Day 131 -Monday 16th January 2017 – phase 2
Small steel beams arrived and preparation for insertion, also blocks for gable delivered

Blocks in place ready for start of gable

bedroom-area

attic-area-cleared-out

area-where-study-will-be
Small steel beams arrived and preparation for insertion, also blocks for gable delivered

Blocks in place ready for start of gable

bedroom-area

attic-area-cleared-out

area-where-study-will-be
Wet day – Work limited to undercover. Skylight gap previously covered in tarpaulin was recovered with board. This will be fitted and sealed within the next few days, so should soon be water tight. Hole was cut for doorway to new bathroom. Bricks laid to fill gap over new lintel above the new back door. Old bedroom window now blocked in. Photos below.

old-bedroom-window-blocked-up

old-little-bedroom-with-window-blocked-up-and-brickwork-cut-to-the-left-to-form-a-new-doorway-into-the-utility-room

new-doorway-cut-into-old-bedroom-which-will-be-new-bathroom-picture-taken-from-utility-side

sloping-wall-corner-to-side-and-rear

rosemary-tiles-for-new-roof-matching-old-tiles

new-entrance-to-house-via-back-door-into-utility
Block work now built up higher on left side of utility

lintel-above-new-back-door-area
Progress on steps today

Step progress

Step progress 2
Removal of roof tiles with bat ecologist on site

Ecologist on site

Tile Removal with supervision 2

Tile Removal with supervision




Progress of retaining wall

Ground drains

Inside Kitchen Area

Top of patio doors

Top of patio doors 2
Work continues on the permitted part of the new roof. No parts of the old roof may be touched without supervision from a bat licenced ecologist.


Work on retaining wall begins

Retaining Wall

New retaining wall


Between New Kitchen and Garage

New entrance to kitchen from utility room

Corner of New Kitchen

Day 20 – Progress so far

Scaffolding around back

View along back of house day 20
Kitchen area is taking shape




Scaffolding ready


Area for Lintl





Delivery of building materials
Foundations are all hardened and ready for building

Blocks all ready for building

Delivery of building materials