaster boarding was finished. Looking brilliant.
Bathroom window fitted with obscure glass
small-bedroom-window-installed
large-bedroom-window-installed
view-from-back-of-bedroom-to-front 3 windows all just visible in this picture Dormer window boarded up till window is ready
progress-on-the-bedroom-ready-for-plasterers. Dormer window on the right – the brown wood area
bedroom-dormer-boarded-up-till-window-is-ready. Pink plasterboard over the beam
bedroom-view-from-ensuite-pink-plasterboard-is-firelined-to-protect-beams
study-area-plaster boarded
ladders-to-bedroom