Tag Archives: tiles

Day 130 – Friday 13th January 2017 – phase 2

Day 130 – Friday 13th January 2017 – phase 2

Warning! A vast amount of scaffolding photos in this post.

scaffolding-delivery

Scaffolding arrived for phase 2

scaffolding-delivery-pic-2

Scaffolding truck

scaffolding-through-the-blinds-in-sitting-room

scaffolding-through-the-blinds-in-sitting-room

the-front-of-springdale-scaffolding-going-up-around-the-front-and-sides

The Front Of Springdale -Scaffolding-going-up-around-the-front-and-sides

c

Scaffolding around house – View from front garden

scaffolding

scaffolding

scaffolding-at-the-side

scaffolding-at-the-side

scaffolding-at-the-right-hand-side

scaffolding-at-the-right-hand-side

side-scaffolding

side-scaffolding

scaffolding-from-outside-along-left-side-of-house

scaffolding-from-outside-along-left-side-of-house

scaffolding-at-right-side-and-satellite-dish

scaffolding-at-right-side-and-satellite-dish

balcony-window-from-outside-not-in-great-condition

balcony-window-from-outside-not-in-great-condition

balcony-window-from-outside-not-in-great-condition-and-tiles-in-poor-state

balcony-window-from-outside-not-in-great-condition-and-tiles-in-poor-state

bottom-scaffolding

bottom-scaffolding

chimney-to-be-removed

chimney-to-be-removed

top-scaffolding-view-towards-fields-over-the-top-of-the-house

top-scaffolding-view-towards-fields-over-the-top-of-the-house

top-scaffolding-view-towards-fields-showing-chimney-that-is-to-be-removed

top-scaffolding-view-towards-fields-showing-chimney-that-is-to-be-removed

view-from-scaffolding-corner-potential-view

view-from-scaffolding-corner-potential-view

view-from-scaffolding

view-from-scaffolding

view-from-top-scaffolding

view-from-top-scaffolding

view-from-top-scaffolding-over-small-garage

view-from-top-scaffolding-over-small-garage

the-beginning-of-the-new-bedroom

the-beginning-of-the-new-bedroom

rock-wool-insulation-in-new-master-bedroom-extension

rockwool-insulation-in-new-master-bedroom-extension

old-chandelier-from-hall-and-old-water-tank-from-attic

old-chandelier-from-hall-and-old-water-tank-from-attic

Day 72 – Tuesday 18th October 2016

Day 72 – Tuesday 18th October 2016

beginning-of-celotex-insulation-between-roof-and-beams-in-utility-room-cut-around-extractor

beginning-of-celotex-insulation-between-roof-and-beams-in-utility-room-cut-around-extractor

plaster-board-for-walls-and-insulation-for-ceiling-has-been-delivered

plaster-board-for-walls-and-insulation-for-ceiling-has-been-delivered

wiring-for-floor-plug-socket-in-new-kitchen

wiring-for-floor-plug-socket-in-new-kitchen

roof-over-back-of-kitchen-nearly-complete-resized

roof-over-back-of-kitchen-nearly-complete

wire-for-outside-light-through-back-wall

wire-for-outside-light-through-back-wall

wire-for-outside-light-through-back-wall-on-other-side-of-patio-window

wire-for-outside-light-through-back-wall-on-other-side-of-patio-window

roof-sloping-down-to-flat-roof-nearly-complete

roof-sloping-down-to-flat-roof-nearly-complete

different-view-of-flat-roof-and-tiling-nearly-complete

different-view-of-flat-roof-and-tiling-nearly-complete

Day 66 – Monday 10th October 2016

Day 66 – Monday 10th October 2016

Progress on roof

the-roof-so-far-at-the-back-of-house-over-new-kitchen

the-roof-so-far-at-the-back-of-house-over-new-kitchen

corner-of-roof-adjacent-to-garage-and-sloping-onto-flat-roof

corner-of-roof-adjacent-to-garage-and-sloping-onto-flat-roof

corner-of-roof-adjacent-to-garage-and-sloping-onto-flat-roof-cemented-in

corner-of-roof-adjacent-to-garage-and-sloping-onto-flat-roof-cemented-in

new-and-old-corner-rosemary-tiles-the-old-ones-are-much-smaller-and-have-a-shallower-curve

new-and-old-corner-rosemary-tiles-the-old-ones-are-much-smaller-and-have-a-shallower-curve

new-kitchen-roof-sloping-to-flat-roof

new-kitchen-roof-sloping-to-flat-roof

 

Day 65 – Friday 7th October 2016

Day 65 – Friday 7th October 2016

Progress of tiling on new roof

roof-tiling-progress-adjacent-to-flat-roof

roof-tiling-progress-adjacent-to-flat-roof

roof-tiling-progress-adjacent-to-flat-roof-picture-2

roof-tiling-progress-adjacent-to-flat-roof-picture-2

roof-tiling-showing-progress-of-tiling-at-back-of-kitchen-roof

roof-tiling-showing-progress-of-tiling-at-back-of-kitchen-roof

roof-tiling-along-side-of-roof-adjacent-to-garage

roof-tiling-along-side-of-roof-adjacent-to-garage

inspection-of-work

inspection-of-work

lead-valley-down-side-of-hip-roof

lead-valley-down-side-of-hip-roof

lead-valley-down-left-side-of-hip-roof

lead-valley-down-left-side-of-hip-roof

progress-on-tiling-7-10-16

progress-on-tiling-7-10-16

Day 64 – Thursday 6th October 2016

Day 64 – Thursday 6th October 2016

Electrician today

electrician-came-today-and-started-wiring-kitchen

electrician-came-today-and-started-wiring-kitchen

wiring-for-cooker-and-sockets-above-work-top-eventually

wiring-for-cooker-and-sockets-above-work-top-eventually in this position

wiring-for-fridge

wiring-for-fridge

wiring-in-corner-of-kitchen-new-hall-door-will-be-located-to-the-left-of-this

wiring-in-corner-of-kitchen-new-hall-door-will-be-located-to-the-left-of-this

Outside work continues with the tiling of the new roof

hip-roof-tiled-and-lead-in-valley

hip-roof-tiled-and-lead-in-valley

Day 61 – Monday 3rd October 2016

Day 61 – Monday 3rd October 2016

Tiles starting to go on roof now

work-today-on-roof-tiles-on-righthand-side-roof-felt-on-peak-over-patio-doors-and-lead-in-valleys

work-today-on-roof-tiles-on-righthand-side-roof-felt-on-peak-over-patio-doors-and-lead-in-valleys

felt-on-new-hip-roof-and-lead-valley-on-right

felt-on-new-hip-roof-and-lead-valley-on-right

lead-valley-on-lefthand-side-of-hip-roof

lead-valley-on-lefthand-side-of-hip-roof

view-along-back-of-house-above-new-kitchen-and-main-bedroom

view-along-back-of-house-above-new-kitchen-and-main-bedroom

view-of-newly-tiled-righthandside-of-new-kitchen-roof

view-of-newly-tiled-right hand side-of-new-kitchen-roof

view-along-side-of-newly-tiled-kitchen-roof-towards-back-garden

view-along-side-of-newly-tiled-kitchen-roof-towards-back-garden

Day 46 – Wednesday 14th September 2016

Day 46 – Wednesday 14th September 2016

sloping-wall-corner-to-side-and-rear

sloping-wall-corner-to-side-and-rear

rosemary-tiles-for-new-roof-matching-old-tiles

rosemary-tiles-for-new-roof-matching-old-tiles

new-entrance-to-house-via-back-door-into-utility

new-entrance-to-house-via-back-door-into-utility

Block work now built up higher on left side of utility

lintel-above-new-back-door-area-and-wire-to-be-re-routed

lintel-above-new-back-door-area

Day 37 – Wednesday 31st August 2016

Day 37 – Wednesday 31st August 2016

Building Control Officer visited today to check on progress.

Also Bat licenced Ecologist came in the afternoon to supervise the removal of tiles from existing utility room roof and small bedroom roof as required by the bat licence.

Tiles removed over the utility room, picture taken from scaffolding

Tiles removed over the utility room, picture taken from scaffolding

Tiles removed from roof over small bedroom, this will be a new bathroom, picture taken from scaffolding

Tiles removed from roof over small bedroom, this will be a new bathroom, picture taken from scaffolding

Another view over utility room roof where tiles have been removed under supervision of bat ecologist

Another view over utility room roof where tiles have been removed under supervision of bat ecologist

Up on Scaffolding - Tiles all removed from old existing roof over utility room and small bedroom

Up on Scaffolding – Tiles all removed from old existing roof over utility room and small bedroom

View to main roof over existing master bedroom, this will be the new lounge

View to main roof over existing master bedroom, this will be the new lounge

View to garden from scaffolding above new kitchen

View to garden from scaffolding above new kitchen

View to back garden from scaffolding over new kitchen

View to back garden from scaffolding over new kitchen

View from scaffolding

View from scaffolding

New Fascia board partly in place over position for patio doors

New Fascia board partly in place over position for patio doors

Progress on the new step area from patio

Progress on the new step area from patio