Day 147 – Thursday 2nd February 2017 – phase 2

New flat roof under construction and view into what will be the master bedroom. This is tied into the top of the existing roof.

view-over-newly-created-flat-roof

view-over-newly-created-flat-roof-another-angle

Beams now inserted in between steel beams to form the structure of the flat roof

New roof rafters on the left side of the house. These have been attached to the newly inserted ridge board that will come out to the front of the house and form the top of the pitched roof and gable end on the right hand side

rafters on the right hand side of the house attached to the ridge board, pic 2

bathroom-window opening -to-be-slightly-altered-as-roof-rafters clip- the edge-of- the window

Bathroom window pic 2

rafters to ridge board viewed form left side. Cross beams notched into steel

view of rafters through bathroom window opening. Edge of bathroom can be seen marked out with wood in flooring

View into bedroom from the right

View through left window to newly created bedroom floor space

new-drawer-unit-in-kitchen-island-fitted-out-with-worktop-for-scone-and-pastry-making-at-a-good-working-height

new-drawer-unit-in-kitchen-island-fitted-out-with-worktop