Days 118, 119 and 120 – 14th, 15th, 16th December 2016

Days 118, 119 and 120 – 14th, 15th, 16th December 2016

new-bathroom-wood-floor-laid-first

New family bathroom – Old doorway from old bedroom to hall now plaster boarded over. Then new bathroom floor is laid. First a wooden flooring is laid and marked with a grid.

grid-pattern-marked-out-on-wood-flooring

grid-pattern-marked-out-on-wood-flooring

new-bathroom-wood-screwed-down-in-a-grid-pattern-to-ensure-tiles-will-be-laid-on-a-solid-base

new-bathroom-wood-screwed-down-in-a-grid-pattern-to-ensure-tiles-will-be-laid-on-a-solid-base

new-bath-in-place

New bath in place

close-up-of-tiles-in-new-bathroom

close-up-of-tiles-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

walkway-up-between-garage-and-new-kitchen-slabs-have-been-jointed-filled-between-each-slab

walkway-up-between-garage-and-new-kitchen-slabs-have-been-jointed-filled-between-each-slab

view-from-main-patio-of-new-patio

view-from-main-patio-of-new-patio

slabs-laid-on-steps-not-cemented-between-slabs-yet

slabs-laid-on-steps-not-cemented-between-slabs-yet

patio-behind-house-now-all-finished-cement-between-slabs-jointing

patio-behind-house-now-all-finished-cement-between-slabs-jointing

Day 111 – Monday 5th December 2016

Day 111 – Monday 5th December 2016

Delivery of kitchen unit to replace damaged one. Step at side of kitchen window put in.  Plasterers/roughcast guys returned to put metal and wood edgings on new walls, in preparation for scratch coat

new-bathroom-suite-arrived-today-for-new-downstairs-family-bathroom

new-bathroom-suite-arrived-today-for-new-downstairs-family-bathroom

view-from-bathroom-to-utility-no-door-on-yet

view-from-bathroom-to-utility-no-door-on-yet

3-shower-boards-1-shower-screen-and-heated-towel-rail

3-shower-boards-1-shower-screen-and-heated-towel-rail

ramp-and-walkway-between-garage-and-new-kitchen-now-built-up-wall-completed-to-tie-in-with-existing-wall

ramp-and-walkway-between-garage-and-new-kitchen-now-built-up-wall-completed-to-tie-in-with-existing-wall

battening-and-metal-strips-now-in-place-for-rough-casting-of-bricks-on-new-extension

battening-and-metal-strips-now-in-place-for-rough-casting-of-bricks-on-new-extension

new-side-step-to-back-of-garage

new-side-step-to-back-of-garage

Day 100 – Thursday 24th November 2016

Day 100 – Thursday 24th November 2016

Plastering and outside work on new patio

 

back-of-ne-kitchen

Back of new kitchen and Bedroom – scaling all levelled

walkway-between-garage-and-new-kitchen-stones-laid-to-form-a-ramp

walkway-between-garage-and-new-kitchen-stones-laid-to-form-a-ramp

plaster-repaired-around-new-doorway-entrance-to-kitchen-from-corridor

plaster-repaired-around-new-doorway-entrance-to-kitchen-from-corridor

ceiling-in-new-bathroom-now-totally-replastered

ceiling-in-new-bathroom-now-totally-replastered

new-small-bedroom-converted-from-sauna-last-year-walls-prepared-and-patched-ready-for-skim-coat-of-plaster

new-small-bedroom-converted-from-sauna-last-year-walls-prepared-and-patched-ready-for-skim-coat-of-plaster

new-small-bedroomblurred-picture-no-light-walls-prepared-for-plastering

new-small-bedroom blurred-picture-no-light-walls-prepared-for-plastering

hip-roof-area-plastered-inside

hip-roof-area-plastered-inside

new-kitchen-ceiling-plaster-starting-to-dry-out-slowly

new-kitchen-ceiling-plaster-starting-to-dry-out-slowly

utility-area-ceiling-painted

utility-area-ceiling-painted

utility-area-wall-and-ceiling-painted

utility-area-wall-and-ceiling-painted

Day 48 – Friday 16th September 2016

Day 48 – Friday 16th September 2016

New beams joining old building to new extension, supports for roof

area-which-will-be-walk-way-into-new-kitchen-from-back-door-beside-old-bedroom-note-large-difference-in-floor-height-steps-will-be-needed

area-which-will-be-walk-way-into-new-kitchen-from-back-door-beside-old-bedroom-note-large-difference-in-floor-height-steps-will-be-needed

view-from-ladders-over-window-into-old-small-bedroom-with-ceiling-removed

view-from-ladders-over-window-into-old-small-bedroom-with-ceiling-removed

view-of-new-beams-now-in-place-for-new-roof-over-old-small-bedroom-soon-to-be-family-bathroom

view-of-new-beams-now-in-place-for-new-roof-over-old-small-bedroom-soon-to-be-family-bathroom

tiles-on-scaffolding

tiles-on-scaffolding