Day 193 – Monday 1st May 2017 – phase 2

Day 193 – Monday 1st May 2017 – phase 2

Upstairs bathroom work continued today.  Marcus Kelly, plumber and Josh his assistant

Upstairs bathroom tiling finished today and grouted

Upstairs bathroom floor tiling finished today and grouted

Showerboards in place - also cut perfectly around the beam

Shower boards in place – also cut perfectly around the beam

shower tray in positio

shower tray in position

Connections visible under the shower tray

Connections visible under the shower tray

bathroom floor tiles

bathroom floor tiles

Day 121 – Monday 19th December 2016

Day 121 – Monday 19th December 2016

newly-tiled-bathroom

Newly tiled bathroom

progress-in-new-bathroom-shower-bords-up-bath-fitted-shower-fitted

progress-in-new-bathroom-shower-boards-up-bath-fitted-shower-fitted

view-of-bath-shower-shower-board-and-tiles

view-of-bath-shower-shower-board-and-tiles

Bath filled with water whilst it sets in place.  This will prevent movement of bath when using shower and bath.

Days 118, 119 and 120 – 14th, 15th, 16th December 2016

Days 118, 119 and 120 – 14th, 15th, 16th December 2016

new-bathroom-wood-floor-laid-first

New family bathroom – Old doorway from old bedroom to hall now plaster boarded over. Then new bathroom floor is laid. First a wooden flooring is laid and marked with a grid.

grid-pattern-marked-out-on-wood-flooring

grid-pattern-marked-out-on-wood-flooring

new-bathroom-wood-screwed-down-in-a-grid-pattern-to-ensure-tiles-will-be-laid-on-a-solid-base

new-bathroom-wood-screwed-down-in-a-grid-pattern-to-ensure-tiles-will-be-laid-on-a-solid-base

new-bath-in-place

New bath in place

close-up-of-tiles-in-new-bathroom

close-up-of-tiles-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

walkway-up-between-garage-and-new-kitchen-slabs-have-been-jointed-filled-between-each-slab

walkway-up-between-garage-and-new-kitchen-slabs-have-been-jointed-filled-between-each-slab

view-from-main-patio-of-new-patio

view-from-main-patio-of-new-patio

slabs-laid-on-steps-not-cemented-between-slabs-yet

slabs-laid-on-steps-not-cemented-between-slabs-yet

patio-behind-house-now-all-finished-cement-between-slabs-jointing

patio-behind-house-now-all-finished-cement-between-slabs-jointing