Day 192 – Wednesday 26th April 2017 – phase 2

Bathroom upstairs partly tiled and floor boarded, screwed down and tiled over, by Marcus Kelly, plumber and Josh

Upstairs bathroom progress so far

Bathroom upstairs partly tiled and floor boarded, screwed down and tiled over, by Marcus Kelly, plumber and Josh

Upstairs bathroom progress so far

View of Springdale from the front with boarded up old porch now ready for demolition of wall inside

Springdale-on-the-first-of-March-2017

old-porch-wall-inside-ready-for-demolition

old-radiators-from-hallway

old-porch-boarded-up inside

front-of-house-boarded-up-ready-for-demolition-of-wall-inside View from the outside

looking-down-from-scaffolding-to-boarded-up-front

dormer-lead-around-window

dormer-sides-lined-with-lead

rendering-applied-today-as-seen-throught-the-scaffolding

rendering-as-seen-from-second-level-of-the-scaffolding-looks-perfect

rendering-as-seen-from-second-level-of-the-scaffolding-pic-3

rendering-pic-4

view-of-bedroom-and-dormer-more-plastering-completed-today

view-of-2-bedroom-windows-and-new-plastering

wall-channelled-out-for-plug-sockets

entrance-to-study

new waste-pipe-installed and connected-to-new downpipe-which-has-been-connected-to-the-house-drains

waste-downpipe-connected-to-vent-with-birds-nest-top

shower-waste-and-wash-hand-basin-waste-water-pipe-in-white-connected-to-the-waste-pipe-under-the-guttering

waste pipe from new upstairs toilet as yet not installed

white-waste-pipe-coming-from-right-to-left-join-waste-pipe-from-shower-and-then-flows-through-to-main-waste-pipe-outside

Plumbing pipes under old ceiling of the old porch. Middle pipe is the cold water supply to the upstairs toilet. Right of the beam is the hot and cold supply of water to the wash basin. Short pipe is the radiator pipe to the bedroom.
Windows arrived today. Most of plaster boarding was finished. Looking brilliant.

Bathroom window fitted with obscure glass

small-bedroom-window-installed

large-bedroom-window-installed

view-from-back-of-bedroom-to-front 3 windows all just visible in this picture Dormer window boarded up till window is ready

progress-on-the-bedroom-ready-for-plasterers. Dormer window on the right – the brown wood area

bedroom-dormer-boarded-up-till-window-is-ready. Pink plasterboard over the beam

bedroom-view-from-ensuite-pink-plasterboard-is-firelined-to-protect-beams

study-area-plaster boarded

ladders-to-bedroom