Day 17 – Monday 1st August 2016

Day 17 – Monday 1st August 2016

Very wet day

Insulation beginning and more work on drains

August 1st - pic 1

More blocks being delivered Truck size is limited by width of drive Therefore that limits weight that can be delivered

August 1st - pic 2

Bricks stacked to hand for builder

August 1st - pic 3

Insulation – celotex repels water

August 1st - pic 4

Rain stops play again

August 1st - pic 5

A whole lot of rain

August 1st - pic 6

Insulation between double block work

Day 3 – Digging out resumes

Friday July 1st

Weather forecast was correct.  Lots of very heavy rain over the past 2 days.

State of play after today’s work is shown in the photos below.

Large pieces of concrete found in ground needed a jackhammer drill to break them up into moveable chunks

Ramp to garden and fields

View of trenches so far from patio