Day 182 – Wednesday 22nd March 2017 – phase 2

Day 182 – Wednesday 22nd March 2017 – phase 2

New staircase has arrived

New staircase has arrived!

Parts of the staircase

Parts of the staircase – spindles, rail, step

New staircase now fixed in place in our new sun lounge, looks so smart and takes up little room

First view of the new staircase to the upstairs bedroom – New staircase now fixed in place in our new sun lounge, looks so smart and takes up little room! So happy with it! Thanks to our builders Steve and Luke.

Side of staircase - no spindles yet

Side of staircase – no spindles yet

Looking up staircase

Looking up staircase

Front of the house at present, soon to be unwrapped

Front of the house at present, soon to be unwrapped

Roof now finished by Royston, all ridge tiles now on

Roof now finished by Royston, all ridge tiles now on

Ridge tiles

Ridge tiles

Ridge tiles all with clips to hold in place

Ridge tiles all with clips to hold in place

Ridge tile clips

Ridge tile clips

Tiling below dormer now also completed

Tiling below dormer now also completed

View looking down over the sloping roof of the dormer side of the house

View looking down over the sloping roof of the dormer side of the house

View over the back of the house and the new ride tiles that have replaced the old crumbling ones

View over the back of the house and the new ridge tiles that have replaced the old crumbling ones

Fixed ridge tiles

Fixed ridge tiles

Corner joint where 2 ridges join

Corner joint where 2 ridges join

View over the top flat roof with ridge tiles now back on, and new ones over the gables

View over the top flat roof with ridge tiles now back on, and new ones over the gables

Day 168 – Friday 3rd March 2017 – phase 2

Day 168 – Friday 3rd March 2017 –   phase 2

Extremely wet day today, but due to canopy over the house, the roofer was still able to work.

royston-roofer

Royston Collier has been the roofer for phase 2

royston-roofer-back-of-van

Royston the roofer back-of-van

royston-tiling-the-sloping-sides-of-the-gables

royston-tiling-the-sloping-sides-of-the-gables

ridge-tiling

Tiling of all the ridges around the flat roof

ridge-tiling-2

ridge-tiling-2

ridge-tiling-pic2

ridge-tiling-pic2

ridge-tiles-on-scaffolding

ridge-tiles-on-scaffolding

ensuite-bathroom-plastered

Ensuite bathroom has been plastered

top-of-stair-wall-plastered-wires-are-for-the-top-of-the-stairs-lights

Top of stair wall plastered. Wires are for the top of the stairs light switches (Joe O’Hara – Ballan Electrical)

plastering-in-the-study-so-far-velux-window-visible

Plastering in the study so far. Velux window visible

formation-of-cupboard-over-the-staircase-accessed-from-study

Formation of the over the stairs cupboard, now all boxed in and plaster-boarded, accessed from the study

very-high-ceiling-over-where-the-staircase-will-be-all-plastered

very-high-ceiling-over-where-the-staircase-will-be. Top ceiling is now all plastered. Small hole is for light.

old-porch-roof-has-had-noggins-put-in-for-extra-support

Old Porch Roof has had noggins inserted for extra strength

old-porch-roof-with-noggins-inserted

old-porch-roof-with-noggins-inserted