Day 173 – Thursday 9th March 2017 – phase 2

Day 173 – Thursday 9th March 2017 – phase 2

Downstairs sun lounge back wall plastered

Downstairs sun lounge back wall plastered

New sun lounge another wall skimmed with plaster

New sun lounge another wall skimmed with plaster

More plastered wall in new sun lounge

More plastered walls in new sun lounge

Plastering around the top of the staircase position

Plastering around the top of the staircase position

Plastering now completed around the dormer window

Plastering now completed around the dormer window

Work on dormer felt and batten at sides

Work on dormer –  membrane and batten has been fixed on at the sides

painting of upstairs bedroom continuing

painting of upstairs bedroom continuing

View from back of bedroom to front, not all painted yet, some areas with only first coat

View from back of bedroom to front, not all painted yet, some areas with only first coat

Side of dormer window, felt and batten on sides

Side of dormer window, membrane and batten on sides

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s