Day 70 – Friday 14th October 2016

Day 70 – Friday 14th October 2016

Indoor work today – builder and plumber

bedroom-prepared-for-removal-of-window

bedroom-prepared-for-removal-of-window

window-before-removal-between-kitchen-and-bedroom

window-before-removal-between-kitchen-and-bedroom

blocked-up-window-between-new-kitchen-and-bedroom-from-bedroom-side

After! blocked-up-window-between-new-kitchen-and-bedroom-from-bedroom-side

blocked-up-window-between-new-kitchen-and-bedroom

After blocked-up-window-between-new-kitchen-and-bedroom

wall-partly-cut-in-readiness-for-new-door-to-kitchen-from-hallway

wall-partly-cut-in-readiness-for-new-door-to-kitchen-from-hallway

kitchen-now-cleared-of-scaffolding-and-building-materials

kitchen-now-cleared-of-scaffolding-and-building-materials

new-pipework-for-hot-and-cold-water-to-new-kitchen-and-gas-to-gas-cooker-partly-installed

new-pipework-for-hot-and-cold-water-to-new-kitchen-and-gas pipe -to-gas-cooker-partly-installed

gas-and-water-supply-pipes-partly-installed-for-new-kitchen-through-new-wall

gas-and-water-supply-pipes-partly-installed-for-new-kitchen-through-new-wall

Day 60 – Friday 30th September 2016

Day 60 – Friday 30th September 2016

leaking-skylight

Leaking Skylight. Heavy rain overnight and water has been dripping through the skylight in one corner. The bubble has now been fixed on over the top so this should stop the problem

felt-nearly-completed-shown-from-inside-of-new-kitchen

felt-nearly-completed-shown-from-inside-of-new-kitchen

felt-from-inside-of-new-kitchen

felt-from-inside-of-new-kitchen

view-of-main-bedroom-through-window-to-be-blocked-up-scaffolding-still-in-place-inside

view-of-main-bedroom-through-window-to-be-blocked-up-scaffolding-still-in-place-inside

view-of-back-of-house-showing-completed-felt-and-battening

view-of-back-of-house-showing-completed-felt-and-battening

view-of-back-of-house-showing-valley-in-the-middle-between-the-two-roofs

view-of-back-of-house-showing-valley-in-the-middle-between-the-two-roofs

top-of-drive-in-front-of-double-garage-with-materials-and-new-roof-structure-with-felt-and-battening-between-house-and-garage

top-of-drive-in-front-of-double-garage-with-materials-and-new-roof-structure-with-felt-and-battening-between-house-and-garage

materials still to be used at the top of the drive and top of the new kitchen roof can be seen with felt and battening

top-of-drive-in-front-of-double-garage-with-materials

top-of-drive-in-front-of-double-garage-with-materials