Day 115 – Saturday 10th December 2016

Day 115 – Saturday 10th December 2016

Assembly of kitchen units begins.  This will not be completed till after Christmas.

base-kitchen-units-going-into-place

Base Kitchen Units going into place along with dishwasher

tall-kitchen-cabinet-and-base-kitchen-units-going-into-place

tall-kitchen-cabinet-and-base-kitchen-units-going-into-place

Advertisements

Day 114 – Friday 9th December 2016

Day 114 – Friday 9th December 2016 (no work carried out on Thursday)

path-between-garage-and-new-kitchen-slabs-cut

Path between garage and kitchen. More Indian Sandstone slabs were delivered and have been cut.

path-between-garage-and-new-kitchen-from-back-to-front-of-house

path-between-garage-and-new-kitchen-from-back-to-front-of-house

progress-of-patio-at-back-of-kitchen

progress-of-patio-at-back-of-kitchen

Day 113 – Wednesday 7th December 2016

Day 113 – Wednesday 7th December 2016

walkway-between-new-kitchen-an-garage-slabs-being-laid-also-scratch-coat-on-new-kitchen-outside-wall

Pathway between new kitchen and garage. Slabs being laid. Also scratch coat on new kitchen wall has been applied.

boards-up-to-stop-us-treading-on-freshly-laid-slabs

boards-up-to-stop-us-treading-on-freshly-laid-slabs

main-steps-to-garden-from-new-kitchen-partially-laid

main-steps-to-garden-from-new-kitchen-partially-laid

scratch-coat-on-walls-and-more-freshly-laid-slabs

scratch-coat-on-walls-and-more-freshly-laid-slabs

scratch-coat-on-outside-of-walls-of-kitchen-back-and-sides

scratch-coat-on-outside-of-walls-of-kitchen-back-and-sides

scratch-coat-on-outside-of-new-back-of-kitchen

scratch-coat-on-outside-of-new-back-of-kitchen

Day 111 – Monday 5th December 2016

Day 111 – Monday 5th December 2016

Delivery of kitchen unit to replace damaged one. Step at side of kitchen window put in.  Plasterers/roughcast guys returned to put metal and wood edgings on new walls, in preparation for scratch coat

new-bathroom-suite-arrived-today-for-new-downstairs-family-bathroom

new-bathroom-suite-arrived-today-for-new-downstairs-family-bathroom

view-from-bathroom-to-utility-no-door-on-yet

view-from-bathroom-to-utility-no-door-on-yet

3-shower-boards-1-shower-screen-and-heated-towel-rail

3-shower-boards-1-shower-screen-and-heated-towel-rail

ramp-and-walkway-between-garage-and-new-kitchen-now-built-up-wall-completed-to-tie-in-with-existing-wall

ramp-and-walkway-between-garage-and-new-kitchen-now-built-up-wall-completed-to-tie-in-with-existing-wall

battening-and-metal-strips-now-in-place-for-rough-casting-of-bricks-on-new-extension

battening-and-metal-strips-now-in-place-for-rough-casting-of-bricks-on-new-extension

new-side-step-to-back-of-garage

new-side-step-to-back-of-garage

Day 110 – Sunday 4th December 2016

Day 110 – Sunday 4th December 2016

view-of-flooring-from-window-new-units-in-centre

view-of-flooring-from-window-new-units-in-centre – Flooring now finished

flooring-finished-new-kitchen-units-now-sitting-in-centre-of-kitchen-whilst-floor-is-laid

flooring-finished-new-kitchen-units-now-sitting-in-centre-of-kitchen-whilst-floor-is-laid

hatch-put-in

hatch-put-in Access to roof space

slabs-now-being-cemented-into-place-for-new-patio-at-back-of-new-kitchen

slabs-now-being-cemented-into-place-for-new-patio-at-back-of-new-kitchen