Tag Archives: scaffolding

Day 166 -Wednesday 1st March 2017 – phase 2

Day 166 -Wednesday 1st March 2017 – phase 2

view-of-springdale-progress-so-far-boarded-up-porch-ready-for-demolition-of-the-inside-wall

View of Springdale from the front with boarded up old porch now ready for demolition of wall inside

springdale-on-the-first-of-march-2017

Springdale-on-the-first-of-March-2017

old-porch-wall-inside-ready-for-demolition

old-porch-wall-inside-ready-for-demolition

old-radiators-from-hallway

old-radiators-from-hallway

old-porch-boarded-up

old-porch-boarded-up inside

front-of-house-boarded-up-ready-for-demolition-of-wall-inside

front-of-house-boarded-up-ready-for-demolition-of-wall-inside                              View from the outside

 

looking-down-from-scaffolding-to-boarded-up-front

looking-down-from-scaffolding-to-boarded-up-front

dormer-lead-around-window

dormer-lead-around-window

dormer-sides-lined-with-lead

dormer-sides-lined-with-lead

rendering-applied-today-as-seen-throught-the-scaffolding

rendering-applied-today-as-seen-throught-the-scaffolding

rendering-as-seen-from-second-level-of-the-scaffolding-looks-perfect

rendering-as-seen-from-second-level-of-the-scaffolding-looks-perfect

rendering-as-seen-from-second-level-of-the-scaffolding-pic-3

rendering-as-seen-from-second-level-of-the-scaffolding-pic-3

rendering-pic-4

rendering-pic-4

view-of-bedroom-and-dormer-more-plastering-completed-today

view-of-bedroom-and-dormer-more-plastering-completed-today

view-of-2-bedrrom-windows-and-new-plastering

view-of-2-bedroom-windows-and-new-plastering

wall-channelled-out-for-plug-sockets

wall-channelled-out-for-plug-sockets

entrance-to-study

entrance-to-study

waste-pipe-connected-to-downpipe-which-has-been-connected-to-the-house-drains

new waste-pipe-installed and connected-to-new downpipe-which-has-been-connected-to-the-house-drains

waste-downpipe-connected-to-vent-with-birds-nest-top

waste-downpipe-connected-to-vent-with-birds-nest-top

shower-waste-and-wash-hand-basin-waste-water-pipe-in-white-connected-to-the-waste-pipe-under-the-guttering

shower-waste-and-wash-hand-basin-waste-water-pipe-in-white-connected-to-the-waste-pipe-under-the-guttering

waste-pipe-from-new-upstairs-toilet-not-yet-put-in

waste pipe from new upstairs toilet as yet not installed

white-waste-pipe-coming-from-right-to-left-join-waste-pipe-from-shower-and-then-flows-through-to-main-waste-pipe-outside

white-waste-pipe-coming-from-right-to-left-join-waste-pipe-from-shower-and-then-flows-through-to-main-waste-pipe-outside

plumbing-pipes-under-old-ceiling-in-the-old-porch-middle-pipe-is-cold-water-supply-to-upstairs-toilet-right-beam-hot-and-cold-supply-of-water-to-the-wash-basin-short-pipe-radiator-pipe-to-bedr

Plumbing pipes under old ceiling of the old porch. Middle pipe is the cold water supply to the upstairs toilet. Right of the beam is the hot and cold supply of water to the wash basin. Short pipe is the radiator pipe to the bedroom.

Day 165 – Tuesday 28th February 2017 – phase 2

Day 165 – Tuesday 28th February 2017 – phase 2

old-front-and-porch-at-the-beginning-of-tuesday-28th-february-steel-beam-in-place

old-front-and-porch-at-the-beginning-of-tuesday-28th-february-steel-beam-in-place

old-front-and-porch-at-the-end-of-tuesday-28th-february-scratch-coat-applied-over-beam

old-front-and-porch-at-the-end-of-tuesday-28th-february-scratch-coat-applied-over-beam

dormer-from-the-outside-progress-so-far

dormer-from-the-outside-progress-so-far

doorway-with-frame-in-place-skimmed-with-plaster

bedroom doorway-with-frame-in-place-skimmed-with-plaster

plastering-continues-upstairs-in-the-new-bedroom-view-over-to-staircase-through-lefthand-doorway-and-to-ensuite-through-right-hand-doorway

plastering-continues-upstairs-in-the-new-bedroom-view-over-to-staircase-through-left hand-doorway-and-to-ensuite-through-right-hand-doorway

view-across-to-dormer-side-of-bedroom-and-plastering-on-this-side-of-bedroom-and-around-beam

view-across-to-dormer-side-of-bedroom-and-plastering-on-this-side-of-bedroom-and-around-beam

top-and-bottom-of-small-window-upstairs-skimmed-with-plaster

top-and-bottom-of-small-window-upstairs-skimmed-with-plaster

window-sill-and-around-windows-skimmed-with-plaster

window-sill-and-around-windows-skimmed-with-plaster

view-through-to-old-hall-from-new-upstairs-study-this-is-where-a-new-cupboard-will-be-built-over-the-new-staircase

view-through-to-old-hall-from-new-upstairs-study-this-is-where-a-new-cupboard-will-be-built-over-the-new-staircase

view-from-scaffolding-of-windows-which-have-now-been-prepared-for-rendering

view-from-scaffolding-of-windows-which-have-now-been-prepared-for-rendering

upstairs-bedroom-windows-being-prepared-for-rendering-mesh-installed-around-sides

upstairs-bedroom-windows-being-prepared-for-rendering-mesh-installed-around-sides

toilet-waste-pipe-in-place-in-ensuite-with-water-supply-pipe-at-the-side

toilet-waste-pipe-in-place-in-ensuite-with-water-supply-pipe-at-the-side

toilet-waste-pipe-in-place-in-ensuite

toilet-waste-pipe-in-place-in-ensuite

toilet-waste-pipe-now-in-position-through-the-back-of-the-eaves-to-the-outside

toilet-waste-pipe-now-in-position-through-the-back-of-the-eaves-to-the-outside

waste-pipe-from-toilet-just-visible-coming-to-the-outside-of-the-house

waste-pipe-from-toilet-just-visible-coming-to-the-outside-of-the-house

waste-pipe-for-wash-hand-basin-in-ceiling-at-the-edge-of-the-old-hall

waste-pipe-for-wash-hand-basin-in-ceiling-at-the-edge-of-the-old-hall. A white pipe which joins up with the waste water from the shower. This will join the outside waste pipe outside the house on the side

waste-water-pipe-for-shower

waste-water-pipe-for-shower

waste-pipe-for-wash-hand-basin-in-ensuite-with-water-supply-pipe-holes-behind

waste-pipe-for-wash-hand-basin-in-ensuite-with-water-supply-pipe-holes-behind

waste-water-pipe-for-wash-basin

waste-water-pipe-for-wash-basin

waste-water-pipe-to-outside-from-shower-to-be-joined-to-main-waste-pipe

waste-water-pipe-to-outside-from-shower-to-be-joined-to-main-waste-pipe

pipes-for-hot-and-cold-water-going-through-into-old-porch-ceiling-and-up-to-the-new-upstairs

pipes-for-hot-and-cold-water-going-through-into-old-porch-ceiling-and-up-to-the-new-upstairs

hot-and-cold-water-pipes-to-upstairs-in-ceiling-of-old-hall-thinner-pipes-are-radiator-pipes

hot-and-cold-water-pipes-to-upstairs-in-ceiling-of-old-hall-thinner-pipes-are-radiator-pipes

hot-and-cold-water-pipes-and-radiator-pipes-for-upstairs

hot-and-cold-water-pipes-and-radiator-pipes-for-upstairs

plasterboarding-at-the-side-of-the-dormer

plaster boarding-at-the-side-of-the-dormer

Day 164 – Monday 27th February 2017 – phase 2

Day 164 – Monday 27th February 2017 – phase 2

4-vans-means-a-lot-of-teas-and-coffees

Four vans on the drive – this means a lot of teas and coffees to be made

Roofer, Royston, has been doing the flat roof sections

another-coat-of-fibre-glass-applied-over-flat-roof

another-coat-of-fibre-glass-applied-over-flat-roof

fibre-glass-roof

fibre-glass-roof

flat-roof-over-the-dormer

flat-roof-over-the-dormer lead area can be seen below

dormer-window-boarded-up-and-flat-roof-has-had-fibre-glass-applied

dormer-window-boarded-up-and-flat-roof-has-had-fibre-glass-applied

Michael the plasterer to begin skimming walls etc.

beginning-of-plastering-in-the-study-sealing-joints

beginning-of-plastering-in-the-study-sealing-joints

plasterer-beginning-to-seal-joints-between-plasterboard-before-skimming

plasterer-beginning-to-seal-joints-between-plasterboard-before-skimming

plastering-of-bedroom-ceiling

plastering-of-bedroom-ceiling

plastering-on-the-new-bedroom-ceiling-half-the-room-has-been-completed-today

plastering-on-the-new-bedroom-ceiling-half-the-room-has-been-completed-today

ceiling-pipework-in-new-front-room-old-hall-in-the-ceiling-for-water-and-radiators

ceiling-pipework-in-new-front-room-old-hall-in-the-ceiling-for-water-and-radiators. Work done by Marcus Kelly and his assistant Josh

pipework-for-radiators-and-hot-and-cold-water-for-upstairs-fitted-today-by-marcus-kelly-plumber

pipework-for-radiators-and-hot-and-cold-water-for-upstairs-fitted-today-by-marcus-kelly-plumber

pipework-in-the-old-porch-roof-space-for-hot-old-water-and-radiators

pipework-in-the-old-porch-roof-space-for-hot and cold-water-and-radiators

extractor-fan-installed-in-new-bathroom

extractor-fan-installed-in-new-bathroom

joe-ohara-electrician-ballen-electrical

Joe O’Hara, electrician, Ballan Electrical, wiring for light switches, sockets, in the old hallway which is becoming the sun lounge

channel-in-the-wall-in-the-new-front-room-for-wiring-to-turn-on-main-lights

channel-in-the-wall-in-the-new-front-room-for-wiring-to-turn-on-main-lights

channel-for-electrics-to-light-switch-which-will-be-by-the-staircase

channel-for-electrics-to-light-switch-which-will-be-by-the-staircase

wiring-installed-for-outside-light

wiring-installed-for-outside-light

wiring-for-right-hand-outside-light

wiring-for-right-hand-outside-light

wiring-for-outside-light-and-porch-light

wiring-for-outside-light

rockwool-filling-cavities-in-the-new-ensuite-bathroom

rockwool-filling-cavities-in-the-new-ensuite-bathroom

upstairs-windows-as-viewed-from-level-2-of-the-scaffolding

upstairs-windows-as-viewed-from-level-2-of-the-scaffolding

progress-at-the-top-of-the-staircase

progress-at-the-top-of-the-staircase

Day 161 – Wednesday 22nd February 2017 – phase 2

Day 161 – Wednesday 22nd February 2017 – phase 2

flat-roof-1st-coat-applied-onto-roof-over-new-upstairs

Flat roof – first coat of fibre glass applied over new upstairs flat roof

flat-roof-pic-2

flat-roof-pic-2

right-side-of-roof-tiles-are-now-being-put-back-on-2-roofers-today

left-side-of-roof-tiles-are-now-being-put-back-on-2-roofers came-today

tiles-are-now-being-put-on-the-new-right-side-of-the-house

tiles-are-now-being-put-on-the-new-left-side-of-the-house

tiling-around-the-new-dormer

tiling-around-the-new-dormer

large-amounts-of-insulation-going-into-ceilings-of-new-upstairs-sloping-roof-and-walls

large-amounts-of-insulation-going-into-ceilings-of-new-upstairs-sloping-roof-and-walls

insulation-and-plasterboard

insulation-and-plasterboard

celotex-insulation

celotex-insulation

blurry-photo-paul-on-scaffold

blurry-photo-Paul-on-scaffold

Day 149 -Monday 6th February 2017 – phase 2

Day 149 -Monday 6th February 2017 – phase 2

kymin-walk-canopy-in-white-visible-from-hillside

Kymin walk – View down hillside – canopy of Springdale visible as big white roof

zoomed-in-photo-of-canopy-from-hillside-above-the-house

zoomed-in-photo-of-canopy-from-hillside-above-the-house

left-side-of-roof-beside-lower-level-scaffolding

left-side-of-roof-beside-lower-level-scaffolding

on-scaffolding

on-scaffolding

velux-window-frame-work-created

velux-window-frame-work-created

new-wall-partition-created-between-new-eaves-and-bathroom-and-study-room-which-will-have-a-sloping-roof

new-wall-partition-created-between-new-eaves-and-bathroom-and-study-room-which-will-have-a-sloping-roof

framework-for-wall-of-bathroom-upstanding-wooden-batons

framework-for-wall-of-bathroom

view-from-left-side-of-house-across-new-upstairs-area-part-of-left-side-of-roof-now-removed-pic-2

view-from-left-side-of-house-across-new-upstairs-area-part-of-left-side-of-roof-now-removed-pic-2

view-from-left-side-of-huse-across-new-upstairs-area-part-of-left-side-of-roof-now-removed

view-from-left-side-of-house-across-new-upstairs-area-

left-side-of-upstairs-area-pic-2

left-side-of-upstairs-area-pic-2

left-side-of-upstairs-area

left-side-of-upstairs-area

Day 146 – Wednesday 1st February 2017 – phase 2

Day 146 – Wednesday 1st February 2017 – phase 2

glimpse-of-new-bedroom-through-gap-in-old-hall-ceiling-flooring-down

glimpse-of-new-bedroom-through-gap-in-old-hall-ceiling-flooring-down

view-from-gap-in-flooring-to-bathroom-area

view-from-gap-in-flooring-to-bathroom-area

view-from-gap-in-flooring-to-bedroom-windows

view-from-gap-in-flooring-to-bedroom-windows

view-from-right-across-floored-upstairs

view-from-right-across-floored-upstairs

view-through-middle-window-from-scaffolding-of-right-side-of-bathroom-and-study

view-through-middle-window-from-scaffolding-of-right-side-of-bathroom-and-study

view-from-scaffolding-through-middle-window-to-back-of-new-bedroom-and-covered-area-of-staircase

view-from-scaffolding-through-middle-window-to-back-of-new-bedroom-and-covered-area-of-staircase

view-to-left-side-of-bedroom-and-flooring-base

view-to-left-side-of-bedroom-and-flooring-base

left-side-of-bedroom-not-floored-yet-beams-down

left-side-of-bedroom-not-floored-yet-beams-down

view-through-to-left-side-of-bedroom

view-through-to-left-side-of-bedroom

right-side-of-house

right-side-of-house

view-from-left-side-of-house-from-scaffolding

view-from-left-side-of-house-from-scaffolding

rubble-and-remnants-of-old-loft

rubble-and-remnants-of-old-loft

old-rafters-and-wood-removed-from-house

old-rafters-and-wood-removed-from-house

Day 145 – Tuesday 31st January 2017 – phase 2

Day 145 – Tuesday 31st January 2017 – phase 2

Roof tiles all stripped off today under supervision from bat licensed ecologist. Balcony window taken out and flat roof taken off.  From phase 1, worktop for new kitchen which had been measured and cut to size has now been fitted.

newly-fitted-worktop-for-kitchen-and-island-unit

newly-fitted-worktop-for-kitchen-and-island-unit

new-worktop-fitted

New worktop fitted – a transformation

balcony-window-now-removed-view-through-to-new-bedroom-floor

balcony-window-now-removed-view-through-to-new-bedroom-floor and through to hall below

left-side-of-house-tiles-stripped-under-supervision-of-a-bat-licensed-ecologist

left-side-of-house-tiles-stripped-under-supervision-of-a-bat-licensed-ecologist

left-and-front-stripped-of-tiles

left-and-front-stripped-of-tiles

right-side-of-house-tiles-all-stripped-off

right-side-of-house-tiles-all-stripped-off

view-of-stripped-roof-from-left

view-of-stripped-roof-from-left

view-into-house-over-old-porch

view-into-house-over-old-porch

view-of-what-will-be-new-bedroom-floor

view-of-what-will-be-new-bedroom-floor

view-through-gap-that-will-be-middle-window-in-the-bedroom

view-through-gap-that-will-be-middle-window-in-the-bedroom

view-through-gap-which-will-be-new-ensuite-bathroom-window

view-through-gap-which-will-be-new-ensuite-bathroom-window

top-of-roof-now-to-compare-later-when-new-roof-is-on

top-of-roof-now-to-compare-later-when-new-roof-is-on

view-from-front-through-to-house-from-scaffolding-of-the-inside-where-the-old-balcony-has-been-removed

view-from-front-through-to-house-from-scaffolding-of-the-inside-where-the-old-balcony-has-been-removed

gap-from-below-seen-in-previous-pictures-as-light-shining-through-from-house

gap-from-below-seen-in-previous-pictures-as-light-shining-through-from-house

tiles-all-stacked-to-be-reused-for-new-roof

tiles-all-stacked-to-be-reused-for-new-roof

tiles-all-stacked-to-be-reused-for-new-roof-down-side-of-scaffolding

tiles-all-stacked-to-be-reused-for-new-roof-down-side-of-scaffolding

Day 142 – Friday 27th January 2017 – phase 2

Day 142 – Friday 27th January 2017 – phase 2

A full day of completing the scaffolding and canopy over the house

canopy-beginning-to-go-over-house

canopy-beginning-to-go-over-house

canopy-from-the-right

canopy-from-the-right

canopy-from-the-front

canopy-from-the-front

canopy-completed-showing-left-side-of-house-and-the-water-containers-which-hold-scaffolding-in-place

canopy-completed-showing-left-side-of-house-and-the-water-containers-which-hold-scaffolding-in-place

beams-and-new-window-gaps-under-the-canopy-window-fitter-came-out-and-measured-these-gaps-for-windows-today

beams-and-new-window-gaps-under-the-canopy-window-fitter-came-out-and-measured-these-gaps-for-windows-today

beams-under-canopy-and-another-pic

beams-under-canopy-and-another-pic

beams-under-canopy-another-pic

beams-under-canopy-another-pic

inside-canopy-on-scaffolding-left-side-of-house

inside-canopy-on-scaffolding-left-side-of-house

two-beams-now-under-canopy

two-beams-now-under-canopy

view-down-to-garages-below-and-skip

view-down-to-garages-below-and-skip

Day 141 – Thursday 26th January 2017 – phase 2

Day 141 – Thursday 26th January 2017 – phase 2

A very important day for the build – the huge new steel beams lifted into the correct position, more scaffolding going up, a 2 day job with 4 men to create a canopy right over the house, which will mean that work is not so weather dependent and the house will be more protected when the roof comes off.  Also from phase 1, air vents over flat utility room roof going in, to try and allow air to flow and to stop build up of condensation.

ab-crane-for-lifting-steel-beams

High Ab Crane for lifting the Steel Beams

crane-house-beams-and-men-preparing-for-lift

Pre-preparation of crane, house and roof, and the beams

steel-beams-on-grass-ready-for-lift-into-position

Steels on the grass ready for lift onto roof and final position

steel-beams-with-slings

Steel beams with slings

supporting-stand-for-crane

Supporting stand for crane

steel-beams-showing-the-size-and-length

Steel beams showing their full size and length

beams-propped-up-ready-for-pick-up-by-crane

Beams propped up ready for lift by crane

builder-cutting-away-roof-ready-for-beam-to-go-into-house

Builder now cutting into roof, where tiles have been removed previously, for beam to inserted onto a prepared strengthened area on an existing original wall of the house

control-of-direction-of-beam-using-rope

Crane begins lift via radio control, operator in high viz jacket whilst the other builder controls the direction of the beam using an attached guide rope

control-of-direction-of-beam-using-rope-pic-2

Beam is lifted

control-of-direction-of-beam-using-rope-pic-3

direction still controlled by rope

control-of-direction-of-beam-using-rope-pic-4

beam rising

beam-going-up

First beam going up

beam-going-up-2

Beam going up pic 2

beam-going-up-3

beam-going-up-3

beam-going-up-4

Beam going up pic 4

beam-going-up-5

Beam going up pic 5

beam-going-up-10

Beam going up pic 6

beam-going-up-11

Beam going up pic 7

beam-going-up-8

Beam going up pic 8

beam-being-maneouvred-10

manoeuvring beam

beam-being-maneouvred-9

beam going into position

beam-being-maneouvred-6

view of crane

beam-going-up-9

Beam going up pic 9 – wrong angle – beam has to be readjusted

beam-being-maneouvred-to-get-a-better-angle-to-put-into-place

Steel beam has to be repositioned as scaffolding is preventing the beam from locating in its correct position in the roof

beam-being-manoeuvred-11

Beam being manoeuvred over scaffolding

beam-being-maneouvred-12

Beam being manoeuvred

beam-being-maneouvred-13

beam now at correct angle to be manoeuvred into position

beam-being-maneouvred-7

close up

beam-being-maneouvred-4

manoeuvring beam

maneouvred-into-position-1

manoeuvred-into-position-1

maneouvred-into-position-2

manoeuvred-into-position-2

maneouvred-into-position-3

manoeuvred-into-position-3

first-beam-in-place

First beam in place

first-beam-in-place-pic-2

Pictures from scaffolding of the first beam in place – pic 2

first-beam-in-place-pic-3

first-beam-in-place-pic-3

first-beam-in-place-pic-4

first-beam-in-place-pic-4

position-for-second-beam

beam 2 to go here

preparing-roof-for-beam-2

preparing-roof-for-beam-2

second-beam-being-craned-in-pic-2

Second beam being craned in

second-beam-being-craned-in-pic-3

second-beam-being-craned-in-pic-3

second-beam-being-craned-in-pic-4

second-beam-being-craned-in-pic-4

second-beam-being-craned-in

second-beam-being-craned-in

second-beam-being-craned-in-pic-5

second-beam-being-craned-in-pic-5

second-beam-going-into-position-pic-2

second-beam-going-into-position

second beam in position

second beam in position

second-beam-going-into-position-pic-3

different view of beam 2

two-new-steel-beams-in-place

Two new steel beams in place under new scaffolding

two-new-steel-beams-in-place-pic-3

two-new-steel-beams-in-place-pic-3

two-new-steel-beams-in-place-pic-2

two-new-steel-beams-in-place-pic-2

steel-beam-number-2-in-position

steel-beam-number-2-in-position

steel-beam-number-2-in-position-pic-2

steel-beam-number-2-in-position-pic-2

More scaffolding going up to create a canopy over house

scaffolders

scaffolding  arrives

scaffolders-move-truck-to-drive-2-days-construction-ahead

scaffolders-move-truck-to-driveway -2-days-construction-ahead

scaffold

scaffold unloading

scaffolders-pic-2

unloading scaffolding

scaffolders-and-one-ton-water-containers-to-hold-scaffolding-and-canopy-securely

scaffolders-and-one-ton-water-containers-to-hold-scaffolding-and-canopy-securely

next-phase-of-scaffolding-with-water-container-1-ton-weights

next-phase-of-scaffolding-with-water-container-1-ton-weights

new-scaffolding-going-up-to-cover-house

new-scaffolding-going-up-to-cover-house

new-scaffolding-going-up-to-cover-house-pic-3

new-scaffolding-going-up-to-cover-house-pic-3

new-scaffolding-going-up-to-cover-house-pic-2

new-scaffolding-going-up-to-cover-house-pic-2

water-containers-to-act-as-weights-to-keep-canopy-and-scaffolding-secure

water-containers-to-act-as-weights-to-keep-canopy-and-scaffolding-secure

fibre-glass-roof-and-new-condensation-vents-pic-2

Phase 1 the fibre-glass-roof-and-new-condensation-vents-to try to eliminate damp patches on utility ceiling

fibre-glass-roof-and-new-condensation-vents

fibre-glass-roof-and-new-condensation-vents

pointing-on-roof-tiles-over-new-kitchen

Phase 1 pointing-on-roof-tiles-over-new-kitchen

view-of-new-kitchen-roof-in-red-beyond-scaffolding

view-of-new-kitchen-roof-in-red-beyond-scaffolding

steel-beam-number-1-from-inside-house-pic-2

steel-beam-number-1-from-inside-house-pic-2

steel-beam-number-1-from-inside-house

steel-beam-number-1-from-inside-house

 

 

Day 138 – Monday 23rd January 2017 phase 2

Day 138 – Monday 23rd January 2017 – phase 2

Chimney removal

underside-of-chimney-supported-to-stop-debris-entering-the-old-kitchen

To Begin the underside of the chimney Is supported to stop debris entering the old kitchen

beginning-of-chimney-removal

Chimney

chimney-removed

No Chimney

chimney-removed-from-scaffolding

chimney-removed-view from-scaffolding

chimney-removed-from-scaffolding-pic-2

chimney-removed-view from-scaffolding-pic-2

chimney-removed-from-scaffolding-pic-3

chimney-removed-view from top of scaffolding-pic-3

daylight-from-the-hall-where-the-chimney-was

daylight-from-the-hall-where-the-chimney-was

from-inside-where-the-chimney-was-creating-an-even-larger-area

Area where chimney was, creating more space for upstairs bedroom and a dormer window

old-position-of-chimney

old-position-of-chimney

view-to-front-beams-to-come-out

This area to be removed after big steels go in later in the week

into-the-new-bedroom

into-the-new-bedroom. Staircase will be fitted here