Day 21 – Friday 5th August 2016

Day 21 – Friday 5th August 2016

Checking new lintel

Checking new lintel

Concrete slab for utility

Concrete slab for utility

View of garage through new kitchen

View of garage through new kitchen

Looking through new window position

Looking through new window position

Over the top

Top of new kitchen

View from kitchen through patio door to steps

View from kitchen through patio door to steps eventually

View of back garden

View of back garden

View of patio through scaffolding

View of patio through scaffolding

View of polytunnel from top of scaffolding

View of polytunnel from top of scaffolding

View over garden to field 2

View over garden to field 2

View to new kitchen window position

View to new kitchen window position

Day 11 -Thursday 14th July

Day 11 – Thursday 14th July

Brickwork is now in place as far as possible.

The next step is to order the block and beams for the flooring.

foundations behind new lounge

Foundations behind new lounge, currently a bedroom

 

 

Day 8 – Friday 8th July

Friday 8th July – Day 8

Concrete filling

‘Before’ pictures

‘During’ pictures

Gate had to be removed

Gate off

Pipes laid for pumping concrete

Concrete pump started up

Trenches being filled

More concrete arriving

Levelling concrete to peg height

More concrete filling

more concrete filling

Tapping out air bubbles and smoothing

Finishing off and creating a working area

‘After’ Pictures

Finished Foundations

A great morning’s work!

 

 

 

Day 7 – Thursday 7th July

Thursday 7th July 2016

All areas are now prepared for concrete.

The Building Control Officer has been to inspect the excavation and everything is in order.

Photos below

ready for concrete

ready for concrete

 

 

 

 

 

 

ready for concrete 2

ready for concrete 2

 

 

 

 

 

 

ready for concrete 3

ready for concrete 3