Day 152 – Thursday 9th February 2017 – phase 2

Day 152 – Thursday 9th February 2017 – phase 2

the-initial-construction-of-the-dormer-in-the-left-side-of-the-new-bedroom-upstairs

the-initial-construction-of-the-dormer-in-the-left-side-of-the-new-bedroom-upstairs

dormer-side-shown-from-the-front-of-the-house

dormer-side-shown-from-the-front-of-the-house

the-sloping-roof-on-left-side-of-the-dormer

the-sloping-roof-on-left-side-of-the-dormer

new-upstairs-area-on-the-left-will-be-the-study-with-velux-window-on-the-right-a-new-ensuite-bathroom

new-upstairs-area-on-the-left-will-be-the-study-with-velux-window-on-the-right-a-new-ensuite-bathroom

new-velux-which-will-be-the-new-window-for-the-study

new-velux-which-will-be-the-new-window-for-the-study

left-gable

left-gable

gable-end-structure-on-the-left-side-of-house-under-construction

gable-end-structure-on-the-left-side-of-house-under-construction

flat-roof-area-between-steelbeams-now-also-under-construction

flat-roof-area-between-steel beams-now-also-under-construction

new-felt-and-batten-adjoining-the-new-roof-to-the-dormer-down-left-side-of-house-over-the-old-kitchen

new-felt-and-batten-adjoining-the-new-roof-to-the-dormer-down-left-side-of-house-over-the-old-kitchen

right-side-of-house-tiling-progress-is-fast

right-side-of-house-tiling-progress-is-fast

right-side-of-house-roof-felted-battened-and-tiles-going-on

right-side-of-house-roof-felted-battened-and-tiles-going-on

new-garage-light-with-sensor

new-garage-light-with-sensor fitted by Ballan Electrical

garage-light-with-sensor

garage-light-with-sensor

Day 151 – Wednesday 8th February 2017 – phase 2

Day 151 – Wednesday 8th February 2017 – phase 2

view-of-inside-of-new-upstairs-from-right-the-progress-so-far

view-of-inside-of-new-upstairs-from-right-the-progress-so-far

rafters-on-the-left-side-of-the-house-in-place

rafters-on-the-left-side-of-the-house-in-place

the-left-side-of-the-house-start-of-the-dormer-window

the-left-side-of-the-house-start-of-the-dormer-window

the-left-side-of-the-house-start-of-the-dormer-window-pic-2

the-left-side-of-the-house-start-of-the-dormer-window-pic-2

second-ridge-beam-in-place-where-left-hand-gable-will-be-positioned

second-ridge-beam-in-place-where-left-hand-gable-will-be-positioned

view-of-2nd-ridge-beam-from-right

view-of-2nd-ridge-beam-from-right

Day 149 -Monday 6th February 2017 – phase 2

Day 149 -Monday 6th February 2017 – phase 2

kymin-walk-canopy-in-white-visible-from-hillside

Kymin walk – View down hillside – canopy of Springdale visible as big white roof

zoomed-in-photo-of-canopy-from-hillside-above-the-house

zoomed-in-photo-of-canopy-from-hillside-above-the-house

left-side-of-roof-beside-lower-level-scaffolding

left-side-of-roof-beside-lower-level-scaffolding

on-scaffolding

on-scaffolding

velux-window-frame-work-created

velux-window-frame-work-created

new-wall-partition-created-between-new-eaves-and-bathroom-and-study-room-which-will-have-a-sloping-roof

new-wall-partition-created-between-new-eaves-and-bathroom-and-study-room-which-will-have-a-sloping-roof

framework-for-wall-of-bathroom-upstanding-wooden-batons

framework-for-wall-of-bathroom

view-from-left-side-of-house-across-new-upstairs-area-part-of-left-side-of-roof-now-removed-pic-2

view-from-left-side-of-house-across-new-upstairs-area-part-of-left-side-of-roof-now-removed-pic-2

view-from-left-side-of-huse-across-new-upstairs-area-part-of-left-side-of-roof-now-removed

view-from-left-side-of-house-across-new-upstairs-area-

left-side-of-upstairs-area-pic-2

left-side-of-upstairs-area-pic-2

left-side-of-upstairs-area

left-side-of-upstairs-area

Day 146 – Wednesday 1st February 2017 – phase 2

Day 146 – Wednesday 1st February 2017 – phase 2

glimpse-of-new-bedroom-through-gap-in-old-hall-ceiling-flooring-down

glimpse-of-new-bedroom-through-gap-in-old-hall-ceiling-flooring-down

view-from-gap-in-flooring-to-bathroom-area

view-from-gap-in-flooring-to-bathroom-area

view-from-gap-in-flooring-to-bedroom-windows

view-from-gap-in-flooring-to-bedroom-windows

view-from-right-across-floored-upstairs

view-from-right-across-floored-upstairs

view-through-middle-window-from-scaffolding-of-right-side-of-bathroom-and-study

view-through-middle-window-from-scaffolding-of-right-side-of-bathroom-and-study

view-from-scaffolding-through-middle-window-to-back-of-new-bedroom-and-covered-area-of-staircase

view-from-scaffolding-through-middle-window-to-back-of-new-bedroom-and-covered-area-of-staircase

view-to-left-side-of-bedroom-and-flooring-base

view-to-left-side-of-bedroom-and-flooring-base

left-side-of-bedroom-not-floored-yet-beams-down

left-side-of-bedroom-not-floored-yet-beams-down

view-through-to-left-side-of-bedroom

view-through-to-left-side-of-bedroom

right-side-of-house

right-side-of-house

view-from-left-side-of-house-from-scaffolding

view-from-left-side-of-house-from-scaffolding

rubble-and-remnants-of-old-loft

rubble-and-remnants-of-old-loft

old-rafters-and-wood-removed-from-house

old-rafters-and-wood-removed-from-house

Day 145 – Tuesday 31st January 2017 – phase 2

Day 145 – Tuesday 31st January 2017 – phase 2

Roof tiles all stripped off today under supervision from bat licensed ecologist. Balcony window taken out and flat roof taken off.  From phase 1, worktop for new kitchen which had been measured and cut to size has now been fitted.

newly-fitted-worktop-for-kitchen-and-island-unit

newly-fitted-worktop-for-kitchen-and-island-unit

new-worktop-fitted

New worktop fitted – a transformation

balcony-window-now-removed-view-through-to-new-bedroom-floor

balcony-window-now-removed-view-through-to-new-bedroom-floor and through to hall below

left-side-of-house-tiles-stripped-under-supervision-of-a-bat-licensed-ecologist

left-side-of-house-tiles-stripped-under-supervision-of-a-bat-licensed-ecologist

left-and-front-stripped-of-tiles

left-and-front-stripped-of-tiles

right-side-of-house-tiles-all-stripped-off

right-side-of-house-tiles-all-stripped-off

view-of-stripped-roof-from-left

view-of-stripped-roof-from-left

view-into-house-over-old-porch

view-into-house-over-old-porch

view-of-what-will-be-new-bedroom-floor

view-of-what-will-be-new-bedroom-floor

view-through-gap-that-will-be-middle-window-in-the-bedroom

view-through-gap-that-will-be-middle-window-in-the-bedroom

view-through-gap-which-will-be-new-ensuite-bathroom-window

view-through-gap-which-will-be-new-ensuite-bathroom-window

top-of-roof-now-to-compare-later-when-new-roof-is-on

top-of-roof-now-to-compare-later-when-new-roof-is-on

view-from-front-through-to-house-from-scaffolding-of-the-inside-where-the-old-balcony-has-been-removed

view-from-front-through-to-house-from-scaffolding-of-the-inside-where-the-old-balcony-has-been-removed

gap-from-below-seen-in-previous-pictures-as-light-shining-through-from-house

gap-from-below-seen-in-previous-pictures-as-light-shining-through-from-house

tiles-all-stacked-to-be-reused-for-new-roof

tiles-all-stacked-to-be-reused-for-new-roof

tiles-all-stacked-to-be-reused-for-new-roof-down-side-of-scaffolding

tiles-all-stacked-to-be-reused-for-new-roof-down-side-of-scaffolding

Day 143 – Saturday 28th January 2017 – phase 2

Day 143 – Saturday 28th January 2017 – phase 2

Split levels – ground floor and new upstairs visible together

picure-showing-opening-for-the-staircase-the-floor-below-and-the-upstairs-area-expanding

picure-showing-opening-for-the-staircase-the-floor-below-and-the-upstairs-area-expanding

new-upstairs-area-around-where-the-top-of-the-staircase-will-be

new-upstairs-area-around-where-the-top-of-the-staircase-will-be

this-is-the-old-balcony-window-still-intact-at-present-with-gap-to-hall-below-just-in-front-through-the-window-the-small-steel-can-be-seen-staddling-the-porch-to-form-the-new-front-of-the-house

this-is-the-old-balcony-window-still-intact-at-present-with-gap-to-hall-below-just-in-front-through-the-window-the-small-steel-can-be-seen-straddling-the-porch-to-form-the-new-front-of-the-house

photo-through-gap-in-the-new-flooring-showing-the-inner-porch-door-below

photo-through-gap-in-the-new-flooring-showing-the-inner-porch-door-below

steel-beam-number-1-showing-it-on-the-inside-of-house-from-upstairs-area

steel-beam-number-1-showing-it-on-the-inside-of-house-from-upstairs-area

view-from-the-orchard-field-down-over-the-the-house-where-the-canopy-can-be-seen-over-the-top

view-from-the-orchard-field-down-over-the-the-house-where-the-canopy-can-be-seen-over-the-top

view-of-back-of-house-new-kitchen-and-canopy-visible-over-the-top-of-main-house-pic-2

view-of-back-of-house-new-kitchen-and-canopy-visible-over-the-top-of-main-house-pic-2

view-of-back-of-house-new-kitchen-and-canopy-visible-over-the-top-of-main-house

view-of-back-of-house-new-kitchen-and-canopy-visible-over-the-top-of-main-house

view-of-back-of-house-and-new-kitchen

view-of-back-of-house-and-new-kitchen

Day 142 – Friday 27th January 2017 – phase 2

Day 142 – Friday 27th January 2017 – phase 2

A full day of completing the scaffolding and canopy over the house

canopy-beginning-to-go-over-house

canopy-beginning-to-go-over-house

canopy-from-the-right

canopy-from-the-right

canopy-from-the-front

canopy-from-the-front

canopy-completed-showing-left-side-of-house-and-the-water-containers-which-hold-scaffolding-in-place

canopy-completed-showing-left-side-of-house-and-the-water-containers-which-hold-scaffolding-in-place

beams-and-new-window-gaps-under-the-canopy-window-fitter-came-out-and-measured-these-gaps-for-windows-today

beams-and-new-window-gaps-under-the-canopy-window-fitter-came-out-and-measured-these-gaps-for-windows-today

beams-under-canopy-and-another-pic

beams-under-canopy-and-another-pic

beams-under-canopy-another-pic

beams-under-canopy-another-pic

inside-canopy-on-scaffolding-left-side-of-house

inside-canopy-on-scaffolding-left-side-of-house

two-beams-now-under-canopy

two-beams-now-under-canopy

view-down-to-garages-below-and-skip

view-down-to-garages-below-and-skip

Day 141 – Thursday 26th January 2017 – phase 2

Day 141 – Thursday 26th January 2017 – phase 2

A very important day for the build – the huge new steel beams lifted into the correct position, more scaffolding going up, a 2 day job with 4 men to create a canopy right over the house, which will mean that work is not so weather dependent and the house will be more protected when the roof comes off.  Also from phase 1, air vents over flat utility room roof going in, to try and allow air to flow and to stop build up of condensation.

ab-crane-for-lifting-steel-beams

High Ab Crane for lifting the Steel Beams

crane-house-beams-and-men-preparing-for-lift

Pre-preparation of crane, house and roof, and the beams

steel-beams-on-grass-ready-for-lift-into-position

Steels on the grass ready for lift onto roof and final position

steel-beams-with-slings

Steel beams with slings

supporting-stand-for-crane

Supporting stand for crane

steel-beams-showing-the-size-and-length

Steel beams showing their full size and length

beams-propped-up-ready-for-pick-up-by-crane

Beams propped up ready for lift by crane

builder-cutting-away-roof-ready-for-beam-to-go-into-house

Builder now cutting into roof, where tiles have been removed previously, for beam to inserted onto a prepared strengthened area on an existing original wall of the house

control-of-direction-of-beam-using-rope

Crane begins lift via radio control, operator in high viz jacket whilst the other builder controls the direction of the beam using an attached guide rope

control-of-direction-of-beam-using-rope-pic-2

Beam is lifted

control-of-direction-of-beam-using-rope-pic-3

direction still controlled by rope

control-of-direction-of-beam-using-rope-pic-4

beam rising

beam-going-up

First beam going up

beam-going-up-2

Beam going up pic 2

beam-going-up-3

beam-going-up-3

beam-going-up-4

Beam going up pic 4

beam-going-up-5

Beam going up pic 5

beam-going-up-10

Beam going up pic 6

beam-going-up-11

Beam going up pic 7

beam-going-up-8

Beam going up pic 8

beam-being-maneouvred-10

manoeuvring beam

beam-being-maneouvred-9

beam going into position

beam-being-maneouvred-6

view of crane

beam-going-up-9

Beam going up pic 9 – wrong angle – beam has to be readjusted

beam-being-maneouvred-to-get-a-better-angle-to-put-into-place

Steel beam has to be repositioned as scaffolding is preventing the beam from locating in its correct position in the roof

beam-being-manoeuvred-11

Beam being manoeuvred over scaffolding

beam-being-maneouvred-12

Beam being manoeuvred

beam-being-maneouvred-13

beam now at correct angle to be manoeuvred into position

beam-being-maneouvred-7

close up

beam-being-maneouvred-4

manoeuvring beam

maneouvred-into-position-1

manoeuvred-into-position-1

maneouvred-into-position-2

manoeuvred-into-position-2

maneouvred-into-position-3

manoeuvred-into-position-3

first-beam-in-place

First beam in place

first-beam-in-place-pic-2

Pictures from scaffolding of the first beam in place – pic 2

first-beam-in-place-pic-3

first-beam-in-place-pic-3

first-beam-in-place-pic-4

first-beam-in-place-pic-4

position-for-second-beam

beam 2 to go here

preparing-roof-for-beam-2

preparing-roof-for-beam-2

second-beam-being-craned-in-pic-2

Second beam being craned in

second-beam-being-craned-in-pic-3

second-beam-being-craned-in-pic-3

second-beam-being-craned-in-pic-4

second-beam-being-craned-in-pic-4

second-beam-being-craned-in

second-beam-being-craned-in

second-beam-being-craned-in-pic-5

second-beam-being-craned-in-pic-5

second-beam-going-into-position-pic-2

second-beam-going-into-position

second beam in position

second beam in position

second-beam-going-into-position-pic-3

different view of beam 2

two-new-steel-beams-in-place

Two new steel beams in place under new scaffolding

two-new-steel-beams-in-place-pic-3

two-new-steel-beams-in-place-pic-3

two-new-steel-beams-in-place-pic-2

two-new-steel-beams-in-place-pic-2

steel-beam-number-2-in-position

steel-beam-number-2-in-position

steel-beam-number-2-in-position-pic-2

steel-beam-number-2-in-position-pic-2

More scaffolding going up to create a canopy over house

scaffolders

scaffolding  arrives

scaffolders-move-truck-to-drive-2-days-construction-ahead

scaffolders-move-truck-to-driveway -2-days-construction-ahead

scaffold

scaffold unloading

scaffolders-pic-2

unloading scaffolding

scaffolders-and-one-ton-water-containers-to-hold-scaffolding-and-canopy-securely

scaffolders-and-one-ton-water-containers-to-hold-scaffolding-and-canopy-securely

next-phase-of-scaffolding-with-water-container-1-ton-weights

next-phase-of-scaffolding-with-water-container-1-ton-weights

new-scaffolding-going-up-to-cover-house

new-scaffolding-going-up-to-cover-house

new-scaffolding-going-up-to-cover-house-pic-3

new-scaffolding-going-up-to-cover-house-pic-3

new-scaffolding-going-up-to-cover-house-pic-2

new-scaffolding-going-up-to-cover-house-pic-2

water-containers-to-act-as-weights-to-keep-canopy-and-scaffolding-secure

water-containers-to-act-as-weights-to-keep-canopy-and-scaffolding-secure

fibre-glass-roof-and-new-condensation-vents-pic-2

Phase 1 the fibre-glass-roof-and-new-condensation-vents-to try to eliminate damp patches on utility ceiling

fibre-glass-roof-and-new-condensation-vents

fibre-glass-roof-and-new-condensation-vents

pointing-on-roof-tiles-over-new-kitchen

Phase 1 pointing-on-roof-tiles-over-new-kitchen

view-of-new-kitchen-roof-in-red-beyond-scaffolding

view-of-new-kitchen-roof-in-red-beyond-scaffolding

steel-beam-number-1-from-inside-house-pic-2

steel-beam-number-1-from-inside-house-pic-2

steel-beam-number-1-from-inside-house

steel-beam-number-1-from-inside-house

 

 

Day 134 – Thursday 19th January 2017 – phase 2

Day 134 – Thursday 19th January 2017 – phase 2

progress-on-day-134-formation-of-upstairs-windows

progress-on-day-134-formation-of-upstairs-windows

progress-on-day-134-formation-of-upstairs-windows-pic-2

progress-on-day-134-formation-of-upstairs-windows-pic-2

side-view-of-new-upstairs

side-view-of-new-upstairs

opening-for-middle-window

opening-for-middle-window

view-looking-down-from-top-scaffolding-onto-old-balcony-window

view-looking-down-from-top-scaffolding-onto-old-balcony-window

view-looking-down-from-top-scaffolding-onto-old-balcony-window-also-showing-areas-of-roof-that-have-been-prepared-for-new-steel-beam

view-looking-down-from-top-scaffolding-onto-old-balcony-window-also-showing-areas-of-roof-that-have-been-prepared-for-new-steel-beam

view-from-the-right-hand-side-of-house-steel-beams-in-brown-now-at-the-bottom-of-the-wall

view-from-the-right-hand-side-of-house-steel-beams-in-brown-now-at-the-bottom-of-the-wall

view-of-the-new-wall-from-the-left-side-of-the-scaffolding

view-of-the-new-wall-from-the-left-side-of-the-scaffolding

view-of-right-hand-side-of-roof

view-of-right-hand-side-of-roof

view-of-double-wall-built-on-top-of-new-steel-beam-at-the-front-of-the-house-and-pitched-roof-covered-to-protect-from-the-weather-roof-felt-is-in-poor-condition-probably-the-original-roofing-felt

view-of-double-wall-built-on-top-of-new-steel-beam-at-the-front-of-the-house-and-pitched-roof-covered-to-protect-from-the-weather-roof-felt-is-in-poor-condition-probably-the-original-roofing-felt

view-from-the-right-hand-side-of-house-showing-double-wall-and-exposed-roof-covered

view-from-the-right-hand-side-of-house-showing-double-wall-and-exposed-roof-covered

left-hand-side-of-roof

left-hand-side-of-roof

Day 133 – Wednesday 18th January 2017 – phase 2

Day 133 – Wednesday 18th January 2017 – phase 2

progress-after-day-133-new-wall-going-up-over-new-supporting-beam-at-front-of-house

progress-after-day-133-new-wall-going-up-over-new-supporting-beam-at-front-of-house

front-of-house-so-far-with-new-wall

front-of-house-so-far-with-new-wall

new-wall-over-new-supporting-beam-over-old-porch-roof

new-wall-over-new-supporting-beam-over-old-porch-roof

another-view-of-new-wall-over-old-porch

another-view-of-new-wall-over-old-porch

new-supporting-beam-as-seen-from-right-side-of-scaffolding

new-supporting-beam-as-seen-from-right-side-of-scaffolding

new-wall-over-right-side-of-house-front

new-wall-over-right-side-of-house-front

left-side-of-house-from-scaffolding-showing-new-wall-going-up-over-the-front-of-the-house-on-the-new-support-beam

left-side-of-house-from-scaffolding-showing-new-wall-going-up-over-the-front-of-the-house-on-the-new-support-beam

left-side-where-tiles-were-removed-yesterday-for-insertion-of-the-large-supporting-steel-next-week

left-side-where-tiles-were-removed-yesterday-for-insertion-of-the-large-supporting-steel-next-week

area-of-roof-where-tiles-were-removed-yesterday-with-bat-ecologists-this-is-where-a-huge-steel-beam-will-be-inserted-into-the-house-for-the-support-of-the-roof-and-the-new-wall-will-be-built-on-top

area-of-roof-where-tiles-were-removed-yesterday-with-bat-ecologists-this-is-where-a-huge-steel-beam-will-be-inserted-into-the-house-for-the-support-of-the-roof-and-the-new-wall-will-be-built-on-top

right-side-of-house-roof

right-side-of-house-roof

top-of-old-balcony-window-just-visible-from-scaffolding

top-of-old-balcony-window-just-visible-from-scaffolding

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area-pic-2

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area-pic-2

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area-pic-3

area-inside-where-roof-beams-have-been-cut-away-at-centre-back-grey-area-pic-3