Day 187 – Thursday 30th March 2017 – phase 2

Day 187 – Thursday 30th March 2017 – phase 2

No work on Wednesday

Today is the last day of the build.  Lots of finishing off tasks and installing new doors downstairs.  Plumber still to do radiators, and bathroom suite upstairs, but all the external build is now complete.  Here are a few pictures, more to come after the scaffolding is removed.

The outside of the house is all ready for unveiling. The scaffolding should come down next week.

The outside of the house is all ready for unveiling. The scaffolding should come down next week.

guttering finished on the right side of house

guttering finished on the right side of house

guttering all finished

guttering all finished

Bat box on the right side of house by bedroom

Bat box on the right side of house by bedroom

bat box at the top of the house under the gable

bat box at the top of the house under the gable

Bat box on the left side of the house

Bat box on the left side of the house

The curtain is down! We now have the archway back and can see our new sun lounge! Superb!

The curtain is down! We now have the archway back and can see our new sun lounge! Superb!

Another view through the archway

Another view through the archway

New door into downstairs bedroom

New door into downstairs bedroom

New glass panelled door into the hall - this will allow some light through

New glass panelled door into the hall – this will allow some light through

Magnolia tree just ready to flower

Magnolia tree just ready to flower

Day 185 – Monday 27th March 2017 – phase 2

Day 185 – Monday 27th March 2017 – phase 2

Springdale nearly finished still with scaffolding

Springdale nearly finished still with scaffolding. View from the back of the house.

Bedroom door now with architrave

Bedroom door now with architrave, also bathroom door both side complete

Cupboard handles on cupboard in study now finished

Cupboard handles on cupboard in study now finished

 

Looking down the new staircase - new handrail up and fitted on the right pic 2

Looking down the new staircase – new handrail up and fitted on the right – pic 2

Looking down the new staircase - new handrail up and fitted on the right

Looking down the new staircase – new handrail up and fitted on the right

Stair rail now with spindles all stained and treated, the rest to complete after work is complete upstairs

Stair rail now with spindles all stained and treated, the rest to complete after work is complete upstairs

New staircase with the stained and treated spindles now fitted

New staircase with the stained and treated spindles now fitted

left gable and new gutterings and downpipes

left gable and new gutterings and downpipes

Old guttering now removed as an extra to the original work - old guttering was full of holes and broken in places

Old guttering now removed as an extra to the original work – old guttering was full of holes and broken in places

Old guttering removed

Old guttering removed

Vents complete under dormer roof

Vents complete under dormer roof

Dormer with vents below guttering just visible

Dormer with vents below guttering just visible

Fuse boxes now all labelled up by Joe, Ballan Electrical

Fuse boxes now all labelled up by Joe, Ballan Electrical

Old alarm wires removed, fuse switch removed and general tidy up of all wiring in utility room

Old alarm wires removed, fuse switch removed and general tidy up of all wiring in utility room

Sockets relocated in the utility room, fuse switch removed from above by Joe, Ballan Electrical

Sockets relocated in the utility room, fuse switch removed from above by Joe, Ballan Electrical

Smoke alarm changed so will not be set off by cooking, just smoke

Smoke alarm changed so will not be set off by cooking, just smoke

Old light which had been removed on a previous occasion by Joe now replaced with smaller light to match the rest of the sun room, also on the same circuit

Old light which had been removed on a previous occasion by Joe now replaced with smaller light to match the rest of the sun room, also on the same circuit

new smaller light in archway connected to the lights in the sunroom

new smaller light in archway connected to the lights in the sunroom

Skirting boards around bedroom now complete

Skirting boards around bedroom now complete

Skirting boards around bedroom now complete pic 2

Skirting boards around bedroom now complete pic 2

Saturday 18th and Sunday 19th March 2017 – phase 2

Saturday 18th and Sunday 19th March 2017 – phase 2

Busy weekend.  Scaffolding is due for removal shortly.  Therefore it was an opportunity that we couldn’t miss to give the new render 2 coats of paint.  We used Sandtex Masonry Paint.

Painting the new render, first coat

Painting the new render, first coat

First coat of masonery paint on new rendering

First coat of masonry paint on new rendering

All painted - will be able to paint from here downwards when the scaffolding is removed

All painted – will be able to paint from here downwards when the scaffolding is removed

Bathroom and bedroom windows

Bathroom and bedroom windows

Gable painted

Gable painted

two coats of paint

two coats of paint

View of painted newly rendered walls along the top of the scaffolding

View of painted newly rendered walls along the top of the scaffolding

Day 153 -Friday 10th February 2017 – phase 2

Day 153 -Friday 10th February 2017 – phase 2

structure-of-new-dormer-progress-so-far-pic-2

Structure of the new dormer, progress so far

structure-of-new-dormer-progress-so-far

Dormer on the left side of house

dormer-construction-from-the-inside

dormer-construction-from-the-inside

flat-roof-construction-beginning-between-the-2-gables-and-across-the-new-bedroom

flat-roof-construction-beginning-between-the-2-gables-and-across-the-new-bedroom

beginning-of-the-flat-roof

beginning-of-the-flat-roof

shape-of-the-front-of-the-house-now-appearing-2-gables-and-flat-roof-between

shape-of-the-front-of-the-house-now-appearing-2-gables-and-flat-roof-between

left-gable-end

left-gable-end

gable-end-on-left-side-of-house-now-with-block-work

gable-end-on-left-side-of-house-now-with-block-work

view-of-gabled-section-from-steel-beam

view-of-gabled-section-from-steel-beam from inside

view-of-left-gable-filled-with-blockwork-above-bedroom-window-gap

view-of-left-gable-filled-with-blockwork-above-bedroom-window-gap

view-from-velux-on-right-side-of-house-across-newly-laid-tiled-section

view-from-velux-on-right-side-of-house-across-newly-laid-tiled-section

view-below-velux

view-below-velux

 

Day 152 – Thursday 9th February 2017 – phase 2

Day 152 – Thursday 9th February 2017 – phase 2

the-initial-construction-of-the-dormer-in-the-left-side-of-the-new-bedroom-upstairs

the-initial-construction-of-the-dormer-in-the-left-side-of-the-new-bedroom-upstairs

dormer-side-shown-from-the-front-of-the-house

dormer-side-shown-from-the-front-of-the-house

the-sloping-roof-on-left-side-of-the-dormer

the-sloping-roof-on-left-side-of-the-dormer

new-upstairs-area-on-the-left-will-be-the-study-with-velux-window-on-the-right-a-new-ensuite-bathroom

new-upstairs-area-on-the-left-will-be-the-study-with-velux-window-on-the-right-a-new-ensuite-bathroom

new-velux-which-will-be-the-new-window-for-the-study

new-velux-which-will-be-the-new-window-for-the-study

left-gable

left-gable

gable-end-structure-on-the-left-side-of-house-under-construction

gable-end-structure-on-the-left-side-of-house-under-construction

flat-roof-area-between-steelbeams-now-also-under-construction

flat-roof-area-between-steel beams-now-also-under-construction

new-felt-and-batten-adjoining-the-new-roof-to-the-dormer-down-left-side-of-house-over-the-old-kitchen

new-felt-and-batten-adjoining-the-new-roof-to-the-dormer-down-left-side-of-house-over-the-old-kitchen

right-side-of-house-tiling-progress-is-fast

right-side-of-house-tiling-progress-is-fast

right-side-of-house-roof-felted-battened-and-tiles-going-on

right-side-of-house-roof-felted-battened-and-tiles-going-on

new-garage-light-with-sensor

new-garage-light-with-sensor fitted by Ballan Electrical

garage-light-with-sensor

garage-light-with-sensor

Day 151 – Wednesday 8th February 2017 – phase 2

Day 151 – Wednesday 8th February 2017 – phase 2

view-of-inside-of-new-upstairs-from-right-the-progress-so-far

view-of-inside-of-new-upstairs-from-right-the-progress-so-far

rafters-on-the-left-side-of-the-house-in-place

rafters-on-the-left-side-of-the-house-in-place

the-left-side-of-the-house-start-of-the-dormer-window

the-left-side-of-the-house-start-of-the-dormer-window

the-left-side-of-the-house-start-of-the-dormer-window-pic-2

the-left-side-of-the-house-start-of-the-dormer-window-pic-2

second-ridge-beam-in-place-where-left-hand-gable-will-be-positioned

second-ridge-beam-in-place-where-left-hand-gable-will-be-positioned

view-of-2nd-ridge-beam-from-right

view-of-2nd-ridge-beam-from-right