Day 90 – Thursday 10th November 2016

blanket-insulation-in-sloping-roof-covered-by-plasterboard

close-up-of-blanket-insulation-above-patio-doors

view-through-new-kitchen-patio-windows-up-the-hillside-lovely-autumnal-day

blanket-insulation-in-sloping-roof-covered-by-plasterboard

close-up-of-blanket-insulation-above-patio-doors

view-through-new-kitchen-patio-windows-up-the-hillside-lovely-autumnal-day

new-loft-area-over-new-kitchen

new-loft-area-over-new-kitchen-pic2

new-loft-area-over-new-kitchen-pic3

new-loft-area-from-new-kitchen-to-old-existing-roof

mess-after-holes-drilled-for-new-doorway-from-hall-to-new-kitchen

holes-in-wall-ready-for-doorway-to-be-cut-through-pic-3

holes-in-wall-ready-for-doorway-to-be-cut-through-pic-2

holes-in-wall-ready-for-doorway-to-be-cut-through

New step built into new bathroom

plasterboard-and-plastering-around-new-doorway-into-new-bathroom

kitchen-at-present

Made Cotswold Crunch bread whilst waiting for the plumber!

new-bathroom-plasterboarding-double-in-places-to-fill-gaps

new-bathroom-plasterboarding

new-door-frame-around-new-bathroom-door-picture-2

new-door-frame-around-new-bathroom-door

new-door-frame-around-new-kitchen-door-top-of-steps

foil-insulation-in-corner-of-kitchen

foil-insulation-in-left-corner-of-kitchen

Holes cut in plasterboard for lighting – lots-of-it!

foil-insulation-going-into-sloping-roof-of-kitchen

foil-insulation-in-kitchen

wiring-holes-in-plasterboard

wiring-through-plasterboard-ceiling

ridge-tiles-nearing-completion
Day 83 – Monday 31st October 2016

back-right-kitchen-corner-now-plasterboarded

double-plasterboarding-under-lintel

front-right-kitchen-corner-now-plasterboarded

utility-room-now-plasterboarded
Plumber today, connecting up pipework under the house.

New drainage pipe for a sink in the utility room and hot and cold water pipes

In new bathroom the pipes-for-towel-rail-capped

pipework-in-place-for-new-bath-in-bathroom

old-radiator-in-utility-reconnected-now-re-routed-under-house

pipework-through-wall-to-new-kitchen

pipework-for-radiator-under-the-window-in-the-new-kitchen-capped

pipework-capped-ready-for-large-radiator-in-new-kitchen-this-blockwork-was-the-old-small-bedroom-window
Patio doors for kitchen arrived today

new-patio-doors-in-new-kitchen-from-inside

New patio doors minus the apex window on order fitted by Clive and Chris

new-patio-doors-to-new-kitchen-from-outside

new-patio-doors-to-new-kitchen-from-outside-2

Spot Marcus, our plumber, in a very tight spot, under the floor in the new bathroom

under-the-new-bathroom-floor-where-toilet-and-sink-will-go

drain-and-pipework-under-floor

under-the-new-bathroom-floor-where-bath-will-be-positioned

new-plasterboard-ceiling-in-utility-room

new-plasterboard-ceiling-in-new-bathroom

new-plasterboard-ceiling-in-entrance-to-kitchen-beneath-flat-roof