Tag Archives: cemented

Days 118, 119 and 120 – 14th, 15th, 16th December 2016

Days 118, 119 and 120 – 14th, 15th, 16th December 2016

new-bathroom-wood-floor-laid-first

New family bathroom – Old doorway from old bedroom to hall now plaster boarded over. Then new bathroom floor is laid. First a wooden flooring is laid and marked with a grid.

grid-pattern-marked-out-on-wood-flooring

grid-pattern-marked-out-on-wood-flooring

new-bathroom-wood-screwed-down-in-a-grid-pattern-to-ensure-tiles-will-be-laid-on-a-solid-base

new-bathroom-wood-screwed-down-in-a-grid-pattern-to-ensure-tiles-will-be-laid-on-a-solid-base

new-bath-in-place

New bath in place

close-up-of-tiles-in-new-bathroom

close-up-of-tiles-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

walkway-up-between-garage-and-new-kitchen-slabs-have-been-jointed-filled-between-each-slab

walkway-up-between-garage-and-new-kitchen-slabs-have-been-jointed-filled-between-each-slab

view-from-main-patio-of-new-patio

view-from-main-patio-of-new-patio

slabs-laid-on-steps-not-cemented-between-slabs-yet

slabs-laid-on-steps-not-cemented-between-slabs-yet

patio-behind-house-now-all-finished-cement-between-slabs-jointing

patio-behind-house-now-all-finished-cement-between-slabs-jointing

Days 116 and 117 December 12th and 13th 2016

Days 116 and 117 December 12th and 13th 2016

plumber-has-now-installed-2-radiators-in-kitchen-very-warm-now

Plumber has now installed 2 radiators in kitchen very warm now

2nd-radiator-on-back-wall-of-kitchen

2nd-radiator-on-back-wall-of-kitchen

c

Final slabs cut on Monday and cemented in Tuesday, still to be jointed

final-patio-slabs-cut-on-monday-and-cemented-in-tuesdaypic-2

final-patio-slabs-cut-on-Monday-and-cemented-in-Tuesday