Day 185 – Monday 27th March 2017 – phase 2

Day 185 – Monday 27th March 2017 – phase 2

Springdale nearly finished still with scaffolding

Springdale nearly finished still with scaffolding. View from the back of the house.

Bedroom door now with architrave

Bedroom door now with architrave, also bathroom door both side complete

Cupboard handles on cupboard in study now finished

Cupboard handles on cupboard in study now finished

 

Looking down the new staircase - new handrail up and fitted on the right pic 2

Looking down the new staircase – new handrail up and fitted on the right – pic 2

Looking down the new staircase - new handrail up and fitted on the right

Looking down the new staircase – new handrail up and fitted on the right

Stair rail now with spindles all stained and treated, the rest to complete after work is complete upstairs

Stair rail now with spindles all stained and treated, the rest to complete after work is complete upstairs

New staircase with the stained and treated spindles now fitted

New staircase with the stained and treated spindles now fitted

left gable and new gutterings and downpipes

left gable and new gutterings and downpipes

Old guttering now removed as an extra to the original work - old guttering was full of holes and broken in places

Old guttering now removed as an extra to the original work – old guttering was full of holes and broken in places

Old guttering removed

Old guttering removed

Vents complete under dormer roof

Vents complete under dormer roof

Dormer with vents below guttering just visible

Dormer with vents below guttering just visible

Fuse boxes now all labelled up by Joe, Ballan Electrical

Fuse boxes now all labelled up by Joe, Ballan Electrical

Old alarm wires removed, fuse switch removed and general tidy up of all wiring in utility room

Old alarm wires removed, fuse switch removed and general tidy up of all wiring in utility room

Sockets relocated in the utility room, fuse switch removed from above by Joe, Ballan Electrical

Sockets relocated in the utility room, fuse switch removed from above by Joe, Ballan Electrical

Smoke alarm changed so will not be set off by cooking, just smoke

Smoke alarm changed so will not be set off by cooking, just smoke

Old light which had been removed on a previous occasion by Joe now replaced with smaller light to match the rest of the sun room, also on the same circuit

Old light which had been removed on a previous occasion by Joe now replaced with smaller light to match the rest of the sun room, also on the same circuit

new smaller light in archway connected to the lights in the sunroom

new smaller light in archway connected to the lights in the sunroom

Skirting boards around bedroom now complete

Skirting boards around bedroom now complete

Skirting boards around bedroom now complete pic 2

Skirting boards around bedroom now complete pic 2

Day 168 – Friday 3rd March 2017 – phase 2

Day 168 – Friday 3rd March 2017 –   phase 2

Extremely wet day today, but due to canopy over the house, the roofer was still able to work.

royston-roofer

Royston Collier has been the roofer for phase 2

royston-roofer-back-of-van

Royston the roofer back-of-van

royston-tiling-the-sloping-sides-of-the-gables

royston-tiling-the-sloping-sides-of-the-gables

ridge-tiling

Tiling of all the ridges around the flat roof

ridge-tiling-2

ridge-tiling-2

ridge-tiling-pic2

ridge-tiling-pic2

ridge-tiles-on-scaffolding

ridge-tiles-on-scaffolding

ensuite-bathroom-plastered

Ensuite bathroom has been plastered

top-of-stair-wall-plastered-wires-are-for-the-top-of-the-stairs-lights

Top of stair wall plastered. Wires are for the top of the stairs light switches (Joe O’Hara – Ballan Electrical)

plastering-in-the-study-so-far-velux-window-visible

Plastering in the study so far. Velux window visible

formation-of-cupboard-over-the-staircase-accessed-from-study

Formation of the over the stairs cupboard, now all boxed in and plaster-boarded, accessed from the study

very-high-ceiling-over-where-the-staircase-will-be-all-plastered

very-high-ceiling-over-where-the-staircase-will-be. Top ceiling is now all plastered. Small hole is for light.

old-porch-roof-has-had-noggins-put-in-for-extra-support

Old Porch Roof has had noggins inserted for extra strength

old-porch-roof-with-noggins-inserted

old-porch-roof-with-noggins-inserted