BUILDING WORK

 

Monday 27th June 2016 – Sunday 12th March 2017

Our long awaited extension is starting today.

Beginning with a new kitchen!

Before work starts

Back of Springdale

Back of Springdale

The back of Springdale

The area in front of the fence will be dug

out until it is in line with the room with

the patio doors.

The small patio

The small patio and wall will be removed

 

 

 

 

 

 

 

The kitchen will stretch from the

table and chairs as far as the end of the wall

that can be seen on the right.

Digger for ground works

Digger for ground works

 

 

 

 

 

 

Monday 27th June 2016

Machinery arrived. Weather lovely. Forecast is not for the rest of the week.

Photos showing the story of today

Digger Commencing Work

Digger Commencing Work

Dumper Truck to take soil to the field

Dumper Truck to take soil to the field

Excavation Begins

Excavation Begins

Digging up the Lawn

Digging up the Lawn

Extremely large dumper takes soil to the field

Extremely large dumper takes soil to the field

Huge Machinery

Huge Machinery

New Patio Area

New Patio Area

New trench dug

New trench dug

New Trench looking towards Original Patio

New Trench looking towards Original Patio

Demolition of Wall

Demolition of Wall

New Road! Tyre tracks

New Road! Tyre tracks

Tracks to field where sub soil will be buried

Tracks to field where sub soil will be recycled

View from trench

View from trench

View from trench, potential for steps here

View from trench, potential for steps here

View along back of garage

View along back of garage

Couldn't resist having a go!

Couldn’t resist having a go!

Excavation Continues -Day 2

Heavy rain forecast.

By 1pm rain stopped play.

The photos below show the work completed today.

Demolishing remains of wall

Digger in action

Wall removed around house

Dumper close to house

Rain stops play

Slippery slope

Muddy

Wet trench

Day 3 – Digging out resumes

Weather forecast was correct.  Lots of very heavy rain over the past 2 days.

State of play after today’s work is shown in the photos below.

Large pieces of concrete found in ground needed a jackhammer drill to break them up into moveable chunks

Ramp to garden and fields

View of trenches so far from patio

Monday July 4th

The forecast was dry.

Here are photos for Monday’s work:

Digger at work

Digger at work

Day 5 and 6 – Tuesday 5th July and Wednesday 6th July

Lots of changes to be seen now.

Foundations are really taking shape.

Photos below

Building Control Officer will come to inspect the foundations tomorrow

Thursday 7th July 2016

All areas are now prepared for concrete.

The Building Control Officer has been to inspect the excavation and everything is in order.

Photos below

ready for concrete

ready for concrete

ready for concrete 2

ready for concrete 2

ready for concrete 3

ready for concrete 3

Day 8 – Friday 8th July

Friday 8th July – Day 8

Concrete filling

‘Before’ pictures

‘During’ pictures

Gate had to be removed

Gate off

Pipes laid for pumping concrete

Concrete pump started up

Trenches being filled

More concrete arriving

Levelling concrete to peg height

More concrete filling

more concrete filling

Tapping out air bubbles and smoothing

Finishing off and creating a working area

‘After’ Pictures

Finished Foundations

A great morning’s work!

Day 9 – Tuesday 12th July

Delivery of building materials

Foundations are all hardened and ready for building

Blocks positioned for use

Building materials 2

Building materials

Day 10 – Wednesday 13th July

Craning in the building materials

Day 11 – Thursday 14th July

Brickwork is now in place as far as possible.

The next step is to order the block and beams for the flooring.

foundations behind new lounge

Foundations behind new lounge, currently a bedroom

Day 12 – Friday 22nd July

Block and Beams for the new flooring delivered today.

Day 17 – Monday 1st August 2016

Very wet day

Insulation beginning and more work on drains

August 1st - pic 1

More blocks being delivered Truck size is limited by width of drive Therefore that limits weight that can be delivered

August 1st - pic 2

Bricks stacked to hand for builder

August 1st - pic 3

Insulation – celotex repels water

August 1st - pic 4

Rain stops play again

August 1st - pic 5

A whole lot of rain

August 1st - pic 6

Insulation between double block work

Day 18 – Tuesday 2nd August 2016

Brick work is rapidly growing.

Back of house

Backdoor

Blocks stacked for building 2

Blocks stacked for building

New walkway between garage and new kitchen

Scaffolding in background 2

Scaffolding waiting

Scaffolding in background

Wall from backdoor

View from back door

Day 19 – Wednesday 3rd August 2016

Kitchen area is taking shape

Brick work 2Brick work 3Brick work 4

Brick work 5

Scaffolding ready

Brick work

Lintl to go into roof here

Area for Lintel

Outside back door 2

Day 20 – Thursday 4th August 2016

Between New Kitchen and Garage

Between New Kitchen and Garage

New entrance to kitchen from utility room

New entrance to kitchen from utility room

corner of new kitchen

Corner of New Kitchen

Day 20 - Progress so far

Day 20 – Progress so far

Scaffolding around back

Scaffolding around back

View along back of house day 20

View along back of house day 20

Day 21 – Friday 5th August 2016

Checking new lintel

Checking new lintel

Concrete slab for utility

Concrete slab for utility

View of garage through new kitchen

View of garage through new kitchen

Looking through new window position

Looking through new window position

Over the top

Top of new kitchen

View from kitchen through patio door to steps

View from kitchen through patio door to steps eventually

View of back garden

View of back garden

View of patio through scaffolding

View of patio through scaffolding

View of polytunnel from top of scaffolding

View of polytunnel from top of scaffolding

View over garden to field 2

View over garden to field 2

View to new kitchen window position

View to new kitchen window position

Day 22 – Saturday 6th August 2016

Roof Construction begins

Beginning of new kitchen roof

Beginning of new kitchen roof

Beginning of new kitchen roof picture 2

Beginning of new kitchen roof picture 2

Beginning of new kitchen roof picture 3

Beginning of new kitchen roof picture 3

Day 23 – Sunday 7th August 2016

Kitchen Roof Construction

Kitchen roof so far

Kitchen roof so far

Kitchen roof so far picture 2

Kitchen roof so far picture 2

Kitchen roof so far picture 3

Kitchen roof so far picture 3

Progress day 23

Progress day 23

Progress day 23 picture 2

Progress day 23 picture 2

Day 24 – Monday 8th August 2016 – BATS

Our property is in an area that has potential for bats, therefore it was deemed necessary that we should have a bat survey carried out before any work could go ahead on the roof of the property.
We had dawn and dusk observations completed last year. During the first bat activity survey, Springdale was identified as a transitional/ day roost for a low number of common bats.
Therefore a Method Statement was drawn up which instructed us on how we must go about our new extension.
In hindsight we now understand what we did wrong.
This is what happened.
Some work to the roof has already been carried out without supervision of a bat licensed ecologist contrary to the licence conditions.
Everything is on hold.  No further work can be carried out to the existing roof without supervision.
We have breached planning conditions and have been reported to Natural Resources Wales.
We must await their decision.Roof top ridge

Back corner joint

If anyone out there is in the same position, a word of warning – do not go ahead and touch the roof without a bat licensed ecologist being employed on site prior to works commencing and during any removal of roof tiles.
Read the Method Statement carefully. Our report was 29 pages long. The Method Statement was on page 17. So it is advisable to read it all.
The local authority have now also been informed of our breach of planning conditions.
We now also have a Shwegler 1 FE Bat Box on the garage as recommended and we will need to install another three on the front of the house on completion of the building.

Day 25 – Monday 15th August 2016

Work continues on the permitted part of the new roof.  No parts of the old roof may be touched without supervision from a bat licenced ecologist.

Roof work 3Roof work 2

Work on retaining wall begins

New retaining wall

Retaining Wall

New retaining wall 2

New retaining wall

New retaining wall 3

Day 26 – Tuesday 16th August 2016

Progress on New Kitchen Roof

Progress of roof

Progress of roof

Progress of roof 2

Progress of roof 2

Progress of roof 3

Progress of roof 3

Retaining Wall and drainage

Retaining Wall and drainage

Day 27 – Wednesday 17th August 2016

Breach of Bat Licence

This is an extract of the email we were sent: I would like to take this opportunity to remind you that any breach of licence is considered to be a breach of the legislation, and we have a duty to act upon such cases, as this was reported timely and works have now halted to allow for the ecologist to be present, in this case please consider this a warning.
Should any further breaches occur we will have no option but to refer this matter to the police for investigation.

Therefore no work has been carried out, but can now continue once we have been supervised during tile removal.

Work today on the retaining wallretaining wall

Day 28 – Thursday 18th August 2016

Removal of roof tiles with bat ecologist on site

Ecologist on site

Ecologist on site

Tile Removal with supervision 2

Tile Removal with supervision 2

Tile Removal with supervision

Tile Removal with supervision

Tile Removal with supervision 3Tile Removal with supervision 5Tile Removal with supervision 4

Progress of retaining wall

Progress of retaining wall

Ground drains

Ground drains

Inside Kitchen Area

Inside Kitchen Area

Top of patio doors

Top of patio doors

Top of patio doors 2

Top of patio doors 2

Day 29 – Friday 19th August 2016

Rain! Heavy! No proper rain for a few weeks, till last night and this morning, just as all roof tiles have been removed – typical!

By lunch time rain was so heavy, the builder and his mate went home. Rain stops play again.

Filling back of retaining wall

Filling back of retaining wall

Retaining wall

Retaining wall

Days 30 and 31 – Monday 22nd and Tuesday 23rd August 2016

Work concentrated on the retaining wall behind the new kitchen and the new step area that will give us quick access to the garden.  The soil is clay and heavy, and although it has been well compacted over the years before its disturbance for this build, it needs to be held back with a strong wall.

Digger to remove remaining soil for steps 2

Digger to remove remaining soil for steps

As the height of the garden from the new patio is well above the ground level, about six steps will be required. This means more digging out to create space for the steps, also taking into consideration the width of each step and the drop of each step.

Digger to remove remaining soil for steps

Digger removing remaining soil

View from bedroom 2

View from bedroom

View from bedroom

2nd View from bedroom

Day 32 – Wednesday 24th August 2016

Roofer and builder here today.  Photos below of progress

Roof progress

Roof progress

Roof progress 2

Roof progress 2

Wall and Step Progress

Wall and Step Progress

Wall progress

Wall progress

Day 33 and Day 34 – Thursday 25th and Friday 26th August 2016

Thursday was fine first thing, then heavy rain stopped the work

Retaining Wall and Steps

Retaining Wall and Steps

Step progress 2

Step progress 2

Step progress

Step progress

Wall progress

Wall progress

Wall progress 2

Wall progress 2

Day 35 – Saturday 27th August 2016

Although the weekend the roofer continued work today.

Roof Progress

Roof Progress

Roof Progress 2

Roof Progress 2

Roof Progress 3

Roof Progress 3

View up to new ceiling height in kitchen

View up to new ceiling height in kitchen

View up to new ceiling height

View up to new ceiling height

View down to new step area and new kitchen extension

View down to new step area and new kitchen extension

Day 36 – Tuesday 30th August 2016

Batons and roofing felt was delivered today.

More work on the retaining wall and steps.

Step area

Step area

View from above of the new steps area

View from above of the new steps area

Another view of retaining wall

Another view of retaining wall

Wall from new patio area

Wall from new patio area

Wall view from side of garage

Wall view from side of garage

Day 37 – Wednesday 31st August 2016

Building Control Officer visited today to check on progress.

Also Bat licenced Ecologist came in the afternoon to supervise the removal of tiles from existing utility room roof and small bedroom roof as required by the bat licence.

Tiles removed over the utility room, picture taken from scaffolding

Tiles removed over the utility room, picture taken from scaffolding

Tiles removed from roof over small bedroom, this will be a new bathroom, picture taken from scaffolding

Tiles removed from roof over small bedroom, this will be a new bathroom, picture taken from scaffolding

Another view over utility room roof where tiles have been removed under supervision of bat ecologist

Another view over utility room roof where tiles have been removed under supervision of bat ecologist

Up on Scaffolding - Tiles all removed from old existing roof over utility room and small bedroom

Up on Scaffolding – Tiles all removed from old existing roof over utility room and small bedroom

View to main roof over existing master bedroom, this will be the new lounge

View to main roof over existing master bedroom, this will be the new lounge

View to garden from scaffolding above new kitchen

View to garden from scaffolding above new kitchen

View to back garden from scaffolding over new kitchen

View to back garden from scaffolding over new kitchen

View from scaffolding

View from scaffolding

New Fascia board partly in place over position for patio doors

New Fascia board partly in place over position for patio doors

Progress on the new step area from patio

Progress on the new step area from patio

Day 38 – Thursday 1st September 2016

Progress on steps today

Step progress

Step progress

Step progress 2

Step progress 2

Saturday 3rd and Sunday 4th September 2016

Heavy, heavy rain

This resulted in a lot of leaking rain water finding its way into the utility room and the small bedroom.

saturday-3rd-september-small-bedroom-roof-leaked-badly-tiles-have-been-removed

Saturday-3rd-September-small-bedroom-roof-leaked-badly-tiles-have-been-removed

Saturday-3rd-September-utility-roof-leaked-badly-tiles-have-been-removed

Saturday-3rd-September-utility-roof-leaked

Sunday – tarpaulins now in place over old roof

Day 39 – Monday 5th September 2016

Today the roofer returned and completed the valleys on the hips of the roof. Also the fascia board was completed.  The builder added vents to allow air into the roof space and any water vapour to escape.  We are not allowed to have breathable membrane on the roof as it may harm any potential bat visitors.

fascia-board

Fascia Board

fascia-board-2

Fascia Board 2

fascia-board-3

Fascia Board 3

back-of-house-progress-so-far-day-39

back-of-house-progress-so-far-day-39

back-of-house-progress-so-far-day-39-another-angle

back-of-house-progress-so-far-day-39-another-angle

back-of-house-progress-so-far-day-39-another-angle-2

back-of-house-progress-so-far-day-39-another-angle-2

Day 40 – Tuesday 6th September 2016

Main steps are really taking shape now. Also felt and battening on the roof began.

main-steps-now-back-filled-and-with-concrete

Main-steps-now-back-filled-and-with-concrete

main-steps-filled-with-concrete-and-view-up-to-roof-where-felt-and-batoning-has-begun

Main-steps-filled-with-concrete-and-view-up-to-roof-where-felt-and-battening-has-begun

main-steps-and-roof-view-progress-so-far

Main-steps-and-roof-view-progress-so-far

Also the builder collected fibre glass coated board for part of the flat roof that will eventually be over new utility room and new bathroom.

Day 41 – Wednesday 7th September 2016

Felt and battening going up onto new kitchen roof.

felt-and-battening-progress

felt-and-battening-progress

felt-and-battening-progress-2

felt-and-battening-progress-2

Day 42 – Thursday 8th September 2016

Progress of retaining wall and back view of house

roof-and-walls-of-steps

roof-and-walls-of-steps

view-of-new-extension-from-back-garden

view-of-new-extension-from-back-garden

Days 43 and 44 – Friday 9th September and Monday 12th September 2016

Views of progress on steps and extension

back-view-of-kitchen-extension

back-view-of-kitchen-extension

side-view-of-new-extension

side-view-of-new-extension

new-main-steps-progress-so-far

new-main-steps-progress-so-far

Day 45 – Tuesday 13th September 2016

wet-room-roof-leaking-again

Thuderstorms wet-room-roof-leaking-again

view-to-new-lintel-above-position-of-backdoor

view-to-new-lintel-above-position-of-backdoor

view-through-extension-from-old-small-bedroom

view-through-extension-from-old-small-bedroom

inside-new-kitchen-extension-view-of-roof-area

inside-new-kitchen-extension-view-of-roof-area

new-slabs-for-patio-and-steps

new-slabs-for-patio-and-steps

Day 46 – Wednesday 14th September 2016

sloping-wall-corner-to-side-and-rear

sloping-wall-corner-to-side-and-rear

rosemary-tiles-for-new-roof-matching-old-tiles

rosemary-tiles-for-new-roof-matching-old-tiles

new-entrance-to-house-via-back-door-into-utility

new-entrance-to-house-via-back-door-into-utility

Block work now built up higher on left side of utility

lintel-above-new-back-door-area-and-wire-to-be-re-routed

lintel-above-new-back-door-area

Day 47 – Thursday 15th September 2016

The start of the disruption in our living space.

New supporting beams being inserted joining old house to new extension.

small-bedroom-roof-removed

small-bedroom-roof-removed

small-bedroom-roof-removed-2

small-bedroom-roof-removed-2

inside-small-bedroom

inside-small-bedroom

inside-small-bedroom-2

inside-small-bedroom-2

hallway-untouched-as-yet-new-supporting-beam-not-required-here-luckily

hallway-untouched-as-yet-new-supporting-beam-not-required-here-luckily

Day 48 – Friday 16th September 2016

New beams joining old building to new extension, supports for roof

area-which-will-be-walk-way-into-new-kitchen-from-back-door-beside-old-bedroom-note-large-difference-in-floor-height-steps-will-be-needed

area-which-will-be-walk-way-into-new-kitchen-from-back-door-beside-old-bedroom-note-large-difference-in-floor-height-steps-will-be-needed

view-from-ladders-over-window-into-old-small-bedroom-with-ceiling-removed

view-from-ladders-over-window-into-old-small-bedroom-with-ceiling-removed

view-of-new-beams-now-in-place-for-new-roof-over-old-small-bedroom-soon-to-be-family-bathroom

view-of-new-beams-now-in-place-for-new-roof-over-old-small-bedroom-soon-to-be-family-bathroom

tiles-on-scaffolding

tiles-on-scaffolding

Day 49 – Saturday 17th September 2016

Removal of 2 ceilings discovered over the Utility Room

two-ceilings-had-to-be-removed-from-here-before-insertion-of-new-beams-over-utility-room-the-room-had-to-be-emptied-because-of-mess-caused-in-a-job-like-this

two-ceilings-had-to-be-removed-from-here-before-insertion-of-new-beams-over-utility-room-the-room-had-to-be-emptied-because-of-mess-caused-in-a-job-like-this

view-of-new-roof-beams-spanning-utility-room-fibre-glass-boards-will-be-used-over-this-part-of-the-roof

view-of-new-roof-beams-spanning-utility-room-fibre-glass-boards-will-be-used-over-this-part-of-the-roof

rubble-and-old-ceiling-to-be-removed-from-new-kitchen-walkway

rubble-and-old-ceiling-to-be-removed-from-new-kitchen-walkway

view-through-utility-door-old-ceiling-outside

view-through-utility-door-old-ceiling-outside

electricity-box-all-exposed-in-utility

electricity-box-all-exposed-in-utility

old-electricity-box-surround-which-fell-down-during-removal-of-ceiling-in-the-utility-room

old-electricity-box-surround-which-fell-down-during-removal-of-ceiling-in-the-utility-room

rubble-to-be-removed-from-old-bedroom

rubble-to-be-removed-from-old-bedroom

old-wood-to-be-removed-from-old-bedroom

old-wood-to-be-removed-from-old-bedroom

Day 50 – Sunday 18th September 2016

More Work on Utility Room

utility-outside-wall-now-removed

utility-outside-wall-now-removed

view-from-kitchen-through-utility-to-new-wall-of-utility

view-from-kitchen-through-utility-to-new-wall-of-utility

utility-room-with-old-wall-removed-right-hand-side

utility-room-with-old-wall-removed-right-hand-side

utility-room-with-old-wall-removed

utility-room-with-old-wall-removed

Day 51 – Monday 19th September 2016

Work in and around Utility Room continues

rain-overnight-leaking-into-utility-room

rain-overnight-leaking-into-utility-room

rubble-and-plaster-board-from-utility-wall-also-see-vertical-cuts-in-wall-which-will-be-the-door-opening-into-the-new-bathroom

rubble-and-plaster-board-from-utility-wall-also-see-vertical-cuts-in-wall-which-will-be-the-door-opening-into-the-new-bathroom

close-up-of-grooves-cut-for-door-to-new-bathroom

close-up-of-grooves-cut-for-door-to-new-bathroom

everything-covered-to-protect-from-very-fine-red-brick-dust-after-cutting-grooves-for-new-doorway-in-utility-room-2

everything-covered-to-protect-from-very-fine-red-brick-dust-after-cutting-grooves-for-new-doorway-in-utility-room-2

dust-masks-essential

dust-masks-essential

new-brickwork-around-timbers-in-utility-room

new-brickwork-around-timbers-in-utility-room

close-up-of-new-sloping-beams-to-accomodate-head-height-for-steps-which-have-yet-to-be-built-to-reach-new-level-of-kitchen

close-up-of-new-sloping-beams-to-accomodate-head-height-for-steps-which-have-yet-to-be-built-to-reach-new-level-of-kitchen

Day 52 – Tuesday 20th September 2016

Work to utility room, new bathroom, and brickwork

drilling-and-loosening-brick-work-in-new-doorway-before-inserting-2-new-lintels

drilling-and-loosening-brick-work-in-new-doorway-before-inserting-2-new-lintels

new-lintels-in-over-new-doorway-and-window-out-of-old-bedroom

new-lintels-in-over-new-doorway-and-window-out-of-old-bedroom

two-new-lintels-over-new-doorway

two-new-lintels-over-new-doorway Between old bedroom and utility room

old-bedroom-cleared-of-rubble-and-window-removed

old-bedroom-cleared-of-rubble-and-window-removed

old-bedroom-window-removed

old-bedroom-window-removed

new-bathroom-old-bedroom-with-gap-for-flat-roof-light-bubble

new-bathroom-old-bedroom-with-gap-for-flat-roof-light-bubble

position-of-new-polycarbonate-dome-for-light-for-new-bathroom

position-of-new-polycarbonate-dome-for-light-for-new-bathroom

lead-inserted-into-roof-this-will-go-over-fibre-glass-board-double-wall-here-completed-between-rafters

lead-inserted-into-roof-this-will-go-over-fibre-glass-board-double-wall-here-completed-between-rafters

lead-inserted-into-roof-and-wall-finished

lead-inserted-into-roof-and-wall-finished

sloping-roof-created-to-accomodate-enough-head-height-when-going-down-steps-from-new-kitchen-to-utility

sloping-roof-created-to-accomodate-enough-head-height-when-going-down-steps-from-new-kitchen-to-utility

sloping-roof-from-above-outside-view

sloping-roof-from-above-outside-view

view-from-new-kitchen-area-through-to-back-door-position-and-garage

view-from-new-kitchen-area-through-to-back-door-position-and-garage

Day 53 – Wednesday 21st September 2016

Unfortunately the builder fell through the beams of the utility room today, landing on a stone floor.  This meant a hospital check up. He is very sore, but luckily no broken bones.

close-up-of-new-sloping-beams-to-accomodate-head-height-for-steps-which-have-yet-to-be-built-to-reach-new-level-of-kitchen

gaps in beams, some unsecured

Day 54 – Thursday 22nd September 2016

Builder is very fortunately ok and back here, although very sore.  A lot of work today on the roof over utility and new entrance to kitchen.

view-into-utility-room-from-new-kitchen-fibre-boards-in-place-on-roof

view-into-utility-room-from-new-kitchen-fibre-boards-in-place-on-roof

utility-roof-showing-slope

utility-roof-showing-slope

fibre-boarding-over-utility-room

fibre-boarding-over-utility-room

skylight-shown-in-blue-tarpaulin-over-top

skylight-shown-in-blue-tarpaulin-over-top

this-will-be-door-out-of-new-bathroom-to-utility-lintels-in-part-cut

this-will-be-door-out-of-new-bathroom-to-utility-lintels-in-part-cut

Day 55 – Friday 23rd September 2016

More roof work – pictures taken Saturday 24th September from scaffolding

view-from-scaffolding-of-tarpaulins-new-bathroom-and-utility-room-sloping-roof-can-be-seen-under-tarpaulin

view-from-scaffolding-of-tarpaulins-new-bathroom-and-utility-room-sloping-roof-can-be-seen-under-tarpaulin

view-from-scaffolding-of-tarpaulins-over-part-of-new-bathroom-and-utility-room-lefthand-side-of-roof

view-from-scaffolding-of-tarpaulins-over-part-of-new-bathroom-and-utility-room-lefthand-side-of-roof

view-from-scaffolding-of-tarpaulins-over-part-of-new-bathroom-and-utility-room

view-from-scaffolding-of-tarpaulins-over-part-of-new-bathroom-and-utility-room

view-of-roof-over-utility-and-entrance-to-new-kitchen-between-the-three-sloping-roofs

view-of-roof-over-utility-and-entrance-to-new-kitchen-between-the-three-sloping-roofs

view-from-scaffolding

view-from-scaffolding

scaffolding-between-new-kitchen-and-garage

scaffolding-between-new-kitchen-and-garage

view-across-scaffolding-along-back-of-house

view-across-scaffolding-along-back-of-house

view-towards-back-garden-from-saffolding-showing-felt-and-battening

view-towards-back-garden-from-scaffolding-showing-felt-and-battening

view-to-back-garden-across-scaffolding

view-to-back-garden-across-scaffolding

view-of-new-steps-from-scaffolding

view-of-new-steps-from-scaffolding

view-into-new-kitchen-through-new-side-window-opening

view-into-new-kitchen-through-new-side-window-opening

rain-leaking-into-utility-roof-is-unfinished-as-yet

rain-leaking-into-utility-roof-is-unfinished-as-yet

heavy-rain-has-totally-filled-tarpaulin-over-new-skylight-rain-is-leaking-in-again

heavy-rain-has-totally-filled-tarpaulin-over-new-skylight-rain-is-leaking-in-again

sunday-another-night-of-heavy-rain-8-buckets-of-water-removed-from-tarpaulin-covering-skylight

sunday-another-night-of-heavy-rain-8-buckets-of-water-removed-from-tarpaulin-covering-skylight

Day 56 – Monday 26th September 2016

Wet day – Work limited to undercover.  Skylight gap previously covered in tarpaulin was recovered with board.  This will be fitted and sealed within the next few days, so should soon be water tight.  Hole was cut for doorway to new bathroom.  Bricks laid to fill gap over new lintel above the new back door.  Old bedroom window now blocked in.  Photos below.

old-bedroom-window-blocked-up

old-bedroom-window-blocked-up

old-little-bedroom-with-window-blocked-up-and-brickwork-cut-to-the-left-to-form-a-new-doorway-into-the-utility-room

old-little-bedroom-with-window-blocked-up-and-brickwork-cut-to-the-left-to-form-a-new-doorway-into-the-utility-room

new-doorway-cut-into-old-bedroom-which-will-be-new-bathroom-picture-taken-from-utility-side

new-doorway-cut-into-old-bedroom-which-will-be-new-bathroom-picture-taken-from-utility-side

Day 57 – Tuesday 27th September 2016

Fibre glass roofing over flat/sloping roof was completed today.  Fibre glass roofing was chosen as it is strong and durable and can last for 20 years.  It was the ideal solution to cover this kind of roof where all the tiled roofs meet.  An expert came out to do the job and it had to be a dry day.  There are several layers, the first of which is a fibre glass coated board, then a resin goes on, followed by the fibre glass matting, then more resin and finally a top coat. Photos are shown below.

Also today a mistake was noticed by the double glazing man in the hip above the patio doors when he was measuring, so this needs to be corrected.

hip-roof-has-been-constructed-incorrectly-one-angle-is-wrong-3-inches-out

hip-roof-has-been-constructed-incorrectly-one-angle-is-wrong-3-inches-out

hip-roof-has-been-constructed-incorrectly-picture-2

hip-roof-has-been-constructed-incorrectly-picture-2

hip-roof-has-been-constructed-incorrectly-picture-3

hip-roof-has-been-constructed-incorrectly-picture-3

hip-roof-has-been-constructed-incorrectly-picture-4

hip-roof-has-been-constructed-incorrectly-picture-4

hip-roof-being-reconstructed

hip-roof-being-reconstructed

hip-roof-being-reconstructed-2

hip-roof-being-reconstructed-2

fibre-glass-roof-between-sloping-roofs-completed-today-all-sealed-and-watertight-skylight-and-vents-are-also-sealed-in

fibre-glass-roof-between-sloping-roofs-completed-today-all-sealed-and-watertight-skylight-and-vents-are-also-sealed-in

fibre-glass-roof-shows-sloping-sections-and-new-skylight-and-vents-all-put-in-place-today

fibre-glass-roof-shows-sloping-sections-and-new-skylight-and-vents-all-put-in-place-today

fibre-glass-roof-took-a-day-to-do-and-sealed-with-a-special-glue

fibre-glass-roof-took-a-day-to-do-and-sealed-with-a-special resin and top coat

sealed-vent-for-utility-room-in-new-fibre-glass-roof

sealed-vent-for-utility-room-in-new-fibre-glass-roof

vent-put-in-new-bathroom

vent-put-in-new-bathroom

new-vent-can-be-seen-in-utility-room

new-vent-can-be-seen-in-utility-room

skylight-over-new-bathroom-to-be-in-place-natural-light-coming-through-is-considerable

skylight-over-new-bathroom-to-be-in-place natural-light-coming-through-is-considerable

bricks-in-place-over-back-door-outside-doors-and-windows-have-been-measured

bricks-in-place-over-back-door-outside-doors-and-windows-have-been-measured

blocked-up-old-bedroom-window

blocked-up-old-bedroom-window

2-doorways-now-opened-up-left-to-kitchen-right-to-new-bathroom-rubble-all-cleared-away

2-doorways-now-opened-up-left-to-kitchen-right-to-new-bathroom-rubble-all-cleared-away

a-fleet-of-white-vans-today

a-fleet-of-white-vans-today

Day 58 Wednesday 28th September 2016

block-wall-between-bedroom-and-new-kitchen-window-will-be-removed-next-week

block wall between bedroom and new kitchen window will be removed next week

block-wall-going-up-between-bedroom-and-new-kitchen-from-scaffolding-window-to-be-filled-in-next-week

block wall going up between bedroom and new kitchen from scaffolding window to be filled in next week

block-wall-going-up-between-bedroom-and-new-kitchen

block-wall-going-up-between-bedroom-and-new-kitchen

hip-roof-now-corrected-and-finished-now-in-at-correct-angle

hip-roof-now-corrected-and-finished-now-in-at-correct-angle

hip-roof-now-corrected-picture-2

hip-roof-now-corrected-picture-2

Day 59 – Thursday 29th September 2016

installation-of-plastic-and-foam-lining-to-seal-cavity-around-door

installation-of-plastic-and-foam-lining-to-seal-cavity-around-door

cavity-wall-closers-around-patio-doors

cavity-wall-closers-around-patio-doors

cavity-closers-around-windows

cavity-closers-around-windows

cavity-closers-around-windows-pic-3

cavity-closers-around-windows-pic-3

cavity-closers-around-windows-pic-2

cavity-closers-around-windows-pic-2

tiles-now-being-replaced-around-new-fibre-glass-roof-picture-from-scaffolding

tiles-now-being-replaced-around-new-fibre-glass-roof-picture-from-scaffolding

tiles-now-being-replaced-around-new-fibre-glass-roof-picture-2

tiles-now-being-replaced-around-new-fibre-glass-roof-picture-2

fibre-glass-roof

fibre-glass-roof

fibre-glass-roof-2-showing-valley

fibre-glass-roof-2-showing-valley

Day 60 – Friday 30th September 2016

leaking-skylight

Leaking Skylight. Heavy rain overnight and water has been dripping through the skylight in one corner. The bubble has now been fixed on over the top so this should stop the problem

felt-nearly-completed-shown-from-inside-of-new-kitchen

felt-nearly-completed-shown-from-inside-of-new-kitchen

felt-from-inside-of-new-kitchen

felt-from-inside-of-new-kitchen

view-of-main-bedroom-through-window-to-be-blocked-up-scaffolding-still-in-place-inside

view-of-main-bedroom-through-window-to-be-blocked-up-scaffolding-still-in-place-inside

view-of-back-of-house-showing-completed-felt-and-battening

view-of-back-of-house-showing-completed-felt-and-battening

view-of-back-of-house-showing-valley-in-the-middle-between-the-two-roofs

view-of-back-of-house-showing-valley-in-the-middle-between-the-two-roofs

top-of-drive-in-front-of-double-garage-with-materials-and-new-roof-structure-with-felt-and-battening-between-house-and-garage

top-of-drive-in-front-of-double-garage-with-materials-and-new-roof-structure-with-felt-and-battening-between-house-and-garage

materials still to be used at the top of the drive and top of the new kitchen roof can be seen with felt and battening

top-of-drive-in-front-of-double-garage-with-materials

top-of-drive-in-front-of-double-garage-with-materials

Day 61 – Monday 3rd October 2016

Tiles starting to go on roof now

work-today-on-roof-tiles-on-righthand-side-roof-felt-on-peak-over-patio-doors-and-lead-in-valleys

work-today-on-roof-tiles-on-righthand-side-roof-felt-on-peak-over-patio-doors-and-lead-in-valleys

felt-on-new-hip-roof-and-lead-valley-on-right

felt-on-new-hip-roof-and-lead-valley-on-right

lead-valley-on-lefthand-side-of-hip-roof

lead-valley-on-lefthand-side-of-hip-roof

view-along-back-of-house-above-new-kitchen-and-main-bedroom

view-along-back-of-house-above-new-kitchen-and-main-bedroom

view-of-newly-tiled-righthandside-of-new-kitchen-roof

view-of-newly-tiled-right hand side-of-new-kitchen-roof

view-along-side-of-newly-tiled-kitchen-roof-towards-back-garden

view-along-side-of-newly-tiled-kitchen-roof-towards-back-garden

Day 62 – Tuesday 4th October 2016

Tiling of the new roof continued.  Much progress was made today.

progress-of-tiling-over-kitchen-roof

progress-of-tiling-over-kitchen-roof

progress-of-tiling-over-kitchen-roof-picture-2

progress-of-tiling-over-kitchen-roof-picture-2

close-up-of-tiling-in-progress-through-scaffolding

close-up-of-tiling-in-progress-through-scaffolding

back-of-house-view-2

back of house view

view-of-back-of-house-so-far

view-of-back-of-house-different angle

Day 63 – Wednesday 5th October 2016

Two windows and a door!

first-new-window-for-kitchen-partly-obscured-by-scaffolding

first-new-window-for-kitchen-partly-obscured-by-scaffolding

second-new-window-also-partly-obscured-by-scaffolding

second-new-window-also-partly-obscured-by-scaffolding

new-back-door-into-utility

new-back-door-into-utility

view-through-window-from-main-bedroom-to-new-kitchen

view-through-window-from-main-bedroom-to-new-kitchen

view-through-window-from-main-bedroom-to-new-kitchen-marked-for-sik-dishwasher-cooker

view-through-window-from-main-bedroom-to-new-kitchen-marked-for-sik-dishwasher-cooker

kitchen-planning

kitchen-planning

new-back-door-picture-taken-from-inside

new-back-door-picture-taken-from-inside

Day 64 – Thursday 6th October 2016

Electrician today

electrician-came-today-and-started-wiring-kitchen

electrician-came-today-and-started-wiring-kitchen

wiring-for-cooker-and-sockets-above-work-top-eventually

wiring-for-cooker-and-sockets-above-work-top-eventually in this position

wiring-for-fridge

wiring-for-fridge

wiring-in-corner-of-kitchen-new-hall-door-will-be-located-to-the-left-of-this

wiring-in-corner-of-kitchen-new-hall-door-will-be-located-to-the-left-of-this

Outside work continues with the tiling of the new roof

hip-roof-tiled-and-lead-in-valley

hip-roof-tiled-and-lead-in-valley

Day 65 – Friday 7th October 2016

Progress of tiling on new roof

roof-tiling-progress-adjacent-to-flat-roof

roof-tiling-progress-adjacent-to-flat-roof

roof-tiling-progress-adjacent-to-flat-roof-picture-2

roof-tiling-progress-adjacent-to-flat-roof-picture-2

roof-tiling-showing-progress-of-tiling-at-back-of-kitchen-roof

roof-tiling-showing-progress-of-tiling-at-back-of-kitchen-roof

roof-tiling-along-side-of-roof-adjacent-to-garage

roof-tiling-along-side-of-roof-adjacent-to-garage

inspection-of-work

inspection-of-work

lead-valley-down-side-of-hip-roof

lead-valley-down-side-of-hip-roof

lead-valley-down-left-side-of-hip-roof

lead-valley-down-left-side-of-hip-roof

progress-on-tiling-7-10-16

progress-on-tiling-7-10-16

Day 66 – Monday 10th October 2016

Progress on roof

the-roof-so-far-at-the-back-of-house-over-new-kitchen

the-roof-so-far-at-the-back-of-house-over-new-kitchen

corner-of-roof-adjacent-to-garage-and-sloping-onto-flat-roof

corner-of-roof-adjacent-to-garage-and-sloping-onto-flat-roof

corner-of-roof-adjacent-to-garage-and-sloping-onto-flat-roof-cemented-in

corner-of-roof-adjacent-to-garage-and-sloping-onto-flat-roof-cemented-in

new-and-old-corner-rosemary-tiles-the-old-ones-are-much-smaller-and-have-a-shallower-curve

new-and-old-corner-rosemary-tiles-the-old-ones-are-much-smaller-and-have-a-shallower-curve

new-kitchen-roof-sloping-to-flat-roof

new-kitchen-roof-sloping-to-flat-roof

Day 67 – Tuesday 11th October 2016

Lovely day

completed-corner-all-down-roof-to-over-new-back-door

completed-corner-all-down-roof-to-over-new-back-door

completed-corner-all-down-roof-to-over-new-back-door-picture-2

completed-corner-all-down-roof-to-over-new-back-door-picture-2

new-kitchen-roof-sloping-onto-flat-roof-area

new-kitchen-roof-sloping-onto-flat-roof-area

hip-roof-cemented

hip-roof-cemented

electrician-at-work-in-kitchen

electrician-at-work-in-kitchen

electricians-work-so-far-installing-electricity-and-plug-sockets-in-new-kitchen

electricians-work-so-far-installing-electricity-and-plug-sockets-in-new-kitchen

showing-wiring-coming-over-the-top-of-the-wall-into-the-new-kitchen-from-scaffolding-level

showing-wiring-coming-over-the-top-of-the-wall-into-the-new-kitchen-from-scaffolding-level

new-sockets-in-kitchen

new-sockets-in-kitchen

new-box-for-plug-socket

new-box-for-plug-socket

cable-coming-down-for-sky-aerial-and-power-for-tv

cable-coming-down-for-sky-aerial-and-power-for-tv

wiring-coming-over-wall-in-new-kitchen

wiring-coming-over-wall-in-new-kitchen

wiring-for-plug

wiring-for-plug and switch

wiring-in-kitchen

wiring-in-kitchen

Day 68 – Wednesday 12th October 2016

back-of-house-over-kitchen-a-few-corner-tiles-to-be-sourced-for-roof

back-of-house-over-kitchen-a-few-corner-tiles-to-be-sourced-for-roof

back-of-house-over-kitchen-a-few-corner-tiles-to-be-sourced-for-roof-close-up

back-of-house-over-kitchen-a-few-corner-tiles-to-be-sourced-for-roof-close-up

Day 69 – Thursday 13th October 2016

Electrician and builder today

valley-tiles-all-cut

valley-tiles-all-cut

tiles-down-valley-all-neatly-cut

tiles-down-valley-all-neatly-cut

wiring-now-fed-through-in-readiness-for-kitchen-lights

wiring-now-fed-through-in-readiness-for-kitchen-lights

wiring-now-fed-through-in-readiness-for-kitchen-lights-picture-2

wiring-now-fed-through-in-readiness-for-kitchen-lights-picture-2

wiring-in-new-bathroom-for-ceiling

wiring-in-new-bathroom-for-ceiling

wiring-in-ceiling-between-new-kitchen-and-utility

wiring-in-ceiling-between-new-kitchen-and-utility

Day 70 – Friday 14th October 2016

Indoor work today – builder and plumber

bedroom-prepared-for-removal-of-window

bedroom-prepared-for-removal-of-window

window-before-removal-between-kitchen-and-bedroom

window-before-removal-between-kitchen-and-bedroom

blocked-up-window-between-new-kitchen-and-bedroom-from-bedroom-side

After! blocked-up-window-between-new-kitchen-and-bedroom-from-bedroom-side

blocked-up-window-between-new-kitchen-and-bedroom

After blocked-up-window-between-new-kitchen-and-bedroom

wall-partly-cut-in-readiness-for-new-door-to-kitchen-from-hallway

wall-partly-cut-in-readiness-for-new-door-to-kitchen-from-hallway

kitchen-now-cleared-of-scaffolding-and-building-materials

kitchen-now-cleared-of-scaffolding-and-building-materials

new-pipework-for-hot-and-cold-water-to-new-kitchen-and-gas-to-gas-cooker-partly-installed

new-pipework-for-hot-and-cold-water-to-new-kitchen-and-gas pipe -to-gas-cooker-partly-installed

gas-and-water-supply-pipes-partly-installed-for-new-kitchen-through-new-wall

gas-and-water-supply-pipes-partly-installed-for-new-kitchen-through-new-wall

Day 71 – Monday 17th October 2016

Builder, Electrician and Plumber today. Heavy showers too, so roof not complete yet.

wall-at-front-where-patio-doors-going-has-been-levelled

wall at front where the patio doors are going has been levelled

kitchen-looking-through-window-from-hall-soon-to-be-removed

Looking through to new kitchen – window-from-hall-soon-to-be-removed and replaced with a door

new-steps-built-today-from-utility-to-new-kitchen-thet-are-not-level-at-the-top-as-the-kitchen-floor-has-not-been-built-up-yet

New steps-built-today-from-utility-to-new-kitchen. They are-not-level-at-the-top-as-the-kitchen-floor-has-not-been-built-up-yet

new-pipe-for-radiator-in-kitchen

new-pipe-for-radiator-in-kitchen

new-pipe-for-radiator-in-kitchen-2

new-pipe-for-radiator-in-kitchen picture 2

radiator-pipes-going-through-wall-to-new-bathroom

radiator-pipes-going-through-wall-to-new-bathroom

radiator-pipes-unning-around-flooring-will-be-below-level-of-floor-when-floor-has-been-put-in

radiator-pipes-running-around-flooring-will-be-below-level-of-floor-when-floor-has-been-put-in

switch-in-kitchen-on-left-at-the-top-of-the-new-steps

switch-in-kitchen-on-left-at-the-top-of-the-new-steps

new-switch-for-outside-light-just-outside-back-door

new-switch-for-outside-light-just-outside-back-door

old-outdoor-window-sill-now-chisled-away

old outdoor window sill now chiselled away

Day 72 – Tuesday 18th October 2016

beginning-of-celotex-insulation-between-roof-and-beams-in-utility-room-cut-around-extractor

beginning-of-celotex-insulation-between-roof-and-beams-in-utility-room-cut-around-extractor

plaster-board-for-walls-and-insulation-for-ceiling-has-been-delivered

plaster-board-for-walls-and-insulation-for-ceiling-has-been-delivered

wiring-for-floor-plug-socket-in-new-kitchen

wiring-for-floor-plug-socket-in-new-kitchen

roof-over-back-of-kitchen-nearly-complete-resized

roof-over-back-of-kitchen-nearly-complete

wire-for-outside-light-through-back-wall

wire-for-outside-light-through-back-wall

wire-for-outside-light-through-back-wall-on-other-side-of-patio-window

wire-for-outside-light-through-back-wall-on-other-side-of-patio-window

roof-sloping-down-to-flat-roof-nearly-complete

roof-sloping-down-to-flat-roof-nearly-complete

different-view-of-flat-roof-and-tiling-nearly-complete

different-view-of-flat-roof-and-tiling-nearly-complete

Day 73 – Wednesday 19th October 2016

Double layers of insulation have been inserted into ceiling area.  This has been a tricky job as all pieces need cutting and shaping.  The main kitchen area should not be so time consuming as larger straight pieces can be cut.

celotex-insulation-in-utility-room

Celotex insulation in Utility Room

celotex-insulation-in-utility-room-view-from-back-door

Celotex insulation in Utility Room View from Back Door

celotex-insulation-in-new-kitchen-entrance

celotex-insulation-in-new-kitchen-entrance

Day 74 – Thursday 20th October 2016

Insulation, insulation, insulation

insulation-in-new-kitchen-roof-going-in

insulation-in-new-kitchen-roof-going-in

insulation-in-new-kitchen-roof-at-back-of-kitchen-sloping-roof

insulation-in-new-kitchen-roof-at-back-of-kitchen-sloping-roof

insulation-in-new-kitchen-roof-on-slopng-roof-over-left-hand-window

insulation-in-new-kitchen-roof-on-sloping-roof-over-left-hand-window

insulation-in-new-kitchen-roof-on-slopng-roof-over-right-hand-window

insulation-in-new-kitchen-roof-on-sloping-roof-over-right-hand-window

insulation-in-new-bathroom-flat-roof

insulation-in-new-bathroom-flat-roof

insulation-in-new-bathroom-flat-roof-picture-2

insulation-in-new-bathroom-flat-roof-picture-2

Day 75 – Friday 21st October 2016

More insulation and roof nearly completed

kitchen-partly-floored-and-partly-insulated

kitchen partly floored and partly insulated

new-kitchen-partly-insulated-and-floored

New Kitchen partly floored and partly insulated

kitchen-with-insulation-partly-complete-and-flooring-also-shows-electrical-plug-socket-in-floor-for-island-unit

kitchen-with-insulation-partly-complete-and-flooring-also-shows-electrical-plug-socket-in-floor-for-island-unit

electrical-socket-in-flooring-not-yet-connected-in-kitchen-floor-for-island-unit

electrical-socket-in-flooring-not-yet-connected-in-kitchen-floor-for-island-unit

roof-nearly-complete

Roof nearly completed

roof-between-old-kitchen-and-new-kitchen

roof-between-old-kitchen-and-new-kitchen

Day 76 – Saturday 22nd October 2016

kitchen-flooring-insulation-and-chipboard-complete

Kitchen flooring base now complete Insulation on floating floor followed by chipboard

kitchen-flooring-insulation-and-chipboard-complete-view-2

kitchen-flooring-insulation-and-chipboard-complete-view-2

Day 77 – Monday 24th October 2016

plaster-board-up-on-new-kitchen-ceiling

Plaster board is now up on the 10 foot high ceiling. A mobile plasterboard hoist was used to lift it into place

plaster-board-up-on-new-kitchen-ceiling-picture-2-taken-from-front-to-back

plaster-board-up-on-new-kitchen-ceiling-picture-2-taken-from-front-to-back

plaster-board-on-right-hand-side-of-kitchen

plaster-board-on-right-hand-side-of-kitchen

left-hand-side-of-kitchen-showing-new-plaster-board-and-hatch

left-hand-side-of-kitchen-showing-new-plaster-board-and-hatch

back-garden-from-kitchen-looking-through-gap-for-patio-doors

A damp day today. The view of part of the back garden through the gap for the patio doors.

Day 78 – Tuesday 25th October 2016

Builder and plumber today

house-from-back-day-78

View of progress of House from the back

house-from-back-day-78-pic-2

house-from-back-day-78-pic-2

progress-with-plasterboarding-in-kitchen

Progress with the plaster boarding in the kitchen

plasterboard-2nd-window-sill-in-kitchen

Plaster boarding in the kitchen

plasterboard-window-sill-in-kitchen

plasterboard-window-sill-in-kitchen

plasterboard-2nd-window-sill-in-kitchen-on-right

plasterboard-2nd-window-sill-in-kitchen-on-right

positions-for-sink-and-toilet-in-new-bathroom

positions-for-sink-and-toilet-in-new-bathroom

position-for-radiator

position-for-radiator

position-for-bath-in-new-bathroom

position-for-bath-in-new-bathroom

position-for-toilet-in-new-bathroom

position-for-toilet-in-new-bathroom

position-for-sink-in-new-bathroom

position-for-sink-in-new-bathroom

gas-and-water-pipes-in-utility-room

gas-and-water-pipes-in-utility-room

capped-water-pipes-ready-for-sink

capped-water-pipes-ready-for-sink

Day 79 – Wednesday 26th October 2016

progress-on-roof-today

Progress on the roof – Day 79

close-up-of-roof-progress

close-up-of-roof-progress

roof-zoomed-in

Ridge tiles not yet in final position

roof-between-old-and-new-building

roof-between-old-and-new-building

roof-between-old-and-new-building-from-step-ladder

roof-between-old-and-new-building-from-step-ladder

roof-between-old-and-new-building-from-step-ladder-2

roof-between-old-and-new-building-from-step-ladder-2

new-bathroom-pipework-under-floor-boards

new-bathroom-pipework-under-floor-boards

new-bathroom-pipework-under-floor-boards-2

new-bathroom-pipework-under-floor-boards-2

new-bathroom-pipework-under-floor-boards-3

new-bathroom-pipework-under-floor-boards-3

new-bathroom-pipework-for-shower

new-bathroom-pipework-for-shower

Day 80 – Thursday 27th November 2016

marcus-the-plumber-in-a-very-tight-spot-under-the-floor-in-the-new-bathroom

Spot Marcus, our plumber, in a very tight spot, under the floor in the new bathroom

under-the-new-bathroom-floor-where-toilet-and-sink-will-go

under-the-new-bathroom-floor-where-toilet-and-sink-will-go

drain-and-pipework-under-floor

drain-and-pipework-under-floor

under-the-new-bathroom-floor-where-bath-will-be-positioned

under-the-new-bathroom-floor-where-bath-will-be-positioned

new-plasterboard-ceiling-in-utility-room

new-plasterboard-ceiling-in-utility-room

new-plasterboard-ceiling-in-new-bathroom

new-plasterboard-ceiling-in-new-bathroom

new-plasterboard-ceiling-in-entrance-to-kitchen-beneath-flat-roof

new-plasterboard-ceiling-in-entrance-to-kitchen-beneath-flat-roof

Day 81 – Friday 28th October 2016

Patio doors for kitchen arrived today

new-patio-doors-in-new-kitchen-from-inside

new-patio-doors-in-new-kitchen-from-inside

new-patio-doors-minus-the-apex-window-on-order-fitted-by-clive-and-chris

New patio doors minus the apex window on order fitted by Clive and Chris

new-patio-doors-to-new-kitchen-from-outside

new-patio-doors-to-new-kitchen-from-outside

new-patio-doors-to-new-kitchen-from-outside-2

new-patio-doors-to-new-kitchen-from-outside-2

Day 82 – Saturday 29th October 2016

Plumber today, connecting up pipework under the house.

new-drainage-pipe-for-a-sink-in-the-utility-room

New drainage pipe for a sink in the utility room and hot and cold water pipes

pipes-for-towel-rail-capped

In new bathroom the pipes-for-towel-rail-capped

pipework-in-place-for-new-bath-in-bathroom

pipework-in-place-for-new-bath-in-bathroom

old-radiator-in-utility-reconnected-now-re-routed-under-house

old-radiator-in-utility-reconnected-now-re-routed-under-house

pipework-through-wall-to-new-kitchen

pipework-through-wall-to-new-kitchen

pipework-for-radiator-under-the-window-in-the-new-kitchen-capped

pipework-for-radiator-under-the-window-in-the-new-kitchen-capped

pipework-capped-ready-for-large-radiator-in-new-kitchen-this-blockwork-was-the-old-small-bedroom-window

pipework-capped-ready-for-large-radiator-in-new-kitchen-this-blockwork-was-the-old-small-bedroom-window

Day 83 – Monday 31st October 2016

back-right-kitchen-corner-now-plasterboarded

back-right-kitchen-corner-now-plasterboarded

double-plasterboarding-under-lintel

double-plasterboarding-under-lintel

front-right-kitchen-corner-now-plasterboarded

front-right-kitchen-corner-now-plasterboarded

utility-room-now-plasterboarded

utility-room-now-plasterboarded

Day 84 – Tuesday 1st November 2016

foil-insulation-going-into-sloping-roof-of-kitchen

foil-insulation-going-into-sloping-roof-of-kitchen

foil-insulation-in-kitchen

foil-insulation-in-kitchen

wiring-holes-in-plasterboard

wiring-holes-in-plasterboard

wiring-through-plasterboard-ceiling

wiring-through-plasterboard-ceiling

ridge-tiles-nearing-completion

ridge-tiles-nearing-completion

Day 85 – Wednesday 2nd November 2016

foil-insulation-in-corner-of-kitchen

foil-insulation-in-corner-of-kitchen

foil-insulation-in-left-corner-of-kitchen

foil-insulation-in-left-corner-of-kitchen

holes-cut-in-plasterboard-for-lighting-lots-of-it

Holes cut in plasterboard for lighting – lots-of-it!

Day 86 – Thursday 3rd November 2016

new-bathroom-plasterboarding-double-in-places-to-fill-gaps

new-bathroom-plasterboarding-double-in-places-to-fill-gaps

new-bathroom-plasterboarding

new-bathroom-plasterboarding

new-door-frame-around-new-bathroom-door-picture-2

new-door-frame-around-new-bathroom-door-picture-2

new-door-frame-around-new-bathroom-door

new-door-frame-around-new-bathroom-door

new-door-frame-around-new-kitchen-door-top-of-steps

new-door-frame-around-new-kitchen-door-top-of-steps

Day 87 – Friday 4th November 2016

plasterboarding-in-new-bathroom-beam-boxed-in

Plasterboarding in new bathroom – old beam boxed in

plasterboarding-new-bathroom-beam-boxed-in

plasterboarding-new-bathroom-beam-boxed-in

plasterboarding-in-utility

plasterboarding-in-utility

Day 88 – Monday 7th November 2016

new-step-into-new-bathroom

New step built into new bathroom

plasterboard-and-plastering-around-new-doorway-into-new-bathroom

plasterboard-and-plastering-around-new-doorway-into-new-bathroom

kitchen-at-present

kitchen-at-present

my-bread

Made Cotswold Crunch bread whilst waiting for the plumber!

Day 89 – Wednesday 9th November 2016

new-loft-area-over-new-kitchen

new-loft-area-over-new-kitchen

new-loft-area-over-new-kitchen-pic2

new-loft-area-over-new-kitchen-pic2

new-loft-area-over-new-kitchen-pic3

new-loft-area-over-new-kitchen-pic3

new-loft-area-from-new-kitchen-to-old-existing-roof

new-loft-area-from-new-kitchen-to-old-existing-roof

mess-after-holes-drilled-for-new-doorway-from-hall-to-new-kitchen

mess-after-holes-drilled-for-new-doorway-from-hall-to-new-kitchen

holes-in-wall-ready-for-doorway-to-be-cut-through-pic-3

holes-in-wall-ready-for-doorway-to-be-cut-through-pic-3

holes-in-wall-ready-for-doorway-to-be-cut-through-pic-2

holes-in-wall-ready-for-doorway-to-be-cut-through-pic-2

holes-in-wall-ready-for-doorway-to-be-cut-through

holes-in-wall-ready-for-doorway-to-be-cut-through

Day 90 – Thursday 10th November 2016

blanket-insulation-in-sloping-roof-covered-by-plasterboard

blanket-insulation-in-sloping-roof-covered-by-plasterboard

close-up-of-blanket-insulation-above-patio-doors

close-up-of-blanket-insulation-above-patio-doors

view-through-new-kitchen-patio-windows-up-the-hillside-lovely-autumnal-day

view-through-new-kitchen-patio-windows-up-the-hillside-lovely-autumnal-day

Day 91 – Friday 11th November 2016

New Triangular Shaped glass, made to measure went in today over patio doors.  Also plaster boarding above hip roof inside new kitchen now finished.

new-kitchen-plaster-board-completed-above-hip-roof

Plasterboarding over the hip roof around patio doors now complete

plaster-board-complete-in-new-kitchen-over-hip-roof

plaster-board-complete-in-new-kitchen-over-hip-roof

patio-doors-and-triangular-glass-fitted-above

patio-doors-and-triangular-glass-fitted-above

new-patio-doors-with-triangular-window-fitted-above

new-patio-doors-with-triangular-window-fitted-above

new-triangular-window-over-patio-door

new-triangular-window-over-patio-door

Day 92 – Monday 14th November 2016

The break through into the house.

breaking-out-of-the-hall-into-the-new-itchen

breaking-out-of-the-hall-into-the-new-kitchen

doorway-knocked-through-to-kitchen

doorway-knocked-through-to-kitchen

finally-a-link-to-the-new-kitchen

finally-a-link-to-the-new-kitchen

new-doorway

new-doorway

Day 93 – Tuesday 15th November 2016

Then and Now

block-wall-between-bedroom-and-new-kitchen-window-will-be-removed-next-week

28th September this is what the wall looked like!

new-kitchen-with-dot-and-dab-plaster-board-all-finished-ready-for-plasterer

Today 15th November wall looks like this New Kitchen wall finished with dot and dab plaster board technique, ready for plasterer

Installation of block and beam 6

Window to left of wheel barrow is now the doorway in the next picture. This photo taken on 26th July 2016.

new-doorway-into-hall-plasterboarded-ready-for-plasterer

New doorway into main house, with frame and plasterboard surround ready for plasterer.  This was the small window in the photo above.

old-window-position-from-main-bedroom-to-outside-now-bricked-up-new-kitchen-on-the-other-side-see-picture-1-above

old-window-position-from-main-bedroom-to-outside-now-bricked-up-new-kitchen-on-the-other-side

What it used to look like below

View from bedroom

Before being bricked up – 29th August 2016

Day 94 – Wednesday 16th November 2016

Plasterer in new kitchen today

plastering-along-back-wall-of-kitchen-adjacent-to-2-doorways

Plastering along the back wall of the kitchen adjacent to the two doorways

plastering-along-wall-adjacent-to-garage

Plastering along the wall adjacent to the garage. All the kitchen units are planned for this area

plastering-along-wall-where-fridge-freezer-will-sit-hence-high-plug-sockets-easy-to-turn-on-and-off-for-defrosting

plastering-along-wall-where-fridge-freezer-will-sit-hence-high-plug-sockets-easy-to-turn-on-and-off-for-defrosting

plastering-on-right-hand-side-of-patio-doors

plastering-on-right-hand-side-of-patio-doors

ceiling-plastered-between-2-doorways

ceiling-plastered-between-2-doorways

Day 95 – Thursday 17th November 2016

large-wall-adjacent-to-main-bedroom-now-plastered

large-wall-adjacent-to-main-bedroom-now-plastered

large-wall-adjacent-to-main-bedroom-now-plastered-pic-2

large-wall-adjacent-to-main-bedroom-now-plastered-pic-2

plasterers-van

Plasterer’s van

sloping-ceiling-to-new-kitchen-plastered

sloping-ceiling-to-new-kitchen-plastered

utility-room-ceiling-plastered

utility-room-ceiling-plastered

new-bathroom-ceiling-partly-plastered

new-bathroom-ceiling-partly-plastered

Day 96 – Friday 18th November 2016

Wall beside patio – preparation and rebuild of existing wall.  Also plastering progress in new bathroom and kitchen.

bathroom-plastering

bathroom-plastering

bathroom-plastering-2

bathroom-plastering-2

sloping-ceiling-to-new-kitchen

sloping-ceiling-to-new-kitchen

plaster-around-ceiling-in-new-kitchen

plaster-around-ceiling-in-new-kitchen

wall

Rebuild of old wall in front of patio

wall-3

Old wall merges into new

wall-2

Five steps are to be constructed here up to patio

Day 97 – Monday 21st November 2016

So wet today – torrential rain all day

Plasterer was off sick and rain stopped play on the wall outside for the builder.

Some architraves around doorways were fixed on and husband started stripping wallpaper in the old bedroom which is now a bathroom.

architraves-around-doorway

architraves-around-doorway

removing-wallpaper

Removing old wallpaper

Day 98 – Tuesday 22nd November 2016

delivery-of-chippings-10-tons-for-bottoming-under-new-patio

delivery-of-chippings-10-tons-for-bottoming-under-new-patio

delivery-of-chippings-10-tons-for-bottoming-under-new-patio-pic-2

delivery-of-chippings-10-tons-for-bottoming-under-new-patio-pic-2

delivery-of-chippings-10-tons-for-bottoming-under-new-patio-pic-3

delivery-of-chippings-10-tons-for-bottoming-under-new-patio-pic-3

delivery-of-chippings-10-tons-for-bottoming-under-new-patio-pic-4

delivery-of-chippings-10-tons-for-bottoming-under-new-patio-pic-4

delivery-of-chippings-10-tons-for-bottoming-under-new-patio-dumped-on-drive

delivery-of-chippings-10-tons-for-bottoming-under-new-patio-dumped-on-drive

chippings-used-right-along-the-back-of-the-house-in-preparation-for-new-slabs-being-laid

chippings-used-right-along-the-back-of-the-house-in-preparation-for-new-slabs-being-laid

chippings-used-at-the-back-of-the-kitchen

chippings-used-at-the-back-of-the-kitchen

first-coat-of-paint-over-plaster-in-kitchen-watered-down-so-it-does-nor-flake-when-second-coat-is-applied

first-coat-of-paint-over-plaster-in-kitchen-watered-down-so-it-does-nor-flake-when-second-coat-is-applied

first-coat-of-watered-down-paint-applied-but-ceiling-not-plastered-yet-so-no-painting-higher-up

first-coat-of-watered-down-paint-applied-but-ceiling-not-plastered-yet-so-no-painting-higher-up

kitchen-painting

kitchen-painting

painting-at-the-back-of-kitchen

painting-at-the-back-of-kitchen

Day 99 – Wednesday 23rd November 2016

Amazing pictures of our plasterers on stilts!!!

a-lot-of-workmen-this-morning-builder-2-plasterers-and-guy-to-do-fibre-glass-roof-repair

a-lot-of-workmen-this-morning-builder-2-plasterers-and-guy-to-do-fibre-glass-roof-repair

Quite funny really, had  a Viv, a Matt, and a Tom working here today! All names of family members!

plasterers-on-stilts-skimming-the-very-high-ceiling-this-was-amazing

plasterers-on-stilts-skimming-the-very-high-ceiling-this-was-amazing

plasterers-at-work-on-stilts

plasterers-at-work-on-stilts

plasterers-at-work-on-stilts-3

plasterers-at-work-on-stilts-3

plasterers-at-work-on-stilts-2

plasterers-at-work-on-stilts-2

base-for-steps-laid

base-for-steps-laid

bottoming-for-patio-slabs-to-be-laid-on

bottoming-for-patio-slabs-to-be-laid-on

Day 100 – Thursday 24th November 2016

Plastering and outside work on new patio

back-of-ne-kitchen

Back of new kitchen and Bedroom – scaling all levelled

walkway-between-garage-and-new-kitchen-stones-laid-to-form-a-ramp

walkway-between-garage-and-new-kitchen-stones-laid-to-form-a-ramp

plaster-repaired-around-new-doorway-entrance-to-kitchen-from-corridor

plaster-repaired-around-new-doorway-entrance-to-kitchen-from-corridor

ceiling-in-new-bathroom-now-totally-replastered

ceiling-in-new-bathroom-now-totally-replastered

new-small-bedroom-converted-from-sauna-last-year-walls-prepared-and-patched-ready-for-skim-coat-of-plaster

new-small-bedroom-converted-from-sauna-last-year-walls-prepared-and-patched-ready-for-skim-coat-of-plaster

new-small-bedroomblurred-picture-no-light-walls-prepared-for-plastering

new-small-bedroom blurred-picture-no-light-walls-prepared-for-plastering

hip-roof-area-plastered-inside

hip-roof-area-plastered-inside

new-kitchen-ceiling-plaster-starting-to-dry-out-slowly

new-kitchen-ceiling-plaster-starting-to-dry-out-slowly

utility-area-ceiling-painted

utility-area-ceiling-painted

utility-area-wall-and-ceiling-painted

utility-area-wall-and-ceiling-painted

Day 101 – Friday 25th November 2016

steps-up-to-patio-from-new-patio-area-taking-shape

steps-up-to-patio-from-new-patio-area-taking-shape

another-view-of-step-progress-up-to-patio

another-view-of-step-progress-up-to-patio

new-bedroom-plastered-now-drying-out

new-bedroom-plastered-now-drying-out

new-bedroom-plastered-now-drying-out-pic-3

new-bedroom-plastered-now-drying-out-pic-3

new-bedroom-plastered-now-drying-out-pic-2

new-bedroom-plastered-now-drying-out-pic-2

wills-helping-out-drying-the-plaster-on-ceiling-ready-for-painting

wills-helping-out-drying-the-plaster-on-ceiling-ready-for-painting

new-kitchen-with-1st-coat-of-paint-on-ceiling

new-kitchen-with-1st-coat-of-paint-on-ceiling

painted-kitchen-another-coat-to-go

painted-kitchen-another-coat-to-go

kitchen-with-another-coat-of-paint

kitchen-with-another-coat-of-paint

hip-roof-plaster-now-drying-out

hip-roof-plaster-now-drying-out

laminate-flooring-for-kitchen-delivered

laminate-flooring-for-kitchen-delivered

Day 102 – Saturday 26th November 2016

Kitchen delivered! Painting continues and the first internal door is fitted!

kitchen-delivery-from-wrens-pic-2

The kitchen has arrived all the way from Hull

kitchen-delivery-from-wrens-pic-3

Wrens Kitchens

kitchen-delivery-from-wrens-pic-4

Delivery vehicle just about got up the driveway. Had to back up the road

kitchen-delivery-from-wrens-pic-5

kitchen-delivery-from-wrens

kitchen-delivery-from-wrens-pic-6

kitchen-delivery

kitchen-delivery-from-wrens

Kitchen in Kitchen!

new-door-to-hall-from-new-kitchen

The first internal door to be fitted from new kitchen to hallway.

Day 103 – Sunday 27th November 2016

new-laminate-floor-sample

Close up of laminate for new kitchen floor

tony-laying-the-laminate-flooring

Tony laying the laminate flooring on a layer of underlay

progress-of-laminate-floor

Progress of laminate floor so far

paul-painting-another-coat-to-utility-ceiling

Paul-painting-another-coat-to-utility-ceiling before electrician on Monday

paul-painting-another-coat-to-utility-ceiling-pic-2

Utility area painting

Day 104 – Monday 28th November 2016

Electrician in today wiring up all sockets in the kitchen ready for the power switch on, later this week!  Also builder finishing brick work on steps to main patio.

brickwork-for-steps-up-to-main-patio-now-finished-new-indian-sandstone-slabs-to-be-put-on

brickwork-for-steps-up-to-main-patio-now-finished-new-indian-sandstone-slabs-to-be-put-on

steps-beside-side-kitchen-window-base-prepared-and-protected-from-frost

steps-beside-side-kitchen-window-base-prepared-and-protected-from-frost

new-plug-sockets-in-small-bedroom-prepared-no-electrics-in-here-before-as-this-was-a-bathroom

new-plug-sockets-in-small-bedroom-prepared-no-electrics-in-here-before-as-this-was-a-bathroom

plug-sockets-wired-up-in-small-bedroom-after-plastering

plug-sockets-wired-up-in-small-bedroom-after-plastering

Day 105 – Tuesday 29th November 2016

Temperatures below zero today, -5C.  No work on the wall, steps or slabs. Tap outside frozen. New little bedroom painted with first coat of paint over  newly plastered walls.

base-for-new-step-beside-kitchen-window-no-work-on-it-today-due-to-temps-below-zero-5-c-this-morning

base-for-new-step-beside-kitchen-window-no-work-on-it-today-due-to-temps-below-zero-5-c-this-morning

new-small-bedroom-with-first-coat-of-paint

new-small-bedroom-with-first-coat-of-paint

Day 106 – Wednesday 30th November 2016

steps-with-cut-indian-sandstone-slabs-too-cold-for-laying

Steps with Indian Sandstone slabs placed on- all have been cut to size today but too-cold-for-laying

steps-with-cut-indian-sandstone-slabs-side-steps-to-main-patio

Steps with -Indian-sandstone-slabs, cut today, up the new side-steps-to-main-patio

view-from-main-patio-along-back-of-house-slabs-cut-ready-for-laying

view-from-main-patio-along-back-of-house-slabs-cut-ready-for-laying

slabs-cut-at-side-of-house

slabs-cut-at-side-of-house

some-of-16-lights-installed-in-kitchen-ceiling

some-of-16-lights-installed-in-kitchen-ceiling

Day 107 – Thursday 1st December 2016

new-lights-in-kitchen

We have lights! In new kitchen

new-lights-in-kitchen-pic-3

new-lights-in-kitchen-pic-3

new-lights-in-kitchen-pic-2

new-lights-in-kitchen-pic-2

lights-now-connected-in-new-kitchen

lights-now-connected-in-new-kitchen

lights-in-utility-room-this-is-a-great-light-has-an-occupancy-sensor-so-light-comes-on-immediately-on-entering-from-which-ever-of-the-4-doors-you-come-through

lights-in-utility-room-this-is-a-great-light-has-an-occupancy-sensor-so-light-comes-on-immediately-on-entering-from-which-ever-of-the-4-doors-you-come-through

Day 108 – Friday 2nd December 2016

steps-to-patio-slabs-cut-and-laid-waiting-to-be-fixed-when-weather-is-above-freezing

steps-to-patio-slabs-cut-and-laid-waiting-to-be-fixed-when-weather-is-above-freezing

slabs-cut-for-patio-indian-sandstone-all-vary-in-colou-creating-a-patterned-effect

slabs-cut-for-patio-indian-sandstone-all-vary-in-colour-creating-a-patterned-effect

Day 109 – Saturday 3rd December 2016

patio-with-slabs-cut-ready-to-be-secured

patio-with-slabs-cut-ready-to-be-secured

inside-of-hip-roof-now-painted-twice

inside-of-hip-roof-now-painted-twice

bathroom-ceiling-now-painted-for-a-3rd-time

bathroom-ceiling-now-painted-for-a-3rd-time

Day 110 – Sunday 4th December 2016

view-of-flooring-from-window-new-units-in-centre

view-of-flooring-from-window-new-units-in-centre – Flooring now finished

flooring-finished-new-kitchen-units-now-sitting-in-centre-of-kitchen-whilst-floor-is-laid

flooring-finished-new-kitchen-units-now-sitting-in-centre-of-kitchen-whilst-floor-is-laid

hatch-put-in

hatch-put-in Access to roof space

slabs-now-being-cemented-into-place-for-new-patio-at-back-of-new-kitchen

slabs-now-being-cemented-into-place-for-new-patio-at-back-of-new-kitchen

Day 111 – Monday 5th December 2016

Delivery of kitchen unit to replace damaged one. Step at side of kitchen window put in.  Plasterers/roughcast guys returned to put metal and wood edgings on new walls, in preparation for scratch coat

new-bathroom-suite-arrived-today-for-new-downstairs-family-bathroom

new-bathroom-suite-arrived-today-for-new-downstairs-family-bathroom

view-from-bathroom-to-utility-no-door-on-yet

view-from-bathroom-to-utility-no-door-on-yet

3-shower-boards-1-shower-screen-and-heated-towel-rail

3-shower-boards-1-shower-screen-and-heated-towel-rail

ramp-and-walkway-between-garage-and-new-kitchen-now-built-up-wall-completed-to-tie-in-with-existing-wall

ramp-and-walkway-between-garage-and-new-kitchen-now-built-up-wall-completed-to-tie-in-with-existing-wall

battening-and-metal-strips-now-in-place-for-rough-casting-of-bricks-on-new-extension

battening-and-metal-strips-now-in-place-for-rough-casting-of-bricks-on-new-extension

new-side-step-to-back-of-garage

new-side-step-to-back-of-garage

Day 112 -Tuesday 6th December 2016

Aco drains

aco-drains-put-in-today-down-the-side-of-the-garage-ground-built-up-to-provide-a-downward-flow-and-ramp-away-from-house-and-to-stop-water-going-into-the-garage

aco-drains-put-in-today-down-the-side-of-the-garage-ground-built-up-to-provide-a-downward-flow-and-ramp-away-from-house-and-to-stop-water-going-into-the-garage

aco-drain-down-side-of-garage

aco-drain-down-side-of-garage

view-of-aco-drain-from-back-of-new-kitchen

view-of-aco-drain-from-back-of-new-kitchen

Day 113 – Wednesday 7th December 2016

walkway-between-new-kitchen-an-garage-slabs-being-laid-also-scratch-coat-on-new-kitchen-outside-wall

Pathway between new kitchen and garage. Slabs being laid. Also scratch coat on new kitchen wall has been applied.

boards-up-to-stop-us-treading-on-freshly-laid-slabs

boards-up-to-stop-us-treading-on-freshly-laid-slabs

main-steps-to-garden-from-new-kitchen-partially-laid

main-steps-to-garden-from-new-kitchen-partially-laid

scratch-coat-on-walls-and-more-freshly-laid-slabs

scratch-coat-on-walls-and-more-freshly-laid-slabs

scratch-coat-on-outside-of-walls-of-kitchen-back-and-sides

scratch-coat-on-outside-of-walls-of-kitchen-back-and-sides

scratch-coat-on-outside-of-new-back-of-kitchen

scratch-coat-on-outside-of-new-back-of-kitchen

Day 114 – Friday 9th December 2016  (no work carried out on Thursday)

path-between-garage-and-new-kitchen-slabs-cut

Path between garage and kitchen. More Indian Sandstone slabs were delivered and have been cut.

path-between-garage-and-new-kitchen-from-back-to-front-of-house

path-between-garage-and-new-kitchen-from-back-to-front-of-house

progress-of-patio-at-back-of-kitchen

progress-of-patio-at-back-of-kitchen

Day 115 – Saturday 10th December 2016

Assembly of kitchen units begins.  This will not be completed till after Christmas.

base-kitchen-units-going-into-place

Base Kitchen Units going into place along with dishwasher

tall-kitchen-cabinet-and-base-kitchen-units-going-into-place

tall-kitchen-cabinet-and-base-kitchen-units-going-into-place

Days 116 and 117 December 12th and 13th 2016

plumber-has-now-installed-2-radiators-in-kitchen-very-warm-now

Plumber has now installed 2 radiators in kitchen very warm now

2nd-radiator-on-back-wall-of-kitchen

2nd-radiator-on-back-wall-of-kitchen

c

Final slabs cut on Monday and cemented in Tuesday, still to be jointed

final-patio-slabs-cut-on-monday-and-cemented-in-tuesdaypic-2

final-patio-slabs-cut-on-Monday-and-cemented-in-Tuesday

Days 118, 119 and 120 – 14th, 15th, 16th December 2016

new-bathroom-wood-floor-laid-first

New family bathroom – Old doorway from old bedroom to hall now plaster boarded over. Then new bathroom floor is laid. First a wooden flooring is laid and marked with a grid.

grid-pattern-marked-out-on-wood-flooring

grid-pattern-marked-out-on-wood-flooring

new-bathroom-wood-screwed-down-in-a-grid-pattern-to-ensure-tiles-will-be-laid-on-a-solid-base

new-bathroom-wood-screwed-down-in-a-grid-pattern-to-ensure-tiles-will-be-laid-on-a-solid-base

new-bath-in-place

New bath in place

close-up-of-tiles-in-new-bathroom

close-up-of-tiles-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

walkway-up-between-garage-and-new-kitchen-slabs-have-been-jointed-filled-between-each-slab

walkway-up-between-garage-and-new-kitchen-slabs-have-been-jointed-filled-between-each-slab

view-from-main-patio-of-new-patio

view-from-main-patio-of-new-patio

slabs-laid-on-steps-not-cemented-between-slabs-yet

slabs-laid-on-steps-not-cemented-between-slabs-yet

patio-behind-house-now-all-finished-cement-between-slabs-jointing

patio-behind-house-now-all-finished-cement-between-slabs-jointing

Day 121 – Monday 19th December 2016

newly-tiled-bathroom

Newly tiled bathroom

progress-in-new-bathroom-shower-bords-up-bath-fitted-shower-fitted

progress-in-new-bathroom-shower-boards-up-bath-fitted-shower-fitted

view-of-bath-shower-shower-board-and-tiles

view-of-bath-shower-shower-board-and-tiles

Bath filled with water whilst it sets in place.  This will prevent movement of bath when using shower and bath.

Day 122 – Tuesday 20th December 2016

new-bath-and-shower

New Bath and Shower

new-bathroom-and-towel-rail

New family bathroom with towel radiator toilet and sink

toilet-and-wash-hand-basin

toilet-and-wash-hand-basin

Day 123 – Thursday 22nd December 2016

new-door-for-new-bathroom-too-big-has-to-be-cut

New door for bathroom too tall, cut to fit

Kitchen fitting over Christmas holiday

tv-fitting

tv-fitting

tv-fitting-1

Smart TV

paul-and-tony-fitting-kitchen-2

Kitchen unit and island assembly

paul-and-tony-fitting-kitchen

The mobile island!

high-gloss-wall-cabinets

High Gloss Wall Cabinets from Wrens Kitchens

wall-units-and-base-units-now-fitted-measurements-can-now-be-taken-for-worktops

wall-units-and-base-units-now-fitted-measurements-can-now-be-taken-for-worktops

wall-units

Wall and Base units

Day 124 – Tuesday 3rd January 2017

Delivery of new dual fuel RangeMaster cooker 1100

rangemaster-cooker-delivery-3-1-17

rangemaster-cooker-delivery-3-1-17

kitchen-3-1-17

kitchen-3-1-17

kitchen-3-1-17-b

kitchen-3-1-17 before delivery of cooker

rangemaster-arrives-3-1-17

rangemaster-arrives-3-1-17

rangemaster-132kg

rangemaster-132kg

Day 128 also -Wednesday 11th January 2017 – phase 1

outside-of-kitchen-has-had-more-layers-of-roughcast-added

outside-of-kitchen-has-had-more-layers-of-roughcast-added

roughcast-on-outside-of-kitchen

roughcast-on-outside-of-kitchen

scratch-coat-on-walls-and-more-freshly-laid-slabs

From the scratch-coat-on-walls-to a smooth coat as below

roughcast-outside-patio-doors-of-kitchen

roughcast-outside-patio-doors-of-kitchen

Part of phase 1 being completed, the outside rendering of the new kitchen, Friday 20th January  Day 135  and Saturday 21st January day 136

new-tyrolean-render-applied-today

new-tyrolean-render-applied-today

new-tyrolean-render-applied-side-of-new-kitchen

new-tyrolean-render-applied-side-of-new-kitchen

Day 137 – Sunday 22nd January 2017 – back to phase 1 – near completion of the new family bathroom

Fitments all in place, door needs painting or varnishing and also handle required.

Interesting to compare it with how it used to look in September 2016.  See the transformation below.

saturday-3rd-september-small-bedroom-roof-leaked-badly-tiles-have-been-removed

Small bedroom to new bathroom

wet-room-roof-leaking-again

small bedroom

rubble-to-be-removed-from-old-bedroom

rubble-to-be-removed-from-old-bedroom

old-bedroom-cleared-of-rubble-and-window-removed

old-bedroom-cleared-of-rubble-and-window-removed

drilling-and-loosening-brick-work-in-new-doorway-before-inserting-2-new-lintels

drilling-and-loosening-brick-work-in-new-doorway-before-inserting-2-new-lintels

new-doorway-cut-into-old-bedroom-which-will-be-new-bathroom-picture-taken-from-utility-side

new-doorway-cut-into-old-bedroom-which-will-be-new-bathroom-picture-taken-from-utility-side

marcus-the-plumber-in-a-very-tight-spot-under-the-floor-in-the-new-bathroom

Spot Marcus, our plumber, in a very tight spot, under the floor in the new bathroom

new-bathroom-pipework-for-shower

new-bathroom-pipework-for-shower

plasterboarding-new-bathroom-beam-boxed-in

plasterboarding-new-bathroom-beam-boxed-in

new-bathroom-wood-floor-laid-first

New family bathroom Old doorway from old bedroom to hall now plaster boarded over. Then new bathroom floor is laid. First a wooden flooring is laid and marked with a grid.

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

some-floor-tiles-and-wall-tiles-laid-in-new-bathroom

progress-in-new-bathroom-shower-bords-up-bath-fitted-shower-fitted

progress-in-new-bathroom-shower-boards-up-bath-fitted-shower-fitted

new-family-bathroom-picture-2

New Family Bathroom

new-family-bathroom

New Family bathroom – right hand side

new-family-bathroom-picture-3

new-family-bathroom-picture-3

Day 145 – Tuesday 31st January 2017 – phase 1+2

Roof tiles all stripped off today under supervision from bat licensed ecologist. Balcony window taken out and flat roof taken off.  From phase 1, worktop for new kitchen which had been measured and cut to size has now been fitted.

newly-fitted-worktop-for-kitchen-and-island-unit

newly-fitted-worktop-for-kitchen-and-island-unit

new-worktop-fitted

New worktop fitted – a transformation

Day 149 – Monday 6th February 2017 – phase 1 – kitchen

new-under-cupboard-unit-lighting-in-new-kitchen-cooker-hob-still-to-be-connected-to-the-gas

New under kitchen unit lighting. Kitchen cooker hob still to be connected to the gas supply. Our electrician came up trumps with the lighting! So pleased with it – it is so smart! All electrical work in the kitchen completed by Ballan Electrical Ltd. First Class job!

new-under-cupboard-unit-lighting-in-new-kitchen

new-under-cupboard-unit-lighting-in-new-kitchen

new-under-cupboard-unit-lighting

new-under-cupboard-unit-lighting –  Kitchen not quite completed  – More photos soon

Weekend work – Sunday 5th March 2017 – phase 1

Phase 1 work this weekend – Tony (brother-in-law) has fitted handles to bathroom and kitchen door and has begun to tile the kitchen (white tiles!)

Phase 2 work this weekend – Paul has been working on the upstairs, beginning the painting of the ceiling in the new upstairs bedroom in readiness for Joe to return and fit the lights.

Handles to door to utility and new family bathroom fitted by Tony

Handles now in place on door to kitchen from utility and door to new family bathroom. Fitted by Tony

The start of the tiling in the new kitchen - thanks Tony!

The start of the tiling in the kitchen – thanks Tony!

This is what is called 'Buttering of tiles'

This is what is called the ‘back buttering’ of tiles. It ensures a thin even coverage of the cement

New white tiles for a new white kitchen

New white tiles with spacers

Tiling starts from the centre of the cooker and works out the way in both directions

Tiling starts from the centre of the cooker and works out the way in both directions

Spirit levels are essential

Spirit levels are essential

tiling in new kitchen

tiling in new kitchen

tiling in new kitchen pic 2

tiling in new kitchen pic 2

More photos soon when tiling is complete and grouting done.

11th and 12th March – Weekend Work

Tiles above cooker before being grouted

Tiles above cooker before being grouted

Tiles after the grouting in kitchen

Tiles after the grouting in kitchen

Tiling and grouting all completed, thanks Tony!

Tiling and grouting all completed, thanks Tony!

Kitchen ready to use

Kitchen ready to use

Kitchen finished! Just need to fill cupboards now!

Kitchen finished! Just need to fill cupboards now!

Island unit for all our baking needs!

Island unit for all our baking needs!