Day 178 – Thursday 16th March 2017 – phase 2

Windows and doors have arrived for the front

Chris and Clive our window fitters – CWH Windows and Doors, Cardiff – an excellent job done on all our windows and doors!

Clive – the window expert

Clive, Chris and Steve, our builder

Finally the new French Doors for the front of the house have arrived. This is a sideways view until the scaffolding is taken away

French door with letterbox to the bottom right

New French Window Front Doors

New front doors from outside

New front windows and doors – fabulous

side view of new window pic 2

side view of new window

View from the ladder of the new window

View of the front from the side

Windows and doors have arrived for the front pic 2

Window units put in place today in the dormer, where the boarding up was, supplier sent the wrong size

View of the house with new front doors and windows

View of the house with new front doors and windows from a slightly different angle

New fitted cupboards under construction in the sloping roof area. Taking shape!

New large fitted wardrobes also under construction

New large fitted wardrobes under construction on both sides of the doorway. Looking brilliant